STEPHEN K. DAVIS, Plaintiff and Appellant, v. FRESNO UNIFIED SCHOOL DISTRICT et al., Defendants and Respondents.
No. F068477
Fifth Dist.
June 1, 2015
237 Cal.App.4th 261
COUNSEL
Carlin Law Group and Kevin R. Carlin for Plaintiff and Appellant.
Briggs Law Corporation, Cory J. Briggs, Mekaela M. Gladden and Anthony N. Kim for Kern County Taxpayers Association as Amicus Curiae on behalf of Plaintiff and Appellant.
Atkinson, Andelson, Loya, Ruud & Romo, Martin A. Hom and Jennifer D. Cantrell for Defendant and Respondent Fresno Unified School District.
Fagen Friedman & Fulfrost, Kathy McKee, Paul G. Thompson, James Traber and Luke Boughen for California‘s Coalition for Adequate School Housing as Amicus Curiae on behalf of Defendant and Respondent Fresno Unified School District.
Lozoya & Lozoya and Frank J. Lozoya for Defendant and Respondent Harris Construction Company, Inc.
OPINION
FRANSON, J.—Plaintiff Stephen K. Davis is a taxpayer challenging a noncompetitive bid contract between the Fresno Unified School District (Fresno Unified) and Harris Construction Co., Inc. (Contractor), for the construction of a middle school for $36.7 million. The construction was completed in 2014 pursuant to a lease-leaseback arrangement that Fresno Unified and Contractor contend is exempt from competitive bidding under
The trial court sustained demurrers filed by Fresno Unified and Contractor. Davis appealed.
As to the causes of action based on the
As to the conflict of interest cause of action, we conclude
We therefore reverse the judgment.
FACTS
This case involves a project for the construction of buildings and facilities at the Rutherford B. Gaston Sr. Middle School, located in southwest Fresno. On September 26, 2012, Fresno Unified‘s governing board adopted a resolution authorizing the execution of contracts pursuant to which Fresno Unified would lease the project site to the Contractor, which would build the project on the site, and lease the improvements and site back to Fresno Unified. The contracts were a site lease (Site Lease) and a facilities lease (Facilities Lease; collectively, the Lease-leaseback Contracts).
Under the Site Lease, Fresno Unified leased the project site to Contractor for $1 in rent. The Site Lease began on September 27, 2012, and terminated
The Facilities Lease was structured so that Contractor would (1) build the project on the site pursuant to the “Construction Provisions” attached as an exhibit to the Facilities Lease and (2) sublease the site and project to Fresno Unified2 in exchange for payments under a “Schedule of Lease Payments.” The Construction Provisions were a detailed construction agreement (55 pages long) whereby Contractor agreed to build the project in accordance with the plans and specifications approved by Fresno Unified for a guaranteed maximum price of $36,702,876. Completion was to be 595 days from the notice to proceed.
The “Schedule of Lease Payments” attached to the Facilities Lease simply referred to the “payments for the Project as set forth in the Construction Provisions.” The Construction Provisions outlined monthly progress payments for construction services rendered each month, up to 95 percent of the total value for the work performed, with a 5 percent retention pending acceptance of the project and recordation of a notice of completion. Final payment for all of the work was to be made within 35 days after recordation by Fresno Unified of the notice of completion. Simply put, the funds paid by Fresno Unified under the Facilities Lease were based solely on the construction services performed by Contractor.3
Once the project was completed and the final lease payment made, the Facilities Lease terminated. Counsel for Fresno Unified confirmed at oral argument that the term of the lease was from the date of signing to the date of completion. As to possession of the project, the Facilities Lease stated that Fresno Unified was allowed to take possession of the project “as it is completed.” However, consistent with Davis‘s allegations of fact, Fresno Unified‘s opening brief acknowledged the Facilities Lease was in effect only during the construction of the school facilities and its counsel confirmed during oral argument that a phased completion of the project was not used in this case. Thus, the brief and counsel‘s statement do not contradict the allegation that Fresno Unified did not occupy or use the newly constructed facilities during the term of the Facilities Lease.
As to ownership of the newly constructed improvements, the Facilities Lease provided that Fresno Unified would obtain title from Contractor “as
PROCEEDINGS
On November 20, 2012, Davis filed his original complaint.4 The operative pleading is the first amended complaint (FAC) he filed in March 2013. The causes of action in the FAC are (1) violation of the competitive bidding requirements of the
Davis alleged that, although the site was leased by Fresno Unified to Contractor while Contractor performed the construction, there was no genuine leaseback to Fresno Unified because Fresno Unified did not regain the right to use and occupy the property during the leaseback period. Davis also alleged that Fresno Unified made payments that lasted only as long as the duration of construction, varied based upon the value of the work performed, and ended with the completion of the construction. In addition, Davis alleged
In April 2013, Fresno Unified filed a demurrer to the FAC, which was supported by a request for judicial notice.5 In May 2013, Contractor filed a separate demurrer that was similar to Fresno Unified‘s.
