. The only question presented in this case is, whether the first lien filed was a good and valid lien. If it was, then within the principle of Mulloy v. Lawrence, 31 Mo. 583, the second lien was a nullity, as the plaintiff could have but one lien for the same demand.

By the mechanics’ lien law applicable to St. Louis county, every person, except the original contractor, who may wish to avail himself of the benefits o£ the act, must give ten days’ notice before the filing of the lien, to the owner or agent of the property on which the lien is sought to be enforced, of his claim. This notice is indispensable, and without it the lien is utterly void.

The first paper filed as a lien being inoperative and not sustained by any statute, the claimant might file another, if the prescribed time had not expired. The second lien being filed within the proper time, and the required notice being given, was sufficient and effective according to law.

The judgment is reversed and the cause remanded.

The other judges concur.

Case Details

Case Name: Davis v. Schuler
Court Name: Supreme Court of Missouri
Date Published: Mar 15, 1866
Citation: 38 Mo. 24
Court Abbreviation: Mo.
AI-generated responses must be verified and are not legal advice.
Your Notebook is empty. To add cases, bookmark them from your search, or select Add Cases to extract citations from a PDF or a block of text.