200 Misc. 657 | New York Court of Claims | 1951
This suit was brought to recover damages for breach of contract and for extra work, labor and services performed. After the matter was at issue the parties consented to entry of judgment in favor of claimants in the sum of $29,835.87, the balance admitted by the defendant to be due and owing upon the contract for the quantities furnished in constructing a highway at the line item prices. The award was made without interest and the question of the right to recover interest was directed to be held in abeyance until the trial of this part of the claim. We shall consider this question later.
After the severance of the first cause of action and after the entry of judgment thereon, claimants, upon due notice, moved to amend their claim by adding thereto allegations of certain items of extra work, labor and services performed not included in the sum awarded as hereinabove recited and not previously pleaded. The motion was granted and an order of amendment granted. Although the Attorney-General appeared and opposed the motion and at the time did not claim surprise nevertheless he again attacks the ruling of the court and, since he does, we make comment. The Attorney-General’s position is not well taken. All of the items pleaded and on which proof was offered arose out of the work of construction under the contract and the circumstances surrounding these disputes were or should have been within the knowledge of the engineers who represented the
Claimants entered into a contract with the State of New York to construct a farm to market, or secondary, road known as the Phoenicia-Stony Clove Highway, Part 2, FAS SH 47-9 State highway. The construction was to be three miles of grading, drainage and bituminous macadam pavement. The road ran through the Catskill State Forest Preserve and where it deviated from the old location the highway was to be built on lands owned by the State of New York as part of the Preserve. Item No. IS of claimants’ itemized proposal was for the necessary quantities of clearing and grubbing, a lump sum bid in the amount of $2,331.87. Before preparing their bid claimants inspected the site and found, in the area to be cleared and grubbed, a timber growth. There being nothing in the contract to prohibit them, claimants planned to salvage the timber from the areas which they would clear and grub and to sell it at a profit and they made their lump sum bid accordingly. Claimants’ bid was filed and accepted on September 17, 1947. Thereafter and before the written contract was signed claimants were informed by a representative of the Department of Public Works that the State Conservation Department demanded that the trees cut in clearing for the building of the new road be piled in four foot lengths on the right of way and made available for crews of that department to collect for use on State recreational campsites. This information was available to the Department of Public Works on September 16, 1947, but was not made known to claimants until September 30, 1947. Thereupon claimants offered to fell the trees if the State would remove them so that claimants could proceed with their work. There ensued extended correspondence, in writing and by telephone, between the State Department of Public Works and the State Conservation Department in which i lie latter department amended its requirements with respect to
To this item of the claim the State offers several defenses. The first is that section 1 of article XIV of the Constitution, which provides that the forest preserve shall be forever kept as wild forest lands and that the timber thereon shall not be sold, removed or destroyed, prohibited claimants from availing themselves of any salvage from the trees and that they should have known the law and the Constitution before they bid. The fact is that the plans for the highway to be built through the forest preserve necessarily contemplated that a certain amount of growing timber would be cut, removed or destroyed. The Attorney-G-eneral concedes as much. This was a proper exercise of authority by the State Department of Public Works. (L. 1921, ch. 401, as amd. by L. 1937, ch. 488.) As the plans did not call for the removal of timber to any material or unreasonable degree, the Constitution was not violated. (Association for Protection of Adirondacks v. MacDonald, 253 N. Y. 234 [1930].)
A second defense interposed is that the claimants had actual knowledge of the Conservation Department’s demand for the
The Attorney-General’s further defense to the item is that claimants having availed themselves of the lump sum bid for doing all necessary work in the area to be cleared and grubbed cannot recover more than the amount of their bid and this amount they have been paid. Although there is proof that at the time the contract was let there was an available market in the area for timber on the stump, and that the claimants could then reasonably anticipate the sale of the timber at a profit, and although findings to such effect have been proposed and are adopted by the court because the proof is uncontradicted, nevertheless, claimants are not suing for the loss of profits. Their claim is for the extra amount of time, labor and use of machinery and equipment involved in the performance of their work due to
Item No. 2 of the claim is based on change of location of the center line of the highway which was shifted to the east to avoid undercutting a mountain of talus on the west side of the right of way. This shift eliminated the necessity of slope protection in the area in question on which claimants had bid $20 a cubic yard for an estimated 250 cubic yards in the performance of which they had expected to net a profit of $3,000. By the shift in location the claimants were deprived of the use of a quantity of cut stone in an existing railroad abutment which they had planned to utilize in the performance of the slope protection item. The shift in the center line of the road extended from Station 128 to 142, a distance of 1,400 feet. It is claimants’ contention that all of the work of excavation and fill required on the right, or westerly, side of the highway was substantially completed before the change in location was directed by the State engineer, which was on or about June 10, 1948. This contention is not supported by the proof. The area had been roughly graded but we are unable to make a finding as