Davis opposed the demurrers and objected to the request for judicial notice. Davis also lodged 11 exhibits with the trial court to support his opposition to the demurrers.
In August 2013, the trial court sustained both demurrers to each of the seven causes of action in the FAC. The court granted Davis 30 days’ leave to amend. Counsel for Davis informed counsel for Fresno Unified that Davis did not intend to file a second amended complaint. After the 30-day period expired, defendants filed applications for dismissal of the action and entry of judgment.
In September 2013, judgment was entered in favor of Fresno Unified and Contractor. Davis appealed.
DISCUSSION
I. Standard of Review
A. Demurrers
Appellate courts independently review the ruling on a general demurrer and make a de novo determination of whether the pleading alleges facts sufficient to state a cause of action. (McCall v. PacifiCare of Cal., Inc. (2001) 25 Cal.4th 412, 415 [106 Cal.Rptr.2d 271, 21 P.3d 1189].)
Generally, appellate courts “give the complaint a reasonable interpretation, reading it as a whole and its parts in their context. [Citation.]” (City of Dinuba v. County of Tulare (2007) 41 Cal.4th 859, 865 [62 Cal.Rptr.3d 614, 161 P.3d 1168] (Dinuba).) Also, the demurrer is treated as admitting all
Ordinarily, the allegations in a pleading “must be liberally construed, with a view to substantial justice between the parties.” (
B. Statutory Construction
This appeal presents a number of issues relating to the proper construction of the
Issues of statutory construction are questions of law subject to independent review by appellate courts. (Neilson v. City of California City (2007) 146 Cal.App.4th 633, 642 [53 Cal.Rptr.3d 143].)
“A reviewing court‘s fundamental task in construing a statute is to determine the intent of the lawmakers so as to effectuate the purpose of the statute. [Citations.] Courts start this task by scrutinizing the actual words of the statute, giving them their usual, ordinary meaning. [Citation.] When statutory language is clear and unambiguous (i.e., susceptible to only one reasonable construction), courts adopt the literal meaning of that language, unless that literal construction would frustrate the purpose of the statute or produce absurd consequences. [Citation.]
“Alternatively, when the statutory language is ambiguous, courts must select the construction that comports most closely with the apparent intent of the Legislature, with a view to promoting rather than defeating the general purpose of the statute. [Citations.] The interpretation of ambiguous wording is guided by the fundamental principle that courts construe those words in the context and with reference to the entire scheme of law of which they are a part. [Citations.] Courts resolving statutory ambiguity also may be aided by the ostensible objects to be achieved by the legislation, the evils to be remedied, the legislative history, and public policy. [Citation.] When a court interprets an ambiguous statute, it is not authorized to rewrite the statute. It must simply declare what is, in terms or in substance, contained in the statute.
The foregoing rules of statutory construction are subject to specific rules that apply to particular types of statutes. The specific rule relevant in this case provides that any statutory exception to competitive bidding requirements for government contracts is to be strictly construed. (Unite Here Local 30 v. Department of Parks & Recreation (2011) 194 Cal.App.4th 1200, 1209 [123 Cal.Rptr.3d 789]; see 45A Cal.Jur.3d (2008) Municipalities, § 524, p. 301 [exception to competitive bidding should be strictly construed and restricted to circumstances that truly satisfy the statutory criteria].)
II. Exception To Competitive Bidding—First Cause of Action
A. Background
School districts can procure new facilities in various ways based on (1) different methods for financing the project and (2) different delivery methods for the construction.
1. Traditional Financing and Delivery
The traditional method for financing new school facilities is for school districts to obtain voter approval for the issuance of general obligations bonds and then use the proceeds from the bonds to pay for the construction. (62 Ops.Cal.Atty.Gen. 209, 210 (1979).)
The traditional delivery method for new school facilities is referred to as design-bid-build, which involves three separate steps. (See 10 Miller & Starr, Cal. Real Estate (3d ed. 2010) § 27:27, p. 27-143 (rel. 9/2010).) First, the school district hires an architect to design the project. Second, the district uses the design in its request for competitive bids from construction firms. Third, the winning bidder builds the project.
