Dawson County Public Power District v. City of North PlatteDawson County Public Power District v. City of North Platte
INTRODUCTION
The City of North Platte (North Platte) filed an application with the Nebraska Power Review Board (PRB) to determine how much North Platte must compensate the Dawson County Public Power District (power district) for annexing land in the power district’s service area and supplying electricity to customers there. The PRB determined that North Platte did not have to compensate the power district under
FACTUAL BACKGROUND
The pertinent facts are undisputed and have been agreed upon by the partiеs.
Nevertheless, the power district entered into a contract with Flying J on October 24, 1996. The contract did not require that Flying J actually purchase electricity, only that Flying J would purchase electricity from the powеr district at specified rates if Flying J came to have need for electricity on the tract. The contract stated that it would remain in effect for 5 years after the initial billing period for electricity used by Flying J.
Meanwhile, North Platte continued to encouragе Flying J to build the facilities on the tract, offering various forms of concessions and assistance. For example, in February 1997, North Platte promised Flying J that North Platte would be at least partly responsible for bringing the tract into compliance with federal wetlands lаws and would grant various water and sewer subsidies if Flying J built the facilities there. In return, Flying J promised that construction of the facilities on the tract would be completed by February 1999. Flying J became the owner of the tract on February 25, 1997.
North Platte and the power district continued to negotiate the terms of retiring the power district as the supplier of electricity to the tract and establishing North Platte as such. North Platte and the power district were able to agree on all terms but one, that being whether
The power district maintained that North Platte should compensate the power district fоr 2V2 times that amount ($189,366, rounded down) pursuant to
On December 13,1996, North Platte filed an application with the PRB for authority tо serve the newly annexed area and to transfer facilities and customers. By the time the PRB held a hearing on May 9, 1997, Flying J had not yet purchased electricity from either supplier. After the hearing, the PRB determined that North Platte did not have to compensate thе power district for the potential revenue generated by Flying J. The PRB reasoned that ordering such compensation would be too speculative because Flying J had not begun purchasing power at the time of annexation. As a result, the PRB ordered only thаt North Platte pay to the power district the sum of $11,959 for the reproduction cost of the facilities being
ASSIGNMENT OF ERROR
The power district assigns, restated, that the PRB erred in finding that the total economic impact on the power district from transferring electric customers on the tract to North Platte’s service area did not include the loss оf revenue that would potentially be generated by Flying J, an identified future customer.
STANDARD OF REVIEW
A decision of the PRB will be affirmed if it is supported by the evidence and is not arbitrary, capricious, unreasonable, or otherwise illegal.
In re Application of City of Lexington,
ANALYSIS
(1) The [B]oard shall have authority upon application by a supplier at any time to modify service areas or customers to be served as previously established....
(2) In the evеnt of a proposed transfer of customers and facilities from one supplier to another... the parties shall attempt to agree upon the value of the certified service area and distribution facilities and customers being transferred. If the parties cannot agree upon the value, then the [B]oard shall determine the total economic impact on the selling supplier and establish the price accordingly based on, but not limited to, the following guidelines: The supplier acquiring the certified service area, distribution facilities, and customers shall purchase the electric distribution facilities of the supplier located within the affected area, together with the supplier’s rights to serve within such area, for cash consideration which shall consist of . . . (c) an amоunt equal to two and one-halftimes the annual revenue received from power sales to existing customers of electric power within the area being transferred....
(Emphasis supplied.)
This court interpreted
Nevertheless, we held that the PRB was correct in declining to consider the value of expansion and future customers in the area annexed by the city of Lexington. In re Application of City of Lexington, supra. We rеasoned that such considerations were too speculative given the testimony in that case, which did not specifically identify future customers. Id. The power district contends that by specifically identifying Flying J as a future customer prior to the date of annexation, such a consideration is not too speculative in the instant case. We do not agree.
Of course, the power district is correct in pointing out that the PRB may consider factors other than those listed in
Where statutory construction is called for, a court looks to the statute’s purpose and then construes the statute in a reasonable manner that will best achieve thаt purpose, rather than interpreting the statute in a way that would defeat its purpose.
In re Invol. Dissolution of Battle Creek State Bank,
When North Platte annexed the tract in August 1996, North Platte was not obligated to supply electricity to the area. North Platte could have begun negotiations with the power district after annexation аnd then decided not to supply electricity to the tract if it became apparent that Flying J was not coming or for other economic reasons. By the same token, North Platte could have acquired the service area via a PRB determination before Flying J committed to building the facilities, only to have Flying J decline the entire venture. Under either scenario, the power district would not be entitled to the compensation it now seeks. Therefore, the PRB did not act arbitrarily or capriciously when it did not сonsider other factors in assessing the total economic impact on the power district where those factors addressed potential economic benefits that the power district had not yet, and may never have, realized.
However, the date of annexation, as determined by the PRB, is not the key date to determine valuation for purposes of
The dеtermination of the PRB that the Nebraska Department of Roads was the only existing customer in the area being annexed, pursuant to
CONCLUSION
Accordingly, the order of the PRB is affirmed.
Affirmed.