requested by claimants that the work of excavation “ was substantially completed.” According to the State engineer’s testimony there was approximately 900 cubic yards of material yet to be removed on the left side between the stations mentioned. Claimants’ counsel asserts in his brief that the removal of this material would have been profitable to claimants but their demand is not based upon the denial of a certain amount of excavation. Bather, claimants seek to recover the extra cost of performing an estimated 400 cubic yards of excavation in the new location on the right hand side of the road. For this excavation they have been paid at the contract item price. It appears that the material excavated was not dissimilar to that on the left hand side of the road. We are unable to find in the record sufficient proof to support a finding that claimants are entitled to recover anything extra on this item. With respect to the elimination of the slope protection it appears that claimants agreed to the deduction of 144 cubic yards by supplemental agreement No. 1, dated August 20, 1948. By this they are estopped from recovery. (QuinnMeissner, Inc., v. State of New York, Claim No. 25251 [1941], ffd. 268 App. Div. 936.) It does not appear that the additional
Item 3 of the claim deals with 538.2 tons of crushed stone chips not provided for in the original contract but furnished and rolled by claimants as an extra for which they have been paid the agreed price of $4 per ton. The basis of claimants’ demand is that they were induced to agree to the said price by the representations of the State’s engineer who stated that the stone could be purchased from the Catskill Mountain Stone Company and by that company delivered and spread ready for rolling at a price of $3.55 per ton and that the State would pay claimants 45?.; per ton for rolling it. The said stone company furnished and delivered the stone but declined to spread it and claimants sue on a quantum meruit for the work, labor and services performed by them in excess of the amount which they have been paid. There can be no recovery on this item. All that 0 ’Haro, the State engineer, did was to telephone the Catskill Mountain Stone Company and relay to Thomas A. D’Angelo, one of the claimants, who was present in his office at the time, the price quoted to him. Mr. D’Angelo testified that Mr. O’Hara “ made all arrangements. ’ ’ But upon inquiry by the court as to whether he had any recollection of confirming the order with the Catskill Mountain Stone Company, the witness replied “ All I confirmed was the price ”. Surely if the claimant D’Angelo did not take the trouble to inquire from the purveyor of the stone what would be included in the price he cannot charge the State for his omission. He was capable of making his own terms with the stone company. We find that O’Hara did not intentionally nor unintentionally misrepresent to D’Angelo what the stone company’s representative said the company would do for the price quoted. There may have been a misunderstanding. But if the stone company repudiated its offer the State of New York cannot be held liable for the extra expense caused the claimants.
Items 4 and 5 of the claim are based on the difficulties which the claimants had with the natural material which they encountered when they excavated for the roadbed of the highway. This material contained large boulders and was not easily manipulated. It was unsuitable for fill and the claimants proposed to the engineer in charge that they would substitute for it finer material to be drawn from a gravel pit located near the south end of the project. They assert that they supplied 10,000
Claimants further contend that in fill sections where the natural material was used the engineer in charge required them to bulldoze and push the large boulders beyond the “ neat lines ”, or limitations of the contract work, and that in so doing finer and suitable material was spread and wasted. They demand payment for an estimated quantity at the overhaul price of one cent per cubic yard per station hauled. Again, there was no measurement showing the quantity of overhaul furnished and the demand of claimants for payment for an additional 114,066 cubic yards is purely an estimate. It appears that the large boulders “ caused no difficulty in making the heavy fills ” but as the fill got to the higher elevations it was necessary to eliminate them. The direction by the engineer that this be done was proper. This item (5) is disallowed.
The remaining items of the claim are No. 6, for trimming road sections, for which we make an award of $8,713.50, No. 7, for extra excavation between Stations 138 and 140, for which we make an award of $1,465.15, and No. 8, for extra work performed beyond the demands of the contract for scarifying gravel and for the delays resulting therefrom, for which we make an award of $3,000, the amount demanded by the claimants and which we believe to be fair and reasonable and supported by the record.
In computing damages on Items 1, 6 and 7, we have adopted the figures in claimants’ Exhibits 8, 28 and 33 for cost of labor,
We now consider the question of interest on the sum of $29,835.87, the amount of the judgment previously entered in favor of the claimants. Their work was completed December 6, 1948, and accepted by the State of New York on December 21,1948. The State completed its final estimate on February 9, 1949. This lapse of time was not unreasonable. (Banko, Inc., v. State of New York, 186 Misc. 491 [1946], supra.)
The awards under Items 1, 6, 7 and 8, of course, carry interest from February 9,1949, to the date of entry of judgment.
Decision in accordance with the foregoing.
See, also, Rusciano & Son Corp. v. State of New York (Claim No. 28309. [1050], Finding 89, affd. 278 App. Div. 999).
The decision of the Third Department in Busciano é Son Gorp. v. State of New York (Claim No. 28,309, 278 App. Div. 999) cited supra in footnote 1, was handed down while the issues on the several items in this claim were under consideration and after we had written the above sentences on the subject of interest for incorporation in this opinion. The Third Department reiterates the rule expressed in Agostini v. State of New York (Claim No. 24,345, 255 App. Div. 264 [1938]) and upholds our award of interest in Banko, Inc., v. State of New York (Claim No. 25,336, 186 Misc. 491, supra [1946]) and other similar cases.