60 Ct. Cl. 201 | Ct. Cl. | 1925
delivered tbe opinion of the court:
The contract in this case was dated the 5th day of August, 1918, and was for the manufacture of Very pistols. These pistols were to be used for giving signals by firing a charge which exploded with certain lighting effects. Delivery was to be commenced on the 1st of September, 1918, and completed on the 1st of March, 1919. The number of pistols to be delivered was 75,000, for which the plaintiff was to receive payment in the sum of $375,000. The contract contained a clause giving the defendant the right to terminate the contract at any time under certain conditions. The armistice having been declared in November, on the 11th of December the defendant, through the Ordnance Department, addressed a communication to the plaintiff stating that “you are requested immediately to suspend further operations under your contract * * * and to order no further materials or facilities,” and further, “to enter into no further subcontracts ” or make any “ further commitments and incur no further expenses,” and stated that the request was made with the view to the negotiation of a supplemental contract providing for cancellation, settlement, and adjustment of the existing contract in a manner that would permit a more prompt settlement and payment than would be practicable under the terms of the existing contract. It concluded by asking for immediate acknowledgment of receipt of the notice and an indication of plaintiff’s decision to comply with or reject the request. On December 14 this letter was forwarded to the plaintiff with a letter from the representative of the Ordnance Department, stating that upon acceptance of the request the negotiation of a settlement in the form of a supplemental contract would be initiated by the St. Louis district claims board, and in this ivay plaintiff would get a more prompt settlement and payment than under the terms of the existing contract.
Replying to these several letters, on the 18th of December the plaintiff acknowledged the notice of “ suspension of the above contract,” stating “ we accept this suspension, effective December 18, 1918, without prejudicing our rights under said contract,” and further, “ we take it from your request that immediate steps will be taken toward the negotiation
Pursuant to this correspondence the plaintiff on January 16, 1919, filed an itemized claim in the sum of $189,507.38, in which was a claim for profit of $1.66 each on 30,000 pistols which could have been completed before the termination of the contract but for the delay caused by the Government’s changes in the specifications and drawings. Against this claim the plaintiff entered a credit of $18,211.08 for certain materials, the property of the Government, which had been turned back to the Government, and then sold to and retained by the contractor, leaving a net claim of $171,296.30. Thereafter a partial payment and supplemental contract was entered into. Under this supplemental contract the plaintiff was paid the sum of $103,650.66 as an advance payment, and it was stipulated that the United States agree to pay such additional sum which, together with this last-named sum, would cover such portion of his expenditures, obligations, and liabilities necessarily incurred and for work, labor, and services rendered in connection with the performance of the original contract as would be properly and fairly apportionable to the uncompleted part thereof, enumerating the particular classes of items for which payment was to be made. In this supplemental contract the plaintiff waived all claim to prospective profits which he might have made by the performance of that portion of
The item of $49,800 claimed as profits by the plaintiff on the pistols which he claimed could have been completed and delivered before the suspension of the contract but for the delay in the work caused by the Government, was disallowed on the ground that it was prospective profits. The contractor refused to accept this proposed final settlement and took an appeal to the War Department Board of Contract Adjustment, which board affirmed the decision of the claims board. It does not appear that any final appeal was taken to the Secretary of War, as provided by the contract.
The plaintiff is here suing apparently, although his claim has assumed different forms and is in different amounts in his petition and proof, for profits which it claims it would have made on pistols that could have been completed and delivered before the suspension of the contract had not the Government delayed the performance of it.
The original contract contained a provision for its termination at the will of the Government, and, except as provided in the clause for termination, is in the same position as a contract made subject to the provisions of the act of June 15, 1917, which the courts have held must be taken to have been read into the contract. See Meyer Scale Co. v.
The plaintiff suspended work at the request of the Government. It is true that it tried to reserve its rights 'under the original contract, but it nevertheless suspended and entered into negotiations for a settlement, which finally terminated in a supplemental and partial settlement contract under which it accepted payment, as stated, in the sum of $103,650.66. It thus practically put an end to the original contract and all claims under it. It in effect negotiated itself out of its rights under that contract. It accepted part payment under a settlement contract, and is estopped from claiming profits as a part of damages for a breach of the original contract. Having voluntarily terminated the original contract and accepted payment covering in part the outlays and risks under the original contract, it waived its right to any claim for profits thereunder, if it had any. It has no legal standing to sue for damages 'upon the theory of a breach of the original contract while retaining in its possession money paid on the basis of a settlement of it. Upon what theory can prospective profits be allowed to a party to a contract who has voluntarily participated in such a change in the situation of the parties that the contract can not be performed? The plaintiff could have stood upon such-rights as it had under the original contract and demanded a settlement under its provisions and the terms of the termination clause thereof, though, even under this clause, as stated, it could not, have received any payment in the nature of profits unless it had been allowed by the Chief of Ordnance, to whom no appeal was ever made. Its rights, such as it has, were transferred to the Supplemental contract, and are therefore to be determined by the terms of that contract.
If it has a right to recover profits under that contract, the right must be found within its circumference. Under the
The question has been raised in this case as to the application of section 3477 of the Revised Statutes, to the effect that assignments and transfers of any claim from the United States “shall be absolutely null and void unless they are freely made and executed, in the presence of two attesting witnesses, after the allowance of such a claim, the ascertainment of the amount due, and the issuing of a warrant for the payment thereof.” The contract out of which the claim in this case arose was in the name of the National Tool & Manufacturing Co., and this company performed such work
In the instant case this transfer was made by order of the court which had appointed the receivers and having jurisdiction of the subject matter, and by the receivers, the representatives of the court, acting under its order. The claim clearly passed by action of law and the assignment was not in violation of the statute. The plaintiff received its title from the receivers as the result of a judicial proceeding and an order of the court authorizing and directing them so to do.