School construction contracts are a type of public works contract subject to the competitive bidding process unless an exception applies. (See
2. Lease-leaseback Delivery and Financing Method—Section 17406
In 1957, the Legislature authorized another method for financing and delivery of new school facilities and made it exempt from the competitive
Under the lease-leaseback method, the school district leases land that it owns to a construction firm for a nominal amount ($1) and the construction firms agrees to build school facilities on that site. (
Under this financing method, the builder finances the project (probably with assistance from a third party lender) and is paid over the term of the lease, which can last 40 years. (
The fact that the same results could have been achieved under an alternate, simpler contractual arrangement leads us to consider why the Legislature chose a complicated lease-leaseback structure for builder-financed construction. The answer appears to be related to (1) a constitutional provision that prohibited counties, cities and school districts from incurring any indebtedness or liability exceeding the amount of one year‘s income without the assent of two-thirds of its voters and (2) the California Supreme Court‘s determination that leases do not create an indebtedness for the aggregate amount of all installments, but create a debt limited in amount to the installments due each year. (See City of Los Angeles v. Offner (1942) 19 Cal.2d 483 [122 P.2d 14] (Offner) [applying Cal. Const., art. XI, former § 18].) Thus, the Legislature adopted the lease-leaseback structure to create a way for school districts to pay for construction over time and avoid the constitutional limitation on debt. (See former § 18365 [amount of rental a district agrees to pay during any one year is an obligation of such district for such year only], added by Stats. 1957, ch. 2071, § 1, pp. 3682, 3686.)
Therefore, the formalities of the lease-leaseback arrangement were important to the Legislature in 1957 because of their effect on the project‘s financing. Specifically, the formalities spread the school district‘s liability for the construction and carrying costs over the term of the leaseback and limited the amount of debt attributed to the district for any one year.
Next, we consider each component of a traditional lease-leaseback arrangement and the function of that component. The “lease” part of the lease-leaseback arrangement—that is, the agreement pursuant to which the school district leases real estate it owns to a construction firm for $1 for the purpose of building new facilities on that real estate—serves three functions. First, the site lease gives the contractor a possessory or leasehold interest in the real estate so that the contractor holds sufficient property rights or interests to serve as the foundation for the leaseback. The fact the contractor holds these rights to the land lends weight and legitimacy to the leaseback and helps avoid the constitutional limitation on debt exceeding one year‘s income. (See Offner, supra, 19 Cal.2d at p. 486 [the aggregate amount of payments under a subterfuge lease are a present liability for purposes of the constitutional limitation on debt].) Second, the site lease solidifies the bundle of property and contractual rights (particularly the rental payments under the leaseback) that the construction firm can use as collateral to obtain third party financing. (See fn. 6, ante.) Third, the site lease formalizes the contractor‘s right to enter and occupy the location while building the new facilities. This last function is
The “leaseback” part of a lease-leaseback arrangement is the mechanism by which (1) the contractor is compensated for its construction services and the cost of financing the project and (2) the school district‘s obligation to pay for the project is spread over a period of time. The leaseback, with its payment term of up to 40 years, allows a school to acquire facilities that it might not be able to pay for using other financing methods. As a result, the lease-leaseback method opened up a new source of financing for school construction—namely, private sector funding through the contractor and a third party lending money to the contractor. Given the difficulties in obtaining adequate funding for the school construction needs of California in the post-war era, it appears that the primary purpose for the Legislature‘s adoption of
Based on the statutory language and historical context, we conclude the primary purpose for the adoption of
we regard this view of legislative intent as unsupported by legislative history, historical context, or the concerns being addressed in 1957.
In the future, a Legislature might balance the various costs and benefits associated with competitive bidding and with lease-leaseback arrangements and find there are efficiencies that justify excepting lease-leaseback arrangements from competitive bidding even when those arrangements do not provide financing for the construction. While the Legislature is free to make such a finding and amend the statute, we cannot treat recent criticism of competitive bidding as providing insight into the intent of the Legislature in 1957.
