The plaintiff, Frederick Darling, was injured when the ditch in which he was working caved in on him. He brought this action to recover
The plaintiff’s claims of proof include the following: Anderson-Wilcox, Inc., a builder and land developer, by its president, John Wilcox, hired the defendant Burrone Brothers, Ine., as independent contractors, to excavate a ditch to accommodate a storm sewer. There were three steps in the procedure used in digging the ditch: The defendant Joseph Burrone, an employee of the defendant Burrone Brothers, Inc., would dig with a machine called a backhoe; the plaintiff and Charles Mansolf, a coworker, both employees of Anderson-Wilcox, Inc., would smooth the bottom of the ditch with a shovel, guide a section of sewer pipe into place and pack earth around it to keep it from moving laterally; a Burrone Brothers, Inc., employee, the defendant Stephen Kopylec, would then backfill the trench, i.e., push the excavated earth back into the ditch with a bulldozer. The plaintiff was required to be in the ditch throughout the operation. During the backfilling, he would use a shovel to deflect rocks from falling into the sewer pipe.
A one-inch water pipe, or lateral, crossed the path of the ditch, running perpendicular to it. Joseph Burrone told the plaintiff to backfill around the lateral. Having done so, the plaintiff remained in the ditch, standing on the sewer pipe, and watched the backhoe operation. While the plaintiff was in this position, the bulldozer and backhoe were operating and causing vibrations, as did a nearby railroad. The earth which Joseph Burrone dug contained bony gravel and was unstable. Joseph Burrone made no inspection to determine its character; nor did he slope, brace, or shore the walls of the ditch to
The defendants have assigned as error the refusal of the court to include in the plaintiff’s claims of proof six paragraphs which they claim the plaintiff offered as evidence and claimed to have proved. A party to an action may not force into the claims of proof of his adversary factual matters on which the latter does not rely.
Franks
v.
Lockwood,
The defendants’ claims of proof include the following: Anderson-Wilcox, Inc., engaged Burrone Brothers, Inc., as a subcontractor to excavate a ditch for storm sewers, at an hourly rate for its machines and two of its men. Both the machines and the men were subject to the orders of John Wilcox, who had charge of the job, was continuously present at the jobsite, gave orders periodically and was the plain
Joseph Burrone had no responsibility for the work at the water lateral. Because the backhoe could not remove earth around the lateral without pulling out the lateral, excavating and backfilling around it had to be done by hand shovel by the plaintiff or Mansolf. Sloping near the lateral also had to be done in this fashion. The plaintiff backfilled the ditch by hand shovel in the area of the lateral. After backfilling the lateral, he stood in the ditch for more than ten minutes. While the plaintiff was standing there, two or three feet from the lateral, a slide-in occurred, at which time the backhoe was not in operation and the bulldozer was thirty to thirty-five feet away. The
The defendants attack forty-four paragraphs in the plaintiff’s offers of proof in the finding as being unsupported by the evidence. An examination of the appendices adequately supports forty-one paragraphs so attacked by the defendants. One paragraph attacked is of no significance and need not be considered. The finding is corrected as to the two remaining claims: The evidence printed in the appendices supports a finding that a “couple” of feet of gravel were removed above the lateral rather than a few feet and the finding is so corrected; the paragraph in the finding stating “[ajceording to defendant Joseph Burrone, the accident occurred because of the operation of the bulldozer” is deleted.
The defendants assign as error the court’s instruction that as a matter of law the defendants were in charge of the excavation of the ditch and thus in control, without putting the issue of control to the jury for their determination. Where the evidence is such that the minds of fair and reasonable persons could reach but one conclusion as to the identity of the person exercising control, the question is one for the court but, if honest and reasonable persons could fairly reach different conclusions on the question, then the issue should properly go to the jury for their determination.
Trainor
v.
Frank Mercede & Sons, Inc.,
The defendants claim that Burrone Brothers, Inc., received compensation on an hourly basis for its two men and equipment; that John Wilcox told Joseph Burrone where to dig and how deep to dig; that Wilcox located the lateral; that the plaintiff and Mansolf were employees of Anderson-Wilcox, Inc.; that John
The manner of remuneration, whether in wages, salary, commission, by piece or job, is not decisive or controlling in determining whether one is an employee or an independent contractor exercising control over the manner of his own work.
