137 Minn. 352 | Minn. | 1917
Defendant Northwestern Construction Company, a copartnership, contracted with the county of Itasca for the construction of State Road No. 2. Plaintiff, L. W. Dawson, contracted with the construction company to build sections B and C of this road in accordance with the original plans and specifications, except that plaintiff was to receive 30 cents per cubic yard for earth moved 500 feet or less, and one cent per cubic yard for each 100 feet such earth was hauled over 500 feet. These prices were somewhat less than those specified to be received from the county-by the construction company. Plaintiff’s contract provided that the statement of quantities moved and work done made by the engineer in charge at the completion of the work should be final.
The contract for the building of the road was completed December 11, 1915, and. the final estimate of the engineer as to quantities of earth moved and work done by plaintiff Dawson on sections B and C, showed 9,353 cubic yards of grading at 30 cents per cubic yard, amounting to $3,776.05; 1,385,196 cubic yards of overhaul at one cent, amounting to $13,851.96 and extra work amounting to $389.95, making a total for all work done by plaintiff according to the engineer’s estimate of $16,017, of which sum $3,838.70 was paid plaintiff, and the balance is admitted to be due him less certain offsets.
Plaintiff brought this action, alleging that he moved 11,340 cubic yards of earth, at the contract price of 30 cents per yard, that the overhaul amounted to $15,564.84, and the extra work being $389.95 as allowed. He credited the payment of $3,838.70, and demanded judgment for the balance of $15,489.09 with interest. The partnership Northwestern Construction Company, and the individuals composing it, the county of Itasca and its commissioners, and Maryland Casualty Company, were made defendants. On the coming in. of the answer of the county of Itasca and its board of county commissioners, and on the motion of these defendants, the court made an order permitting the county to pay into court the sum of $15,701.05, admitted to be due to the construction company, and substituting as defendants certain corporations and individuals having claims against the fund. These claimants were ordered to file their answers setting forth their claims to the fund within 30 days. The money was paid into court and the county discharged from all liability as ordered. The claimants answered. Insofar as their claims are involved on this appeal we will state what they áre later. Defendant Maryland Casualty Company, the surety on the bond of the construction company, answered the complaint of plaintiff and the claims of the impleaded defendants. The construction company also answered. Plaintiff replied to these answers.
It is sufficient to say, as to the case between plaintiff Dawson and these answering defendants, that the issues made by the pleadings and tried were these: (1) Was plaintiff bound by the statement of earth moved and work done made in the final estimate of the engineer? (3) If
Defendants moved for judgment notwithstanding the verdict or for a .new trial, and appealed from the order denying this motion. The case as between the substituted or impleaded defendants, claimants, and the construction company and casualty company, was tried later before the court without a jury upon the evidence in the case tried by the jury and upon proofs and stipulations as to the respective claims. The court made findings of fact and conclusions of law, adopting the verdict of the jury as to plaintiff’s case, and deciding as to the various claims of the impleaded- defendants as will be hereafter stated. Defendants construction company and casualty company moved for amended findings and conclusions, and for a new trial in the event such motion Was denied. The court amended the findings in certain particulars, but otherwise denied the motion, and the defendants named appealed from the order. There are also appeals by two of the claimants.
We will first consider the case as between plaintiff Dawson and the defendants construction company and casualty company, then the claims of the respective impleaded defendants, claimants against the fund and the bond, and then the claims of the impleaded defendants which were disallowed by the trial court.
I
Plaintiff’s Case.
Was there evidence reasonably tending to show such a gross mistake in the engineer’s estimate as under our decisions removes that bar to plaintiff’s recovery? There is no disagreement as to what the law is. The facts which the evidence tended to establish may be briefly stated as follows:
The discrepancy between the claims of plaintiff as to earth moved and overhaul, and the final estimate of the engineer amounted to more than $3,000. If plaintiff’s claims are correct or substantially so, it necessarily follows that there was a mistake in the engineer’s estimate, and a mistake so gross as to permit recovery for the work actually done notwithstanding the engineer’s estimate and the agreement that it should be final. Practically the entire discrepancy is over the quantities of earth removed from a certain pit, and the overhaul on that earth. This pit, unlike others from which earth was taken for the surfacing of the highway, extended out from the right of way of the road into private property for a considerable distance. The evidence showed that only that part of this pit that lay in the right of way was surveyed and cross-sectioned by the engineer. It warranted the jury in finding that the final estimate of the earth removed from this pit outside of the right of way and the overhaul thereon was at least partly guess work. The evidence was conflicting as to what the contour of the ground was, whether or not there was' a hill, before the earth was removed. It is plain enough that whether there
The witness Hawley stated that the total overhaul, figured in the manner stated, was 1,569,063.9 yards. It is claimed that this is manifestly erroneous, even using Hawley’s factor and his estimate of the quantities moved. This may be true. But if so it was a simple error in multiplication, as clearly discoverable on the trial as afterwards. Counsel did not call attention to this error on the trial. We do not feel that they are fairly entitled to a reversal here on this account.
We see no other points that require mention. In our opinion the evidence justifies the verdict both on the question of mistake and as to the amount of work done by plaintiff under his contract. There were no prejudical errors in the admission of evidence or in the charge, and the verdict must stand.
II
As to the Claimants.
The intervening claimants against the fund and the bond whose claims are involved on this appeal are Jack Riegelsperger, Joseph Gibson Company, First National Bank of Deer River, Nick Nockles, Charles Brown, Henry Mead, all of whose claims were allowed by the trial court, and Engstrom & Hosford and Ord Company, whose claims were allowed in part and disallowed in part.
“For the use of the obligee and of all persons doing work or furnishing skill, tools, machinery, or materiáls under or for the purpose of such contract, conditioned for the payment, as they become due, of all just claims for such work, tools, machinery, skill and materials, for the completion of the contract in accordance with its terms, for saving the obligee harmless from all costs and charges that may accrue on account of the doing of the work” specified.”
The bond by its terms was “for the use of said county, and also for the use of all persons who may perform any work or labor, or furnish any skill or material in the execution of the contract,” etc. The word “tools” is not employed in this “use” clause, but does appear in the condition of the bond, which is that the obligor shall pay, as they become due, “all just claims for all work and labor performed and all skill, tools and material furnished under or for the purpose of, or in the execution of, said contract,” etc. In view of the quoted language of the statute, and the language of the condition clause, it must be held that one furnishing “tools” for the work is entitled to the benefit of the bond. Sepp v. McCann, 47 Minn. 364, 50 N. W. 246.
The claims of Riegelsperger, Joseph Gibson Company, First National Bank of Deer River, Engstrom & Hosford and Ord Company involve the question of whether one renting or furnishing to the original con
Our conclusion, based upon the language of the statute and of the bond, is that the surety is liable for the rental value of horses necessarily used on the work, though the claims did not include the services of teamsters. This would necessarily cover the rental value and cost of repair of harnesses.
What has been said disposes of all the claims of the interpleaded defendants, except those portions of the claims of Engstrom & Hos-
There is a claim that the court erred in finding that plaintiff and the various claimants should share pro rata in the fund deposited in court by the county, and recover the balance of their respective claims from the casualty company. . We do not consider this claim of sufficient merit to require anything further than the expression of our opinion that this could not well prejudice the casualty company and was quite clearly right.
The orders appealed from are affirmed.