Our view that obtaining a new source of school financing was the primary purpose of the lease-leaseback provisions in
Although the lease-leaseback delivery method was authorized in 1957, an alternate form has been growing in use throughout California over the past 15 years. This variation of the lease-leaseback arrangement is the type used by Fresno Unified and Contractor in this case. Under this alternate approach, the school district pays for the construction (using local bond funds) as it progresses, with the final payment being made when construction is completed. As a result, the school district does not occupy and use the new facilities as a rent-paying tenant for a set length of time. Because the school
B. Text of Section 17406
C. The Exception Includes Facilities Leases
An initial question of statutory construction raised by the parties is whether
This specific question of statutory construction was addressed by the court in Los Alamitos, supra, 229 Cal.App.4th 1222. The court interpreted
We agree with the statutory interpretation that the exception to competitive bidding in
First, the ordinary meaning of the word “notwithstanding” is “in spite of.” (Webster‘s 3d New Internat. Dict. (1993) p. 1545, col. 3.) It is well established that the phrase “notwithstanding any other provision of law” is a term of art that expresses a legislative intent to have the specific statute control despite the existence of other law that might govern. (See People v. Harbison (2014) 230 Cal.App.4th 975, 985 [179 Cal.Rptr.3d 187].) Therefore, we conclude the phrase “[n]otwithstanding
Second, the exception created by
The interpretation that the exception can apply to the entire lease-leaseback arrangement is confirmed by the Attorney General‘s statutory construction of the predecessor of
Based on the foregoing, we reject Davis‘s argument that the exception to competitive bidding in
The foregoing statutory interpretation does not resolve all the questions presented in this case about the meaning and application of
D. Satisfaction of the Exception‘s Criteria
Davis‘s first cause of action includes the legal theory that the exception to competitive bidding in
1. Statute Requires a Genuine Lease and Financing
Our interpretation of the statute begins with its words. Generally, the Legislature uses words to indicate substance, not merely as labels. For example, in Williams v. Superior Court (1993) 5 Cal.4th 337 [19 Cal.Rptr.2d 882, 852 P.2d 377], the court refused to interpret a statute protecting law enforcement “investigatory” files from disclosure to mean that any file labeled “investigatory,” regardless of its nature, was shielded from disclosure. (Id. at p. 355.) Based on the principle that words indicate substance, we conclude the word “lease” used in
Moreover, this well-established disregard for labels in favor of an examination of the substance of a document was applied by the California Supreme Court to a public works contract 15 years before the Legislature enacted
The case law that existed prior to 1957 also leads us to conclude that the Legislature used the word “lease” to indicate the substance required, not simply as a label. (See
This interpretation of
In summary, our review of the entire legislative scheme, the ostensible objects it seeks to achieve, the evils to be remedied, and the underlying public policies lead us to conclude the word “lease” refers to the substance of the transaction and means more than a document designated a lease by the parties. Moreover, to fulfill the primary statutory purpose of providing financing for school construction, the arrangement must include a financing component. (See pt. II.A.2., ante.)
2. Relevant Factors
The conclusion that the leaseback must be a true “lease” to satisfy the criteria in
We conclude the true legal effect of the leaseback in question is based on all the terms of the document. (See Parke etc. Co. v. White River L. Co., supra, 101 Cal. at p. 39.) Provisions in the document that are significant include those that define (1) who holds what property rights and when those rights and interests are transferred between the parties and (2) the amount and timing of the payments. (See Offner, supra, 19 Cal.2d at p. 486.) The payment provisions, particularly the length of the period over which payments are made, are important in this context because the primary purpose of the legislation was to provide a source of financing for school construction and the payment provisions will show whether the project is being financed through the contractor or whether the school district is paying for the project by using funds from other source.
3. Sufficiency of the Allegations of a Subterfuge Lease
Paragraph No. 24 of the FAC alleges that the Lease-leaseback Contracts “are merely a sham and subterfuge to avoid the requirements” in the Public Contract Code for competitive bidding. It also alleges the payments required by the Facilities Lease were not real lease payments because they “(1) last only as long as the duration of the construction; (2) are variable based upon the value of construction work performed by CONTRACTOR prior to the date of payment; (3) do not provide for any financing of the work by CONTRACTOR (because its obligation to pay others who are actually
These allegations are supported by the contents of the Site Lease and the Facilities Lease and their attachments, such as the Construction Provisions, which were included in the FAC as exhibits and incorporated by reference. Therefore, the terms of the Site Lease and the Facilities Lease are before this court, which assists our analysis of the true character of the transaction. (See pts. II.D.1. & II.D.2., ante.)
First, we give little weight to the name “Facilities Lease” in evaluating the true character of that document.
Second, we conclude the terms in the Facilities Lease regarding the construction, payment, use, occupancy, possession and ownership of the new facilities adequately support Davis‘s allegation that the arrangement is not a true lease that provided financing for the project.
The Facilities Lease included Contractor‘s agreement to build facilities for Fresno Unified in exchange for a guaranteed maximum price of $36.7 million. The amount of Fresno Unified‘s monthly payments to Contractor was based on the progress of the construction. The final payment for the construction became due upon the completion and acceptance of the construction. Once the final payment was made, both the Facilities Lease and the Site Lease terminated.
