107 Mo. App. 148 | Mo. Ct. App. | 1904
Action to enforce a lien for materials. E. P. Taylor agreed as original contractor to build a residence for Berney Harris in the city of Webster Groves. The lumber for the house was purchased by Taylor from the Darlington Lumber Company, but most of it was never paid for; so the lumber company filed a lien against the property, brought this action to enforce it and obtained judgment for $645.56.
One point made against the judgment is that the evidence was insufficient to prove the different articles of lumber listed in the lien were used in the construction of the house. It was shown wagons were loaded at the respondent’s yard with lumber to be taken to Harris’ lot in Webster Groves, a dray ticket for every load was made and was receipted by Taylor, or one of the men who were working on the house when the load was delivered in Webster Groves. Taylor swore he was about the house a great deal, but not constantly, while it was under construction; that he knew most of the
We overrule the objection that the lien account described more than an acre of ground. The premises on which the lien is prayed are definitely described and the lot contains slightly more than an acre. This is immaterial. The lien is asked on a platted lot in an incorporated city and not on country property. Fitzgerald v. Thomas, 61 Mo. 499; Davitt v. Smith, 63 Mo. 266; Seibel v. Siemon, 5 Mo. App. 305; Holland v. McCarty, 24 Mo. App. 83; Miller v. Hoffman, 26 Mo. App. 199.
Another contention of the appellant is that the four months within which the lien could be filed for most' of the material had expired prior to the filing of same. The basis of this contention is that all the lumber for the house as originally contracted for, was delivered by the respondent between July 14 and October 25, 1902. The lien was filed April 9, 1903, and more than four months after the date of the last item furnished for building the house according to the contract and specifications. Other material which went into the construction of the building was sold and delivered December 10, 1902, and within four months of the filing of the lien; but appellant contends this material was furnished under a new and distinct contract for extra work. Just what the original contract contained and whether it had any provision for changes in the building and extra work, we are not advised; because if the contract was introduced in evidence,
In Scott v. Cook, 8 Mo. App. 193, the building was to be finished on November first and was accepted as completed on October 29. The subcontractor who had done the painting and glazing of the house and had completed that work, put in and painted some weatherstrips December. 6 by direction of the original contractor. That subcontractor was denied a lien for the work done under the first contract as having been filed out of time, because of the completion of the original contract and the acceptance of the house; as to which matters he was as fully advised as the original contractor himself. Like facts appear in Hayden Slate Co. v. Anderson, 76 Mo. App. 281. That plaintiff had slated the ro,of of a house under a subcontract with Anderson Brothers, the original contractors to build the house, and had accepted an order on the owner in full payment for the job, but the owner refused to honor it. The entire work was finished in October, 1896, but some repairs had to be made on the roof in August, 1897, and those repairs were relied on by the slate company to keep alive their lien for all the work they had done. It was ruled that the jury were justified in finding the work had been completed the preceding October and the building delivered to the owner in January, 1897; which facts the slate company knew. In Miller v. Herbert, 62 Mo. App. 682, the Rohan Boiler Company did work and furnished material in the construction of a building for Herbert, the contractor, and filed a lien for a balance covering some work done more than six months before the final completion and acceptance of the plant. It was conceded this extra work was
In the present case the Darlington Lumber Company and Taylor agreed to the estimate of the lumber to be used in Harris’ building. Considerable extra lumber was furnished all along under the original contract, and the undisputed testimony is that when the lumber was ordered for the extra work, for which Taylor had made a separate bid, the respondent company made no fresh arrangement with him and knew nothing about there being a fresh contract between Taylor and Harris, or that they were furnishing material for a job to be done under a distinct contract. This material was charged on a running account with Taylor which had been continuous from the time he began to build Harris ’ house. These facts bring the case within the orbit of decisions holding that when materials are furnished for the same improvement, in installments and at intervals, but the parties intend them to be included in one account and settlement, the entire account will be treated as a continuous and connected transaction and the lien limitation will begin to run from the last item of it. Page v. Bettes, 17 Mo. App. 375; Pullis v. Hoffman, 28 Mo. App. 666; Bruns v. Braun, 35 Id. 337; Lumber Co. v. Planing Co., 87 Id. 671. The essence of this matter is that one rounded and completed transaction for which a lien will lie, will not be seized by the law as a means to resuscitate a defunct lien pertaining to an entirely distinct transaction. Practically no showing was made that the respondent furnished the lumber for the extra
Judgment affirmed.