Davis-Wallbridge, Inc. v. City of SyracuseDavis-Wallbridge, Inc. v. City of Syracuse
OPINION OF THE COURT
Memorandum.
The order of the Appellate Division should be reversed, with costs, and the complaint dismissed.
Defendant City of Syracuse contracted with plaintiff for improvements to a running track in one of its parks. Pursuant to the contract, defendant withheld a sum as liquidated damages when plaintiff failed to complete the work on time. Plaintiff commenced this action to recover the withheld amount.
Plaintiff admits that it failed to comply with the notice of claim provision contained in the Syracuse City Charter (see, § 8-115). It argues, however, that service of a notice of claim was not necessary because it followed the procedure set forth in the contract for presentment of disputes. We disagree. Compliance with the charter’s notice of claim clause, unless waived, is a condition precedent to the commencement of litigation against the City (see, Matter of Geneseo Cent. School [Perfetto & Whalen Constr. Corp.],
Chief Judge Wachtler and Judges Simons, Kaye, Alexander, Hancock, Jr., and Bellacos a concur in memorandum; Judge Titone taking no part.
Order reversed, etc.