43 A. 621 | N.H. | 1898
This is an action to recover the balance due upon contract price for building a house, with sundry claims for extra work. The case has been heard by a referee, who states the account between the parties, in which he allows the plaintiffs the contract price and sundry items of extra labor and material, in all $3,234.58, and allows the defendant sundry cash payments and items for failure to comply with the terms of the contract, amounting to $2,923.35, and finds due the plaintiffs $311.23. The questions reserved upon the referee's report are as to the meaning of the clause in the contract relating to hardware, the allowance made by him for defective painting, and the rule of damages for the plaintiffs' failure to comply with some parts of the specifications. Upon the first question, the specifications, under the head of "Hardware," contain the following: "Allow $45 for hardware. This does not include nails, lead, zinc, window and other fasts, or ordinary builders' hardware, which are *467 to be furnished by contractor. Carpenter to fix all hardware." The contract has not been furnished us, but from the course of the argument we understand that the contract was to build a house for the defendant at a fixed price and according to certain specifications. The plaintiffs in their statement of the account charge the defendant, in addition to the contract price, with certain articles of hardware, and credit him with the allowance of forty-five dollars. That is, the plaintiffs claim the cost of certain articles of hardware in addition to the contract price. The defendant admits he was to pay for all hardware in excess of forty-five dollars, except that which the clause under discussion provided the contractor should furnish, viz., nails, lead, zinc, window and other fasts, or ordinary builders' hardware. As the parties had apparently the same understanding of the general effect of the clause, the only possible ground of difference perceived is as to what particular articles were to be paid for out of the allowance of forty-five dollars, and what were to be furnished by the contractor. The term "ordinary builders' hardware" may have a signification in the building trades designating particular articles of hardware; whatever it includes the contractor was to pay for. If there was dispute upon this question, the report presents no question for our determination, for there is nothing before us upon which to base any opinion as to what articles are covered by the term "ordinary builders' hardware," and the referee's finding that hardware not included in the exception of the value of $55.40 was furnished cannot be disturbed. As provided in the report, including the items admitted by the defendant, there should be allowed on the item of hardware $13.42 instead of $39.46.
The painting was not done in a workmanlike manner, nor as required by the contract. It is found there was no agreement to vary the contract, but that the defendant knew that the work was not being done by the sub-contractor as provided in the specifications and failed to make objections to the contractor in time to stop the work; and on that ground the referee ruled the defendant was not entitled to full damages and allowed fifty dollars only. Whether there was a waiver of strict compliance with any part of the specifications, was a question of fact. Fuller v. Brown,
The remaining question is as to the rule of damages adopted by the referee. It is conceded that the plaintiffs are entitled to payment for their work and materials, and the defendant to an allowance for sundry failures to comply with the specifications; and it is inferred from the whole report that the contract was substantially completed by the plaintiffs, and that the defendant has received the benefit of such work and materials as the plaintiffs have furnished. The only question between the parties is as to the rule of damages by which their respective claims should be determined. Under a special contract for the manufacture or sale of a specific chattel, the purchaser is not bound to accept one differing from the one bargained for though of equal value and usefulness. King v. Rochester,
The plaintiffs are entitled to judgment for $311.23 less $26.04, the erroneous allowance for hardware, or $285.19, unless upon recommittal a different sum be found as damages for the painting.
Case discharged.
All concurred.