Generally, the payment terms set forth in a contract are an important part of the substance of a transaction and are directly relevant to whether the transaction is a true lease or a purchase. (See Offner, supra, 19 Cal.2d at p. 486.) Here, the payment terms were identified in the Construction Provisions as progress payments for construction services and the amount paid each month was determined by the value of construction services completed, less a 5 percent retention. This type of payment schedule is common in construction contracts. (See 4 Miller & Starr, Cal. Real Estate Forms (2d ed. 2006) § 4:4, pp. 36-61 [90 percent progress payments and a 10 percent
Consequently, the substance of the payment terms in the Facilities Lease is that of compensation for construction, not payment for a period of use of the facilities. Moreover, the payment terms support the allegation that Contractor did not provide any financing to Fresno Unified under the Facilities Lease. Thus, the payment terms and the lack of financing support the allegation that the Facilities Lease was not a genuine lease.
Besides the payment terms, the provisions in the Facilities Lease addressing Fresno Unified‘s right to occupy and use of the new facilities and its ownership of those facilities shows the true character of the Facilities Lease is something other than a lease. The Facilities Lease stated that, during its term, Fresno Unified would obtain title to the project as construction progresses and corresponding payments were made to Contractor. Also, any remaining right, title or interest in the project and site was transferred to Fresno Unified upon it making the final payment. Thus, the combination of a relatively short payment schedule and the transfer of title when the final payment was made meant that (1) Contractor never acted in the capacity of a landlord holding rights to real property occupied by a tenant and (2) Fresno Unified never occupied and used the new facilities as a tenant. In addition to these provisions in the Facilities Lease, Davis specifically alleged that Fresno Unified did not have the right or practical ability to occupy and use the new facilities during the term of the Facilities Lease.
The provisions about use, occupancy and title, and the fact that Fresno Unified never occupied and used the project before making its final payment, provide sufficient support for Davis‘s legal theory that the substance of the transaction was a traditional construction contract and not a true lease that included a financing component. (Cf. 4 Miller & Starr, Cal. Real Estate Forms, supra, § 4:6, p. 115 [provision in construction contract addressing title to labor, materials and equipment states all title thereto will pass to the owner upon receipt of payment by contractor].)
Therefore, we conclude that Davis‘s allegations are sufficient to state a cause of action for a violation of the competitive bidding requirements in
4. Use During the Term of the Lease
Davis‘s first cause of action also alleges the Lease-leaseback Contracts violated the statute because they did not require Contractor “to construct on the demised premises . . . buildings for the use of the school district during the term of the lease.” (
Our analysis of the statutory language begins with the meaning of the word “use” that appears in the prepositional phrase “for the use.” In the context of a building, we conclude “use” refers to the occupation and utilization of the building in school operations.
Next, we consider the meaning of the prepositional phrase “of the school district,” which follows immediately after the phrase “for the use.” (
The phrase “during the term of the lease” follows immediately after the wording “for the use of the school district.” (
This interpretation is consistent with the Attorney General‘s statutory construction of the predecessor to
Defendants argue that because the legislation identifies a maximum term of 40 years (
In summary, a lease-leaseback arrangement qualifies for the exception to competitive bidding created by
5. Sufficiency of the Particular Facts Alleged
The next step of our analysis is to review the FAC to determine whether Davis has alleged facts sufficient to support his legal theory that the Facilities Lease was subject to competitive bidding because Fresno Unified failed to satisfy the statutory criterion for use of the buildings by the school district “during the term of the lease.” (
Paragraph No. 24 of the FAC alleged that Fresno Unified “does not have the right or practical ability to have beneficial occupancy of the demised premises during the term of the Facilities Lease to use them for their intended purposes.”
This allegation, which was made before the completion of the project and termination of the leases, directly addresses whether the Facilities Lease provided for the construction of “buildings for the use of the school district during the term of the lease.” (
E. Summary Regarding Competitive Bidding
We conclude the first and third causes of action15 adequately allege that defendants violated the statutory requirements for competitive bidding because the Lease-leaseback Contracts failed to “truly satisfy the statutory criteria” for the exception to competitive bidding set forth in
III. Improper Use of Lease Arrangements When Sufficient Funds Are Available—Fifth Cause of Action
A. Allegations and Legal Theories
The FAC‘s fifth cause of action, like his first, alleges the Lease-leaseback Contracts were ultra vires and void because they did not comply with certain requirements in the Education Code. These requirements are derived from two separate legal theories or interpretations of the Education Code.
