Danka Office Imaging Co. v. General Business Supply, Inc.Danka Office Imaging Co. v. General Business Supply, Inc.
Appeal from a judgment of the Supreme Court (Malone, Jr., J.), entered July 11, 2002 in Albany County, upon a decision of the court in favor of defendant.
Plaintiff commenced this action for breach of contract to recover $19,670.47 in unpaid installments allegedly owing under two equipment service agreements between the parties. These successive written agreements covered one used, high-speed, computer network printer that came into the possession of defendant, a commercial printer, as a result of plaintiffs proposal that defendant lease or purchase two such printers at low cost from a third party while paying plaintiff to maintain the printers under a service agreement. Although it never leased or purchased either one of the printers, defendant did receive them, attempted to use one of them for several months, and executed two service agreements referencing that one printer. As a defense and counterclaim, however, defendant asserted that plaintiff never successfully performed an ancillary oral contract in which plaintiff allegedly had agreed to integrate the printer into defendant’s existing computer network so that documents transmitted from local and remote computers connected to the network could be successfully printed. The consideration for this contract was defendant’s payment of $3,500.
Viewing plaintiff’s performance of the oral contract as a condition precedent, Supreme Court (McNamara, J.), in its decision denying summary judgment to both parties, found a question of fact as to the threshold issue of whether the parties’ oral agreement had required plaintiff to make the printer fully functional on defendant’s network or to merely bring the printer itself up to its manufacturer’s specifications. Although the parties’ motion papers are not included in the record on appeal, we note that the court stated: “The parties are in apparent agreement that the service contract was to be effective only if a condition was met.” After a nonjury trial, Supreme Court (Malone, Jr., J.) found that performance of the oral contract had been a condition precedent to the service agreements going into effect, the contract had required plaintiff to make the printer function successfully on defendant’s network, and plaintiff had failed to perform as promised. Based on these findings, the court dismissed plaintiff’s causes of action and awarded defendant damages on its counterclaims in the amount of $25,119. Plaintiff appeals.
In reviewing the decision rendered following a nonjury trial,
While plaintiff now contends that performance of the oral contract was not a condition precedent and that the service agreement disclaimers bar defendant’s claims, the evidence establishes that defendant executed the service agreements premised on plaintiffs oral promise that the printer would be fit and operational for defendant’s purposes. Plaintiff’s own witnesses testified that use of the printer on the network was integral and necessary to the type of printing defendant wished to perform, and plaintiff’s employees both brought the printer up to manufacturer’s specifications and physically connected it to defendant’s existing network. Defendant’s expert, John Deep, testified that the printer’s inability to perform as desired was the result of its incompatibility with a Sun Microsystems server, and other undisputed evidence showed that the server being used was furnished by plaintiff to resolve the printing problems. Thus, it is clear that plaintiff undertook to both make the printer function on the network and to resolve the difficulties in doing so by furnishing additional equipment. Supreme Court’s finding that plaintiff breached the oral contract and that this breach prevented the service agreements from going into effect is based largely on a determination of the credibility of the witnesses’ testimony (see R.W. Granger & Sons v City School Dist. of Albany,
We reach a different conclusion, however, as to three of the four items of damages awarded to defendant. In its counterclaim and at trial, defendant asserted that it was seeking only three items of consequential damages. First, John Smith, defendant’s owner, testified that defendant made a good faith attempt to complete performance of the oral contract by paying Deep $8,100 for his efforts to make the printer functional on
However, Supreme Court’s award of the other two items of consequential damages finds no similar support in the record. To the extent that the court awarded defendant $6,594 for approximately 600 hours of work by defendant’s employees in attempting to integrate the printer into its network, we note that Smith testified as to the number of hours worked, but neither he nor anyone else testified as to the value of this labor. Thus, the dollar amount awarded in the court decision is based solely on a statement in defendant’s unverified counterclaim and must be reversed. Supreme Court’s award of $6,925 as compensation for the “credits” given by defendant to one of its customers, First Albany Corporation, is also flawed. Smith testified that this amount could not be billed to First Albany due to the printer’s failure to perform properly. Even assuming that this item of consequential damages was foreseeable and within the contemplation of the parties (see e.g. American List Corp. v U.S. News & World Report,
Supreme Court’s award of the fourth item of damages in the amount of $3,500, which represents the consideration paid by defendant to plaintiff pursuant to the oral contract, is precluded because there is no indication in the record that defendant ever pleaded or otherwise gave plaintiff notice that it was seeking such direct damages and never moved to conform its pleadings to the proof. While plaintiff moved at the close of its case to conform its pleadings to the proof pursuant to CPLR 3025 (c), and Supreme Court ultimately granted plaintiffs motion in its written decision, there is no indication in the record that defendant also sought or was granted such relief. Although the contract price is prima facie the measure of such damages (see Ware Bros. Co. v Cortland Cart & Carriage Co.,
Finally, we find no error in Supreme Court’s designation of an intermediary date for interest to begin accruing on this damage award because the damages accrued at various times (see CPLR 5001 [b]). Since Deep worked for defendant from May to September 1998, we find the court’s selection of July 31, 1998 was reasonable (see Hanover Data Servs. v Areata Natl. Corp.,
Mercure, J.P., Spain, Carpinello and Lahtinen, JJ., concur. Ordered that the judgment is modified, on the law and the facts, by reducing the damages awarded to defendant to $8,100, and, as so modified, affirmed.