Bourgeois
v.
Cacciapuoti,
The fact that John Wilcox was present at the job site, indicated to Joseph Burrone where to dig the ditch and how deep to dig it, periodically checked to make sure the depth was accurate and marked the area establishing the location of the lateral by sticks imbedded in the ground signifies no more than the furnishing of specifications for the job. It does not demonstrate control of the manner and means of accomplishing the digging. It is apparent that John Wilcox did no more than exercise his right to supervise the general result and also the immediate results, from time to time, as the work progressed.
Pribulo
v.
Chiarelli,
The defendants admitted by their own offers of proof that Joseph Burrone exercised his own judgment as to the amount of slope which was needed for the adequate protection of persons and property in the ditch; that he decided how wide the ditch was to be at the top; that when he approached the area where a post indicated the location of a lateral he was the one who decided to excavate to the full depth of the trench up to six to nine inches from the south side of the lateral; that he was the one who decided to take two feet of earth from above the lateral; and that it was he who decided where to resume digging the full depth of the ditch on the other side of the lateral.
An analysis of the evidence shows that all the testimony as to actual physical events points directly to Burrone Brothers, Inc., having control. The only testimony pointing in a different direction is that of Joseph Burrone in which he claims that he was subject to the orders of John Wilcox and that he had no
In examining the claims of proof of both parties, and especially those of the defendants, it is apparent that the manner and means of excavating the ditch was in the control of Burrone Brothers, Inc. The status of the defendant Burrone Brothers, Inc., as a matter of law, therefore, was that of an independent contractor. In
Alexander
v.
R. A. Sherman’s Sons Co.,
The general rule is that where the owner of premises employs an independent contractor to perform work on them, the contractor, and not the owner, is liable for any losses resulting from negligence in the performance of the work.
Wright
v.
Coe & Anderson, Inc.,
The defendants contend that a special situation existed as to the water lateral, especially militating against a finding of control by the def endant Burrone Brothers, Inc., at this location. In support of this claim, the defendants relied on testimony to the effect that its machinery was too gross to allow excavating, sloping and backfilling around the lateral and that, as a result, complete responsibility for the area rested in the hand labor of the plaintiff, Mansolf, and John Wilcox, their employer. The court charged on the duty of the defendants to the plaintiff while on the job site but stated the following: “Third: he [Joseph Burrone acting for the defendant Bur
The defendants also attack the court’s charge that a workman “is not required to be on the alert to discover” dangers. Specifically, the trial court charged: “The workman has a right to expect that the excavator will take reasonable care to ascertain the actual condition of the working area and having discovered it, either will make it reasonably safe or will give the workman adequate warning of the actual condition and of the risk involved therein. Therefore,
The charge of the trial court closely followed the language of Restatement (Second), 2 Torts, p. 217, § 343, comment d and is a correct statement of the law.
Newell
v.
K. & D. Jewelry Co.,
Smith
v.
L. & S. Corporation,
The defendants also attack forty-three paragraphs of the charge, an additional three narrative paragraphs on the ground of prejudice, the failure to charge as requested in seven paragraphs of their requests to charge and the court’s failure to use two paragraphs of their draft finding as its narrative of the facts bearing on an evidentiary ruling. Aside from those issues which we have already discussed and which are determinative of a great number of these claims of error and those abandoned by the defendants, only two of these assignments require discussion. The defendants’ claim that the court erred in failing correctly to charge on contributory negligence is without foundation. It is true that the court did not use the exact language requested by the defendants, but the charge adequately instructed the jury on this element of the case.
Mace
v.
Conde Nast Publications, Inc.,
The defendants further claim that the verdict of $150,000 was excessive. The court denied a motion to set aside the verdict as being excessive, setting forth its reasons in a memorandum of decision. The ruling of a trial court on a motion to set aside a verdict is entitled to great weight.
Marin
v.
Silva,
There is no error.
In this opinion the other judges concurred.
