32 Mo. 498 | Mo. | 1862
delivered the opinion of the court.
Plaintiff sued the defendant on an account for work and labor, the greater part of which was on and about the making and burning a kiln of brick.
Defendant, by his answer, avers that the work done in making and burning the brick, was so done under a special contract, whereby the plaintiff agreed to. superintend the making and burning a kiln of brick for the defendant for a stipulated price per day, on condition that the plaintiff was to make for defendant “ a good burn ; ” and if he failed to make a good burn, he was to have nothing for his time and labor. Defendant also alleged that the plaintiff agreed to make and kiln a certain number of bricks per day, and failed to do so, whereby the defendant sustained the loss of a sum named, for which he asked judgment.
Defendant alleged that the bricks were greatly injured in burning, so as to impair their value four hundred dollars, for which he asks judgment.
The defendant also asked judgment against the plaintiff upon an account for moneys paid for boarding, &c.
1. That unless they believe from the evidence plaintiff was to make and kiln six thousand bricks per day, and was to make a good burn, as stated in the defendant’s answer, they will find for the plaintiff.
2. That it devolves on the defendant to prove the contract, as stated in his answer.
3. That all the material allegations in the plaintiff’s petition, not specifically denied by the defendant’s answer, will, for the purposes of this action, be taken to be true.
On motion of the defendant, the court gave the following instructions:
1. That if they believe from the evidence that there was a contract between the plaintiff and defendant, to the effect that plaintiff was not to receive anything from defendant if he failed to make a good kiln of brick; and the jury believe from the evidence that said plaintiff did not make a good kiln of brick, they will find nothing for making said brick, unless the jury believe from the evidence that there was a variance in the contract.
2. The jury will find on defendant’s account whatever they may think is proven in addition to what plaintiff has admitted.
The court also refused the following instruction, asked by the defendant:
“ The court further instructs the jury, that they will find for the defendant, by way of damage, any amount under four hundred dollars, if they believe from the evidence defendant sustained any damage by the unskilfulness or mismanagement of plaintiff, or by intentional mismanagement.”
Yerdict and judgment for ninety dollars was given for plaintiff, and defendant appealed to this court.
The first instruction given for plaintiff was wrong. It connected together, as having the same effect, the contract to make and kiln six thousand bricks per day, and that to make a good burn, and wholly ignored the other items of defendant’s counter-claim. The answer se,ts up that the plaintiff’s
The third instruction given for plaintiff was obviously wrong. It is proper for the court to state the issues to the jury, but it is not proper to refer the jury to the pleadings to ascertain them, and especially to such pleadings as these.
We do not understand what is meant by “ a variance in the contract,” mentioned in the instruction given for the defendant ; nor do we understand the second instruction.
The instruction refused the defendant, was, in the form as asked, properly refused.
The instructions seem to have been as carelessly drawn as the pleadings.
Upon the whole, this case had better be tried over again, for it seems very improbable that the jury could have had any clear understanding of the issues, and of the law applicable to them.
Judgment reversed, and cause remanded.