Norman C. DANIELSON, Plaintiff-Joint-Appellant,† TOWN OF BURKE, Intervening-Plaintiff-Joint-Appellant, v. CITY OF SUN PRAIRIE, Defendant-Respondent.
No. 99-2719
Court of Appeals of Wisconsin
September 28, 2000
2000 WI App 227 | 239 Wis. 2d 178 | 619 N.W.2d 108
Submitted on briefs May 19, 2000. †Petition to review denied.
On behalf of the intervening plaintiff-joint-appellant, the cause was submitted on the briefs of Karl L. Kliminski of Boushea, Segall, Joanis & Johnston of Monona.
On behalf of the defendant-respondent, the cause was submitted on the brief of Richard K. Nordeng of Stafford Rosenbaum LLP of Madison.
Before Dykman, P.J., Eich and Roggensack, JJ.
¶ 1. ROGGENSACK, J. Norman Danielson and the Town of Burke appeal a judgment of the circuit court that concluded the City of Sun Prairie was relieved from seeking prior approval of the Town before the condemnation for or the construction of a City sewer interceptor on Danielson‘s property and that the City was not required to make a relocation order as the first step in its condemnation of Danielson‘s property. Because we conclude that
BACKGROUND
¶ 2. The City condemned for an easement to place a sewer interceptor2 for the City‘s sewer system on Danielson‘s property in the Town of Burke. Danielson commenced this lawsuit pursuant to
¶ 3. The City contends that no approval from the Town was required prior to either condemnation or construction because the sewer interceptor is not a construction of the type referred to in
¶ 4. The circuit court concluded that Danielson and the Town were correct about permission being required prior to both condemnation and construction. However, it determined that the City was relieved of its obligation to obtain the Town‘s approval because the Town did not respond to a letter that the City sent to it. The City‘s letter asserted that, although the City believed no town-approval was required, it was nevertheless requesting it for the project. When the Town did not respond, the circuit court construed the lack of a response as a waiver. The circuit court also concluded that
DISCUSSION
Standard of Review.
¶ 5. This court applies the same summary judgment methodology as does the circuit court. See Smith v. Dodgeville Mut. Ins. Co., 212 Wis. 2d 226, 232, 568 N.W.2d 31, 34 (Ct. App. 1997). We first examine the complaint to determine whether it states a claim, and then we review the answer to determine whether it joins a material issue of fact or law. See id. If we conclude that the complaint and answer join issue, we examine the moving party‘s affidavits to determine whether they establish a prima facie case for summary
¶ 6. Here, both parties moved for summary judgment. Neither party disputed the facts which are material to the summary judgment motions. Therefore, the questions before us are those of statutory interpretation, or the application of statutes to undisputed facts, which we decide de novo. See Cemetery Servs., Inc. v. Department of Regulation and Licensing, 221 Wis. 2d 817, 823, 586 N.W.2d 191, 195 (Ct. App. 1998). Additionally, whether a statute is ambiguous is a question of law which we review without deference to the circuit court. See Awve v. Physicians Ins. Co. of Wisconsin, Inc., 181 Wis. 2d 815, 822, 512 N.W.2d 216, 218 (Ct. App. 1994).
WISCONSIN STAT. § 60.52.
¶ 7.
(1) With the approval of the town board, any city or village adjoining a town may construct and maintain extensions of its sewer or water system in the town. An extension of a sewer or water system under this subsection is subject to s. 62.175(1) and the rights of abutting property owners.
(2) An abutting property owner who is permitted to connect with and use a sewer or water system constructed under sub. (1) may not be deprived of the use of the sewer or water system,
except for nonpayment of water or sewer charges, without the approval of the town board.
¶ 8. The contentions of the parties require us to determine the meaning of the statutory phrase “extensions of its sewer or water system in the town.” As we do so, our efforts are directed at determining and applying legislative intent. See Truttschel v. Martin, 208 Wis. 2d 361, 365, 560 N.W.2d 315, 317 (Ct. App. 1997). We begin with the plain meaning of the language used in the statute. See id. If the language is clear and unambiguous, our inquiry ends, and this court must apply that language to the facts of the case. See id. However, if the language used in the statute is capable of being understood by reasonably well-informed people in more than one way, we will determine legislative intent from the words of the statute in relation to its context, subject matter, scope, history, and the object which the legislature intended to accomplish. See id. at 365-66, 560 N.W.2d at 317.
¶ 9. The appellants and the respondent contend that the provision of
¶ 10. To determine which interpretation best effects the intent of the legislature, we examine the
¶ 11.
(16) WATER MAINS AND SEWERS OF ADJOINING MUNICIPALITY. To grant to any adjoining city or village permission, in the extension of its water or sewage systems, subject to . . . the rights of abutting property owners, to lay and maintain water mains
and sewers in any street or highway in the town, and no abutting property owner who is permitted to connect with and use any such water main shall be deprived of the use thereof, except as to the use of water for nonpayment of water charges, without the consent of the town board.
NOTE: Restates s. 60.29(16), except that the current provision which prohibits depriving an abutting property owner from use of a water system is amended to include an abutting property owner‘s use of a sewer system.
