DAVIS v. JOHNSON
35778
Court of Appeals of Georgia
DECIDED NOVEMBER 1, 1955.
92 Ga. App. 858
The petition set out a cause of action against the plaintiff in error, and the trial court did not err in overruling the general demurrers interposed.
Judgment affirmed. Gardner, P. J., and Carlisle, J., concur.
Fulcher, Fulcher & Hagler, contra.
GARDNER, P. J. 1. As we construe the petition, the sole basis for establishing liability and damages in favor of the plaintiff against the defendant is the allegation that the defendant notified the plaintiff that the permit issued to the plaintiff was void
The act of the General Assembly approved August 19, 1927 (Ga. L. 1927, pp. 1631 et seq.), created a new charter for the City of Thomson. This court takes judicial cognizance of this act. Section 13 of the charter provides: “That the mayor . . . shall not vote on legislative questions and matters before the body, except in case of a tie.”
Construing the petition most strongly against the pleader, as must be done on demurrer, it will be presumed by this court that there was no tie in any action taken by the City Council of Thomson whereby the defendant, as mayor, was authorized to, or actually did, vote upon any question respecting the issuance or the revocation of the plaintiff‘s permit, or the operation of his abattoir. It appears there was no contract between the City of Thomson and the plaintiff (see City of Thomson v. Davis, supra); consequently, there can be none between the plaintiff in the instant case and the defendant. The action for damages in the instant case for the alleged taking and damaging of the property of the defendant is predicated solely on
“The contention in the remaining count that the defendant became liable because its action deprived the plaintiff of his property without due process of law is not well taken. Being ex parte, the revocation of the license was void, and he did not need to pay any attention to it unless his continued operation of the business would subject him to penal action on the part of the city, in which case he would have his remedy by injunction to keep the defendant from interfering with his proper use of
The effect of the provisions of
In Rossignoll v. Northeastern Railroad, 75 Ga. 354, the Supreme Court in referring to a tort action said: “To entitle a party to such an action there must be a violation of right, accompanied with damage.”
It must be kept in mind that there are three essential elements to a cause of action in tort: (1) A right; (2) its violation; (3) damage. We may assume, without deciding, that the plaintiff had a vested right in the permit. Such right alone is not sufficient to enable the plaintiff to maintain his action in the case now before us. It is incumbent upon the plaintiff to go further and show that there was a violation of that right. The revocation of his license was void. Under the allegations of the petition there was no violation of the plaintiff‘s right by the defendant, because the defendant did not take or damage his property (the property of the plaintiff) for public purposes and he did not revoke or attempt to revoke the plaintiff‘s license. The plaintiff must show damage. No damage has been shown in the instant case. The title to the plaintiff‘s property and its
2. The plaintiff, in support of his contention that the court erred in sustaining the demurrer to his petition, calls our attention to Kitchens v. Jefferson County, 85 Ga. App. 902 (70 S. E. 2d 527). In that case the defendants committed overt acts in tearing away a brick wall, placing a culvert in a ditch, tearing up iron stakes, cutting tree limbs and making a roadway over graves. Doing such acts inflicted actual damage on the property and did not leave it physically unimpaired. Also, our attention is called to Stembridge v. Wright, 32 Ga. App. 587 (124 S. E. 115). That case shows overt acts committed by the defendant in making an illegal arrest and imprisonment, thereby depriving the defendant of his liberty and not leaving him physically unimpaired. Our attention is called also to Atlanta v. Gate City Gas Light Co., 71 Ga. 106, and City of Summerville v. Georgia Power Co., 205 Ga. 843 (55 S. E. 2d 540). The principal law, applicable under the facts of those cases, is not applicable in the instant case. In those cases the principle of estoppel was involved. “Estoppel merely precludes from setting up a defense, but creates no new right of action in the opposite party.” See also City of Thomson v. Davis, supra. Our attention is called also to Pruden v. Love, 67 Ga. 190. In that case the plaintiff had been notified of a meeting at a specific time at which his case would be heard. The time of the meeting was changed without notice to the plaintiff. The demolition of his property was approved and the building was demolished. Such are not the facts in the instant case. Also, our attention is called to City of Atlanta v. Dooly, 74 Ga. 702. In that case the billboard of the plaintiff was actually destroyed. The property of the plaintiff was physically impaired. The damage to the property was committed by overt acts, thus the legal prerequisites for the commission of a tort were shown by the existence of a right, its violation, and damage.
