Whether the judgment should be affirmed Qr not depends upon the solution of three plain propositions: First, did the stipulation in the contract, to deliver the building free of all claims, liens, and charges, preclude respondents from filing a lien to enforce payment of any sum they might be compelled to recover of appellant by action ? Sec-
1. A builder may waive his right to the lien remedy given by statute, and does so by agreeing not to exercise such right. Seeman v. Biemann, 108 Wis. 365, 84 N. W. 490. Such an. agreement may he made by an express stipulation not to file-a lien (Fidelity Mut. L. Asso. v. Jackson, 163 Pa. St. 208, 29 Atl. 883; Schroeder v. Galland, 134 Pa. St. 277, 19 Atl. 632; Benedict v. Hood, 134 Pa. St. 289, 19 Atl. 635; Ballman v. Heron, 160 Pa. St. 377, 28 Atl. 914); or by agreement in form that no lien shall be filed on the building under the lien laws of the state (Seeman v. Biemann, supra); or by an agreement that the builder “will not suffer or permit a lien to be filed” (Scheid v. Rapp, 121 Pa. St. 593, 15 Atl. 652); or by the giving of a bond by the builder that no lien shall be filed on the building (Pinning v. Skipper, 71 Md. 347, 18 Atl. 659); or in any other way clearly showing such to be the intention of the parties. But where the terms of a contract are ambiguous on the question, the doubt should be resolved against the waiver, since it should be presumed, in the absence of clear evidence to the contrary, that one has not disabled himself from the use of so valuable a privilege as that given by statute for the enforcement of a builder’s rights in the circumstances involved in such a case as this. The stipulation here was for the delivery of the building, “free from all claims, liens, and charges” on or before November 1, 1900, etc. Payment of the contract price was agreed to be on monthly estimates made by the architect, less fifteen per cent., which reserved amount it was stipulated should be .paid when the contract was completed and the architect satisfied that the building was in fact free from all
2. In support of the court’s ruling that the provision of the contract in regard to forfeiting claims for additions to the contract work and material, was waived, counsel for respondents suggest that such a provision can be waived, and cite Bannister v. Patty’s Ex’rs, 85 Wis. 215. True, such a
3. Much of what has-been said on the second proposition applies to the third. The court found that the architect acted arbitrarily to the extent of perpetrati»g a fraud on respondents, because he did not consider the conditions which caused the delay in the completion of the building, in making the certificate. Tie followed, however, the terms of the contract. That in effect expressly provided that no claims for extra time to complete the structure should be allowed on account of any of the hindrances which respondents insisted in fact delayed them, unless at the time of such hindrances written notice should be given to- the architect and he should then pass upon the same, making an allowance for additional time on account thereof. Ho such notice was given or allowance made. Hence the architect, when he came to make the certificate, had no right to consider any such interference. The learned court disregarded the certificate because he complied with the contract in making it. If he had not done so, it would have been the duty of the court to disregard the certificate in favor of the appellant. We are unable to see in the evidence or in the reasons assigned by counsel for respondents, any justification for holding that the certificate was other than just what the contract contemplated should be made under the circumstances.
A provision of the kind under consideration must not be set aside because it seems harsh. Parties have a perfect right to make harsh provisions in .their contracts if they see fit.
Stipulations of the kind under consideration are uniformly enforced, there being no clear evidence of fraud or wrong equivalent thereto, or mutual mistake in the execution, or clear case of waiver. Baasen v. Baehr, 7 Wis. 516; Hudson v. McCarlney, 33 Wis. 331; Wendt v. Vogel, 87 Wis. 462, 58 N. W. 764; Forster L. Co. v. Atkinson, 94 Wis. 578, 69 N. W. 347; Boden v. Maher, 95 Wis. 65, 69 N. W. 980; John Pritzlaff H. Co. v. Berghoefer, 103 Wis. 359, 79 N. W. 564; Coorsen v. Ziehl, 103 Wis. 381, 79 N. W. 562; Ashland L., S. & C. Co. v. Shores, 105 Wis. 122, 81 N. W. 136.
From the foregoing it will be seen that the trial court should have determined the damages sustained by the respondents’ breach of contract in not finishing the building on time. The claims for damages were: .first, the stipulated damages of $20 per day; second, expenses of a superintendent during the period of delay; third, damages caused by injury to the building itself by reason of work being done during the winter season which was intended to be done in warm weather. It is considered that all elements of damages suggested, which would be recoverable under any circumstances, fall within those intended to be compensated for by the stipulated damages of $20 per day, if the contract provision in that regard is to be taken literally, and we think it is.
Of course, whether a provision in a contract for liquidated damages is to be enforced literally is to be determined by the intention of the parties to be read out of the language used by them, in the light of all the circumstances and some arbitrary judicial rules well established for that purpose. Such rules are peculiar. They are not very philosophical, nor con-, sistent with legal principles generally, but nevertheless are
“Parties may contract for stipulated dama'ges at their pleasure, but such damages only as the law says are liquidated according to the artificial rules which have been adopted to justify courts in saying what the parties intended are in fact to be regarded as such damages.”
One of the most familiar tests for determining whether it should be held, in such a contract as the one in question, that the parties intended their language to be taken literally, is whether the actual damages, reasonably to be anticipated from the standpoint of the parties at the inception of their contract as the probable result of a breach of it, bear some fair relation to tire amount of the damages stipulated for. If the latter is so large that the former cannot reasonably be said to have formed any fair basis for’it, then the inclination is to hold that the stipulated damages, so called, are but a penalty, and that the actual damages suffered are the only recoverable loss. Another of the most common tests is whether the character of the property is such as to render the actual damages caused by a breach of the contract very difficult if not impossible of ascertainment with any reasonable degree of certainty. Both of those tests indicate clearly in this case that the parties intended the language fixing the damages for delay at $20 per day to be enforced literally. The character of the building was such that it was. very diffi
From the foregoing we cannot see any escape from the conclusion that appellant is entitled to a judgment for the stipulated damages of $20 per day for ninety-two days, less $060 unpaid upon the contract, making $1,180, and is entitled to interest thereon from February 12, 1901. If that seems harsh, the parties suffering the burden have but to reflect that it is but the result of enforcing the contract just as they made it, and the law which acts upon them with seeming harshness one day is the same law they may invoke in their favor upon some other occasion. Our construction of the contract is that the delay for which respondents bound themselves to pay damages at $20 per day refers to working days only. The period of delay was not found by the court. We do not feel warranted in finding that it amounted to more than ninety-two days.
By the Gourt. — The judgment appealed from is reversed, and the cause remanded with directions to render judgment in favor of the defendant for $1,180, with interest thereon from February 12, 1901, and with costs as the same may be taxed and allowed according to law.