1. The No-available-funds Theory
The first legal theory asserts the lease-leaseback method for completing a school construction project “is only available for use by school districts in California as a means to finance the cost of construction over time when they do not have sufficient immediate funds available to them to cover the cost of construction.” Davis alleged this requirement was violated because voter-approved bond sales provided Fresno Unified with “sufficient funds available to it to cover the immediate costs of construction of the Project as they are incurred. . . .”
2. Leaseback Must Provide Financing Theory
The second legal theory asserts that the statutory scheme authorizing lease-leaseback arrangements “requires the cost of construction be advanced and carried over a period of many years by the party to whom the lease-leaseback contracts are awarded.”
We will not analyze this legal theory separately because it is part of the first cause of action. (See pt. II.E., ante.)
3. SAB Report
Davis supports his legal theory that lease-leaseback arrangements are permitted only when funding is not otherwise available by referring to a
“Sections 17400 et al., including [section] 17406, make up Article 2 of Chapter 4 of Part 10.5 of the [Education ‘Code] entitled Leasing Property. It describes the requirements imposed on school districts considering the acquisition of school facilities through lease agreements. As confirmed by the Appeals Court ruling in [Morgan Hill Unified School District v. Amoroso, supra, 204 Cal.App.3d 1083], the article is about financing. In that case the court stated that, ‘The Education Code creates the following method for financing school construction.’ The court then went on to describe . . . Sections 39300 through 39325, which are now renumbered as 17400 through 17425. Thus [sections] 17400 through 17425 is a method of financing school construction in which [section] 17406 addresses the mechanism by which the school district can let the property where the construction will take place.
“Staff believes that virtually none of the projects currently using lease-leaseback arrangements actually have financing provided by the developer. If a ‘lease agreement’ other than the site lease exists at all, it serves no significant purpose other than as a construction contract. The full cost of the project is borne by the district using normal funds it has available for capital projects. Normal progress payments are made to the contractor through the course of construction, and the project is completely paid for by the district at the project completion. The projects are in every regard typical public works projects, except that they have not been competitively bid.
“Since no financing exists in the lease lease-back arrangement (or there is no lease agreement at all), the use of Article 2 appears to be inappropriate.”
4. Defendant‘s Arguments
Defendants argue the express requirements of
B. Analysis
We reject Davis‘s legal theory that the statutory scheme restricts the use of lease-leaseback arrangements to situations where the school district does not have sufficient available funds to cover the cost of building the new facilities.
First, there is no express provision in the statutes limiting a school district‘s use of lease-leaseback arrangements to situations where the school district funds are not otherwise available.
Second, Davis has identified no ambiguous provision in the statutes that could be construed in a manner to include such a broad limitation. Although exceptions to competitive bidding are to be narrowly construed, the concept of strict construction does not empower courts to narrow the scope of the statutory exception by imposing conditions or limitations the Legislature did not include in the statute. (See
Third, the views expressed in the SAB Report do not actually include the interpretation advocated by Davis. Specifically, the SAB report does not state that the legislation restricts the availability of the lease-leaseback method to situations where other funding is not available. In other words, the report‘s reference to a case stating the “Education Code creates the following method for financing school construction” (Morgan Hill Unified School Dist. v. Amoroso, supra, 204 Cal.App.3d at p. 1086) does not imply that method is allowed only if other methods of financing are not available.
IV. Breach of Fiduciary Duty—Second Cause of Action
A. Allegations
The FAC‘s second cause of action alleged that Fresno Unified‘s board had a fiduciary duty to the residents and taxpayers within Fresno Unified and that duty applied to the board‘s approval of expenditures for a multimillion-dollar construction project. The FAC also alleged Fresno Unified‘s board breached the fiduciary duty by (1) failing to consider less expensive alternatives to the project, (2) failing to consider whether the price was reasonable, (3) failing to exercise due diligence to determine whether the price paid could be lower, (4) knowing the price paid could have been lower, (5) failing to solicit bids for
The FAC contends that because Fresno Unified did not comply with its fiduciary duties, the Lease-leaseback Contracts are ultra vires, void and unenforceable and “all money paid thereunder must be returned by CONTRACTOR to DISTRICT.”
