Day v. Pennsylvania Railroad

35 Pa. Super. 586 | Pa. Super. Ct. | 1908

Opinion by

Morrison, J.,

This is an appeal by the Pennsylvania Railroad Company, owner, from a judgment on a sci. fa. sur mechanic’s lien in favor of the appellee, a subcontractor. Seeley, Son & Company entered into a contract with the appellant for the erection and construction of a grain elevator. The structure was to be equipped with a certain patented device known as a “ dust collector.” On February 21, 1903, Seeley, Son & Company entered into a written contract with the appellee for the construction and installation of the dust collector complete for the entire sum of $2,124. The appellee averring that he had completed his contract in accordance with its terms and the specifications referred to in the contract, furnished by George M. Moulton & Company, and that the contractors had neglected and refused to pay him for his work and materials, gave notice to the appellant, in writing, duly sworn to, and served on October 30, 1'903, of his intention to file a mechanic’s lien against said grain elevator, etc., to secure a balance alleged to be due appellee of $940.79. In pursuance of said notice, the appellee filed his lien January 15, 1904. As the claim was filed, appellee claimed the additional sum of $168, as alleged under a verbal modification of the written contract and this sum was included in his lien.

A rule was taken to strike the Jien off and, on argument and consideration, the court below made the rule absolute as to the $168 and discharged it as to the balance.

In the opinion of the court refusing to strike off the lien as filed, under the written contract, some doubt is expressed in regard to the failure of the written notice to refer to and give information as to the George M. Moulton & Company specifications referred to in said contract. The learned court, how*589ever, held the notice sufficient and refused to strike off the lien for that reason.

While we find several reasons alleged by appellant in the statement of questions involved, assignments of error, argument, etc., for reversing the judgment, they all hinge on the question of the validity of the lien. First as to the specifications of George M. Moulton & Company, they were not in terms made a part of the contract between the appellee and Seeley, Son & Company. The recital in the contract is “ with the dust collecting system according to the specifications of George M. Moulton & Company and the following specifications.” We are not fully convinced that the failure to attach to the lien the Moulton & Company specifications and to set them out in the notice was fatal to the lien. But we need not decide that question because the learned court below permitted the lien to be amended and if said specifications were a material part of the lien, the amendment brought them on the record and cured that defect. That the court had power to grant this amendment we think is clear under the fifty-first section of the Act of June 4, 1901, P. L. 431. That this amendment was not made till after trial and verdict, we do not consider material. It was purely technical and upon the facts we do not think it introduced anything new into the case of which the appellant has cause to complain. It is averred, and not denied, that during all the time the work was being done and the litigation carried on, the appellant had possession of the Moulton & Company specifications and the appellee did not have possession or custody of the same or a copy thereof. Moreover, we understand it to be a conceded fact that the appellee completed the dust collector in accordance with his contract and the specifications, and, therefore, we cannot see how it would have benefited the defendant a particle if the Moulton specifications had been attached to the lien and referred to in the notice to the defendants of the appellee’s purpose to file the lien.

It is contended that the lien is bad because it fails to comply with paragraphs 4, 6 and 8 of section 11 of the act of June 4, 1901. (See p. 436.) But when we take into consideration the *590fact that the appellee agreed to construct and install a complete dust collector, which was a patent device composed of various articles of wood, iron, etc., and that the appellant was fully advised of the appellee’s claim by the copy of the contract and specifications attached thereto, and reference to the Moulton specifications contained therein, we are inclined to the opinion that the paragraphs referred to were substantially complied with. We cannot agree with the contention that the appellee was bound to set out an itemized statement of the wood, iron, pipes, nails and other material, which went into the construction of the completed dust collector.

We are of the opinion that the notice of the intention to file a lien, dated October 26, 1903, was a substantial compliance with the act of assembly and under the facts it gave the defendant all the notice required: Section 8, Act of June 4,1901, P. L. 431.