Therefore, we conclude that the legislative history of
¶ 12. Finally, it makes sense that the legislature intended to recognize a town‘s interest in an extension of a city‘s sewer or water system in the town if the extension would have an impact on town residents, such as providing and charging for water or sewer service or reviewing the quality of service provided. Giving a town a right to prior approval for that type of an extension is a logical way for the legislature to have provided for a town‘s interest in ensuring that the needs of its residents are met. However, a town would
¶ 13. With the interceptor constructed on Danielson‘s property, the effect on the town resident is from the condemnation for the interceptor‘s easement, and ch. 32 provides for that interest in a uniform manner throughout the state. Therefore, we conclude that interpreting the “extensions of [a city‘s] sewer or water system in the town” as applying to extensions which can provide service to residents of the town effects the legislature‘s intent. Additionally, because towns have no home rule powers but only those powers specifically delegated to them by the legislature or necessarily implied therefrom, see Pugnier v. Ramharter, 275 Wis. 70, 73, 81 N.W.2d 38, 40 (1957), we conclude that the City was not required to seek Town approval prior to either the condemnation for or the construction of the interceptor at issue here.3
WISCONSIN STAT. § 32.05(1).
¶ 14. Most condemnations require that the condemning municipality make a relocation order pursuant to
¶ 15. Danielson‘s argument requires us to interpret
RELOCATION ORDER. (a) Except as provided under par. (b), the . . . city council . . . shall make an order providing for the laying out, relocation and improvement of the . . . storm and sanitary sewers . . . which shall be known as the relocation order. This order shall include a map or plat showing the old and new locations and the lands and interests required. . . .
(b) No relocation order is necessary under par. (a) if the compensation, as estimated by the
appraisal under sub. (2)(a), will be less than $1,000 in the aggregate.
¶ 16. We note that nothing within subsec. (1), on its face, requires that a relocation order be the first step in a condemnation process. Furthermore, para. (1)(b) presumes that an appraisal will be made before a relocation order because a relocation order is not required if the compensation due to the landowner is “estimated by the appraisal under sub. (2)(a), [to] be less than $1,000 in the aggregate.” If the condemning municipality were required to make the relocation order as the first step, it would not have the information to determine whether to comply with para. (1)(a) or (1)(b). Additionally, and in contrast to the legislative directive of subsec. (1), subsec. (2)(a) does require that certain steps to be taken before making a jurisdictional offer. It provides:
Before making the jurisdictional offer provided in sub. (3), the condemnor shall attempt to negotiate personally with the owner. . . . Before attempting to negotiate under this paragraph, the condemnor shall provide the owner or his or her representative with copies of applicable pamphlets prepared under s. 32.26(6).
Therefore, we agree with the City that when the legislature intended to require the condemnor to use the ch. 32 process in a particular sequence, it clearly stated that intent.
¶ 17. Furthermore, we are not persuaded by the cases cited by Danielson to support his assertion that the courts have interpreted
¶ 18. In Toombs, again, the timing of the relocation order was never a concern. The county had made the order at the commencement of the condemnation proceedings, but other factors about the order caused it to be invalid. See Toombs, 119 Wis. 2d at 347, 350 N.W.2d at 721. However, its invalidity was not the focus of the appeal; rather, the appeal focused on whether the landowner was entitled to litigation fees under
¶ 19. Also in Wisconsin Town House Builders, the timing of the relocation order was not necessary to the court‘s decision. The case turned on whether the city had to pay a landowner for lack of access to a limited-access road constructed along the plaintiff‘s property, when no roadway had existed prior to construction of the road for which the condemnation process was being used. See Wisconsin Town House Builders, 37 Wis. 2d at 50, 154 N.W.2d at 234-35. Therefore, we conclude that the City‘s relocation order provides no basis for Danielson‘s assertion that the City‘s condemnation process was defective.
CONCLUSION
¶ 20. Because we conclude that
By the Court.—Judgment affirmed.
Norman C. DANIELSON, Plaintiff-Joint-Appellant, v. CITY OF SUN PRAIRIE, Defendant-Respondent.
Court of Appeals of Wisconsin
September 28, 2000
With the approval of the town board, any city or village adjoining a town may construct and maintain extensions of its sewer or water system in the town.
¶ 22. The majority has concluded that what this statute really means is:
A city or village adjoining a town may construct an interceptor sewer within the town without the permission of the town board.
¶ 23. The way that the majority reaches its conclusion is to conclude that
¶ 24. I believe that if the twenty-eight relevant words of
¶ 25. The City of Sun Prairie‘s position, which the majority adopts, is that the twenty-eight words really refer only to the construction of the part of a sewer system that extends sewer service in a town. The reason why I part company with the City and the majority is that I cannot see how the concept of “hooking up to a sewer” is found within those twenty-eight words. The statute pertains to a “sewer or water system.” The majority might have concluded that a sewer interceptor is not a “sewer or water system.” This conclusion, though it runs aground on the facts, at least does not torture the English language. I do not find it possible, using the conventions of the English language, to bring within the twenty-eight operative words, the foreign concept of town residents being unable to drain their kitchen and bathroom waste water pipes into the city‘s interceptor. That concept is just not there.
¶ 26. The majority‘s answer to this is its conclusion: “We agree that both interpretations are reasonable interpretations for well-informed people to make.” While I accept that this is a conclusion, I do not agree with it. Most inquiries into statutory meaning explain why a statute can be read one way or another. See, e.g., Kurylo v. Wisconsin Elec. Power Co., 2000 WI App 102, ¶ 7, 235 Wis. 2d 166, 612 N.W.2d 380. For example, in Kurylo, we explained, “[b]ecause the statute is silent regarding the time for filing the [certificates], it could reasonably be read to mean the [certificates] and conveyance must be filed simultaneously or that they may be filed at different times.” Id. If there is no answer to the question “Why can the statute be read with two meanings?” it seems to me that the real answer is that the statute is unambiguous.
¶ 27. I need not examine the legislative history examined by the majority because having concluded that