B. Breach of Fiduciary Duty
In litigation between private parties, the elements of a cause of action for breach of fiduciary duty are (1) the existence of a fiduciary duty, (2) a breach of the fiduciary duty, and (3) damage proximately caused by the breach. (Gutierrez v. Girardi (2011) 194 Cal.App.4th 925, 932 [125 Cal.Rptr.3d 210].) When a claim for breach of fiduciary duty is asserted against a public official by the Attorney General or a taxpayer, the damage element can be satisfied by alleging the official obtained profits from the unauthorized act. (People ex rel. Harris v. Rizzo (2013) 214 Cal.App.4th 921, 950 [154 Cal.Rptr.3d 443] [breach of fiduciary duty claim stated against council members who paid themselves excessive salaries].) In these cases, the relief available is restitution, which can include the disgorgement of profits obtained by the public official. (Id. at p. 951, fn. 30.)
C. Analysis
Here, the FAC requests that Contractor return all money paid to it under the Lease-leaseback Contracts, but does not allege Contractor was subject to a fiduciary duty. As to the persons who allegedly breached their fiduciary duty (i.e., Fresno Unified‘s board), the FAC does not allege they profited from the transactions and does not request restitution or the disgorgement of profits. Furthermore, the relief sought for the alleged breach of fiduciary duty is against Contractor, a party that did not have a fiduciary duty. Accordingly, the second cause of action failed to allege facts sufficient to state a claim for breach of fiduciary duty. (See People ex rel. Harris v. Rizzo, supra, 214 Cal.App.4th at p. 950 [city‘s police chief who negotiated excessive salary did not breach a fiduciary duty because any duty would have arisen only after the contract was executed; demurrer properly sustained as to cause of action against him].)
V. Conflict of Interest—Fourth Cause of Action
Davis‘s fourth cause of action attempts to state a conflict of interest claim based upon (1) common law conflict of interest principles, (2)
A. Political Reform Act of 1974
1. Conflict of Interest Provisions
Chapter 7 of the Political Reform Act of 197417 addresses conflicts of interest by public officials. This chapter contains
The term “public official” is defined for purposes of the Political Reform Act of 1974 to mean “every member, officer, employee or consultant of a state or local government agency.” (
2. Allegations in FAC
The FAC contains the following allegations. Contractor had a prior contract with Fresno Unified that created a conflict of interest and, therefore, precluded Contractor from being awarded the Lease-leaseback Contracts. Pursuant to the prior contract, Contractor acted as a consultant and provided Fresno Unified with professional preconstruction services related to the project, which included the development of plans, specifications and other construction documents for the project. Contractor was paid by Fresno Unified for consulting on the project and had a hand in designing and developing plans and specifications by which the project is being constructed.18
The FAC refers to
3. The Demurrers, Opposition and Replies
The demurrers of Fresno Unified and Contractor address the conflict of interest claim under the Political Reform Act of 1974 by asserting (1) it was
In his opposition, Davis cited
Defendants’ reply papers ignored the statutory language in
The minute order sustaining the demurrer to the conflict of interest cause of action mentioned
4. A Corporate Consultant Is Not a Public Official
The definition of “‘[p]ublic official‘” in
The term “consultant” is not defined by the Political Reform Act of 1974, but the regulations promulgated under the act contain a definition. (See League of Cal. Cities, The Cal. Municipal Law Handbook (Cont.Ed.Bar 2014) § 2.114, p. 155 [consultant included in list of key definitions].) A consultant is “an individual who, pursuant to a contract with a state or local government agency: [[] (1) [m]akes a governmental decision. . . .” (Cal. Code Regs., tit. 2, § 18704.6, subd. (a).) The appellate briefing has not mentioned this regulatory definition and, consequently, Davis has not argued the regulation is invalid. (See
Davis alleged that Contractor “is, and at all times mentioned was, a California corporation, doing business in the City of Fresno and State of California.” As a corporation, Contractor falls outside the regulatory definition of “consultant” that refers to individuals. Therefore, we conclude Contractor is not a “public official” subject to the conflict of interest provisions in the Political Reform Act of 1974.
It follows that the FAC failed to state a cause of action against Contractor for violating the conflict of interest prohibition in
B. Government Code Section 1090
1. Basic Principles Governing Conflict of Interest Claims
Courts evaluating a conflict of interest claim under
The breadth of what it means to participate in the making of a contract is illustrated by Stigall. In that case, a taxpayer filed an action seeking to have a contract for plumbing work related to construction of a civic center declared invalid. (Stigall, supra, 58 Cal.2d at p. 566.) The trial court sustained a demurrer to the complaint, concluding the taxpayer failed to allege facts showing a prohibited conflict of interest. The Supreme Court reversed and directed the demurrer to be overruled. (Id. at p. 571.)