It is admitted that the notice served is in the following form:

"To the Pennsylvania Railroad:

“ I hereby give you notice that I intend to file a mechanic’s lien on the grain elevator and curtilege appurtenant thereto, situate at Germantown Junction, Philadelphia, Pa. The amount due to me is $940.79. My claim arises out of a written contract with Messrs. Seeley, Son & Company, contractors, a copy whereof is hereto attached and made part hereof, my obligations in said contract having been fully performed by me. The said sum is made up of the contract price therein recited, to wit, $2,124 (together with the further sum of $168, as the reasonable cost of testing and altering the work done under the aforesaid contract).

“ There has been paid to me by the contractors the sum of $1,351.21, leaving the aforesaid sum of $940.79 still due and payable to me. The labor and materials furnished for the said grain elevator by me were such as are necessary in the erection of the patented dust collector, which formed the subject matter of the aforesaid contract. The last work done and materials furnished in and about the erection of the said dust collector, were done and furnished August 7, 1903. (Signed) H. L. Day.”

*591This notice was duly sworn to on October 26, 1903, and served on October 30, 1903. When we remember that the appellee’s contract was attached to this notice, and that it simply referred to the specifications of George M. Moulton & Company, and that they were not made a part of the contract, and that they were at all times in the custody of the appellant, we think this notice is sufficient.

The case was tried on its merits rand the jury found, on sufficient evidence, all of the essential facts entitling the appellee to recover. We do not understand it to be contended that the amount of the verdict and judgment is not justly due and owing to the appellee, and it is conceded that he could not collect the same from Seeley, Son & Company.

The most serious question raised at the trial, was whether the dust collector was finished and completed prior to July 30, 1903, or was it not so completed till August 7, 1903. If it was completed at and before the former date, then the sworn statement of notice, served October 30, 1903, was too late and the lien was invalid, but if the work done up till August 7, 1903, was a necessary part of the construction of the dust collector, then the notice was in time and the lien filed in pursuance thereof was valid. This question was squarely raised by points presented by defendant’s counsel, and the jury was carefully instructed as to the law, and that the lien could not be sustained and the verdict must be for the defendant if the work done in August, “was not done in and about the erection and construction of the dust collecting system, but was done in changing or altering the work already done and put in so as to make the system operate as a completed work, then your verdict ought to be for the defendant.” Under the evidence, this question was for the jury: Holden v. Winslow, 18 Pa. 160; Driesbach v. Keller, 2 Pa. 77.

We do not consider the alleged insufficiencies of the notice and claim as presenting any substantial difficulty. “The object of the notice is to inform the owner of the demand and the nature thereof, in order that he may require payment of the contractor, or in default thereof withhold the amount from the contract price:” Thirsk v. Evans, 211 Pa. 239. All *592the cases agree that a substantial compliance is sufficient, and this is shown to exist whenever enough appears on the face of the statement to enable the owner to ascertain the amount of the claim, its date, and the nature and amount of the labor or material out of which it arises: Este v. Penna. R. R. Co., 27 Pa. Superior Ct. 521. In American Car, etc., Co. v. Alexandria Water Co., 215 Pa. 520, a lien was filed by a subcontractor and it was striken off by the court below. In reversing the judgment and reinstating the lien much was said by the Supreme Court that applies to the case in hand (see p. 525): “ But all the cases agree that a substantial compliance is sufficient, and this is shown to exist wherever enough appears, on the face of the statement, to point the way to successful inquiry. Adherence to the terms of the statute is indispensable, but the rule must not be pushed into such niceties as serve but to perplex and embarrass a remedy intended to be simple and summary, without in fact, adding anything to the security of the parties having an interest in the building sought to be incumbered. Certainty to a common intent has, therefore, always been held to suffice.” The doctrine of that case and several others, construing the act of 1901, we think, upholds the lien in the present case. We are at a loss to see what additional knowledge or benefit the appellant would have derived if the court below had required a strict compliance with all of the extremely technical points raised by counsel for appellant. If the court below had adopted the counsels' views and struck the lien off, it would, we think, have been error. It is well to note that this is a contest between the subcontractor and owner, and that no lien creditor is questioning the validity of the mechanic’s lien.

We do not find any reversible error raised by the several assignments and they are all dismissed and the judgment is affirmed.