The petitioner proceeds under the St. of 1863, c. 163, which was an act for supplying the city of New Bedford with pure water, and which authorized the construction of a dam
There have been several occasions when it has been necessary to construe acts where, either for public purposes or to aid in enterprises of a public and general character, the construction and permanent maintenance of dams have been authorized. These acts have contained provisions for the protection of those whose lands or other property is taken, or who sustain damage by such structures, but in nearly all it has been provided that the remedy must be pursued within a comparatively short limitation of time. It has been held that, notwithstanding the difficulty of determining within a brief period what is the damage sustained by land or property not taken, it must still be done within the time limited. Heard v. Middlesex Canal,
The reasons why this should be so are certainly as strong in the present case as in those cited. Unless there were a single assessment within a definite period, the cost of such a work could not be ascertained and provided for, as there might be a continued recurrence of claims of indefinite extent and for an indefinite period. Again, that which the respondent should pay is the damage which it has occasioned by diminishing the value of the land, as it existed at the time of the construction, and not as it may exist years afterwards, when increased population or other reasons may have materially added to such value. Heard v. Middlesex Canal, ubi supra.
The petitioner deems that the language of the act under consideration, perhaps in view of the decisions already cited, has been chosen to meet cases such as that which he presents; and that it is intended thereby to provide a remedy for damages, as from time to time they may appear to have been occasioned, to lands not taken. But a careful examination of the act shows that this cannot be its true construction. Although those sustaining damage may proceed within three years according to the provisions of the sixth section of the act, yet they are liable to be barred by the action of the city under the seventh section, which permits the city after twelve months to commence proceedings on its own behalf, which are to be determined in the same manner as if commenced by those who have sustained damage. These limitations would be nearly valueless, if a right to litigate continued at any time thereafter whenever a petitioner could prove additional damage.
The petitioner contends that it was only many years after the construction of the dam that he sustained actual damage; that previously thereto it was speculative merely. The injury likely to arise to land from the flowing thereof is more readily seen and determined, undoubtedly, than that which may proceed from percolation or underground currents of water, when it is collected and stored in a reservoir in the vicinity of a tract of land. Yet, if by exposure to danger therefrom the land is diminished in. value, such loss or diminution would afford a fair measure of the owner’s damage. Heard v. Middlesex Canal, ubi supra.