In Stigall, the complaint alleged the member of the city council in charge of the council‘s building committee owned more than 3 percent of the stock of a plumbing company and the building committee supervised the drawing of plans and specifications for a civic center. (Stigall, supra, 58 Cal.2d at pp. 566–567.) When the bids for the construction work were received and opened, the council member‘s plumbing company was the low bidder for the plumbing work. (Id. at p. 567 bids and advertised for a new round of bidding. (Ibid.) Subsequently, the council member resigned and the council awarded the construction contract to a general contractor that had included a sub-bid for the plumbing work from the former council member‘s plumbing company. (Ibid.)
The Supreme Court addressed the timing of the council member‘s resignation and whether he “made” the contract entered into by the plumbing company. (Stigall, supra, 58 Cal.2d at pp. 568–569.) The court determined the use of technical terms and rules governing the making of contracts was not appropriate and construed the word “made” broadly in light of the statutory objective to “limit the possibility of any personal influence, either directly or indirectly which might bear on an official‘s decision.” (Id. at p. 569Id. at p. 571.) Because the former council member had participated in all of these activities involving the contract and was financially interested in the plumbing company, the court concluded the complaint alleged a violation of the conflict of interest provision in
2. Contentions
Davis contends that the conflict of interest provision in
Defendants contend Hub City and Hanover are readily distinguishable from the facts pled in the FAC and, in any event, the expansion of liability adopted in those cases has been harshly criticized by the court in People v. Christiansen (2013) 216 Cal.App.4th 1181 at pages 1189 through 1190 [157 Cal.Rptr.3d 451]. Defendants also contend that
3. Analysis
In Hanover, supra, 148 Cal.App.4th at p. 684, the conflict of interest claims were pursued against two individuals and not against the corporation that actually entered into the contract with the public agency.
In Hub City, the appellants challenged the adverse judgment on a conflict of interest claim by arguing that corporate consultants do not owe municipalities a fiduciary duty. (Hub City, supra, 186 Cal.App.4th at p. 1125.) The court did not decide this argument, concluding that the limited liability company‘s status as the contracting entity with the city was immaterial because the actions of the company‘s president fell within the scope of
In summary, the courts in Hanover and Hub City interpreted the statute broadly to include individuals who were consultants to the public agency, but neither court decided whether the statutory terms “officers” or “employees” should be expanded to include legal entities such as corporations or limited liability companies.
First, we conclude that the stricter definition of the statutory terms adopted by the court in People v. Christiansen, supra, 216 Cal.App.4th 1181 is appropriate in the context of criminal prosecution, but is not appropriate in the context of civil actions seeking to invalidate a contract with a public entity. In Stigall, a civil action, the Supreme Court interpreted the statutory terms broadly to implement the objectives of the conflict of interest statute and did not rely on technical definitions or rules to limit the reach of the statute. Similarly, we conclude that technical definitions of the term “employee” taken from other areas of law should not be used to limit the scope of
Second, as to whether the word “employees” should be interpreted to exclude corporate consultants, we conclude that corporate consultants should not be categorically excluded from the reach of
Third, the FAC alleged that Fresno Unified and Contractor entered into the Lease-leaseback Contracts pursuant to which Contractor agreed to build the project for a guaranteed maximum price of $36.7 million. These allegations are sufficient to state that Contractor was “financially interested in” the Lease-leaseback Contracts for purposes of
In summary, Davis has alleged sufficient facts to state a cause of action for a violation of the conflict of interest provisions in
C. Common Law Conflict of Interest
In Lexin, the Supreme Court stated that
Because we have concluded the FAC stated a cause of action under
VI. Declaratory Relief
Davis‘s seventh cause of action is based on the previously alleged violations of the Education Code and the need for competitive bidding. This declaratory relief claim depends upon the other causes of action and does not set forth an independent basis for relief. Because we have determined that some causes of action stated facts sufficient to allege a claim, we will allow the request for declaratory relief to remain part of the litigation.
DISPOSITION
The judgment is reversed. The trial court is directed to vacate its order sustaining the demurrer and enter a new order (1) sustaining the demurrer as to the breach of fiduciary duty claim, the violation of the Political Reform Act of 1974 claim, and the fifth cause of action alleging the use of the lease-leaseback arrangement is improper when funds are available to a school from another source and (2) overruling the demurrer as to the other causes of action.
Plaintiff shall recover his costs on appeal.
Levy, Acting P. J., and Gomes, J., concurred.
On June 19, 2015, the opinion was modified to read as printed above. Respondents’ petitions for review by the Supreme Court were denied August 26, 2015, S227786.