Judgment affirmed. Felton, C. J., Carlisle and Quillian, JJ., concur. Townsend and Nichols, JJ., dissent.
TOWNSEND and NICHOLS, JJ., dissenting. 1. We dissent from the majority opinion, for the reason that we think the first three counts of the petition set out a cause of action against the Mayor of Thomson individually as against general demurrer. We disagree with the opinion, insofar as the first three counts are concerned, in that it appears to rely upon City of Thomson v. Davis ante, p. 216, as authority for the proposition that no cause of action is stated against Johnson, Mayor, as an individual. City of Thomson v. Davis was an action against a city in the exercise of a governmental function which was sought to be predicated upon a taking of private property for public purposes. It therefore bears no relation to the present case (except to some extent insofar as count 4 of this petition is concerned) in that the defendant is different, the act alleged to constitute the tort is different, certain factual allegations of the petition are different, and the liability imposed by law upon the named defendant is also different.
We also disagree with the first sentence of the opinion to the effect that the only basis of liability alleged against the defendant Johnson is that he notified the plaintiff that the permit issued was void. This petition shows far more than mere notification. Taking it, together with the charter provisions of which this court takes judicial notice, it must be taken to allege that the municipal government of the city is vested in a mayor and four councilmen; that the mayor does not vote on legislative matters except in case of tie; that he exercises the power of veto; that he is the chief executive officer and shall see that all laws and ordinances are faithfully executed; that he has general jurisdiction of the affairs of the city and all police officers come under his jurisdiction; that he has power to punish for contempt and to preserve the peace and also has certain judicial powers; that the mayor and council have power to issue building permits and also to grant and revoke licenses; that the mayor (apparently without any action on the part of the city council) in his official capacity “signed a permit which granted to plaintiff the right to erect a building for the purpose of equipping and operating
Under this statement of fact, this court need not decide whether or not the allegations are sufficient to show that the permit was in fact a void permit. If it was void, and the defendant maliciously or oppressively or without authority of law allowed the plaintiff to presume it was valid until he had spent a considerable amount of money and had reached the point of commencing operations to realize an income from his investment, and then informed him he could not proceed thereunder, he had violated the plaintiff‘s rights and the plaintiff was injured. If, on the other hand, the permit was valid, and the defendant allowed the plaintiff to obtain it and proceed to make a large investment under its authority and then (the plaintiff having done no act which created a nuisance or in any way changed the situation except by spending money as authorized under the permit) the defendant undertook, as an executive officer in charge of the city police force, to prevent him from exercising his rights thereunder by maliciously or oppressively or without authority of law telling him, as such executive officer, that he would prevent him from exercising his rights thereunder, then also the plaintiff‘s rights had been violated and he was damaged thereby. It was not necessary for the plaintiff to do any overt act which would cause his arrest, it being obvious that to disregard the prohibition would only lead to further difficulties. City of Atlanta v. Dooly, 74 Ga. 702.
The allegations of the petition are sufficient as against general demurrer, construing them most strongly against the pleader, to authorize the inference that the mayor would use the police force at his command in order to prevent the operation of the abattoir, the petition alleging that “defendant in his official capacity as mayor notified plaintiff that he could not operate said abattoir” and that he in such capacity would “prevent plaintiff
2. Count 4 predicates damages upon the taking or damaging of private property for public use without just compensation, and the deprivation of property without due process of law. It was held in City of Thomson v. Davis, supra, that there was no “taking” where the title of the property remained in the plaintiff and only the use thereof was impaired. The same situation