Lead Opinion
After a bench trial in this diversity case, the district court ordered Robert Lang and his construction business, Lang Brothers, Inc. (collectively “Lang”) to pay Dan Ryan Builders, Inc. (“Dan Ryan”) limited damages for breach of contract. Dan Ryan appeals, seeking additional damages. We affirm.
I.
We briefly summarize the relevant facts, which are undisputed.
Lang owned seventy acres of land in West Virginia, on which he sought to build a housing development, Crystal Ridge Development. In 2005, pursuant to a Lot Purchase Agreement (“LPA”), Lang subdivided the land and contracted to sell Dan Ryan all 143 lots in Crystal Ridge. The LPA detailed the responsibilities of both parties, including lot inspection, fill compaction, and building schedules.
/ The parties also entered into a number of other written contracts in connection with the development, including a Contract with Independent Contractor (“fill slope contract”). They agreed in that contract that Lang would construct a fill slope that would provide grading on certain lots to accommodate the construction of houses. Lang completed the grading work and was paid in full by Dan Ryan.
In 2006, Dan Ryan paid Lang for the first twelve lots in accord with the LPÁ. Dan Ryan also entered into additional contracts with Lang including a second fill slope contract. In 2007, Dan Ryan purchased another five lots, and Lang continued to work on the infrastructure of the Crystal Ridge Development.
In March 2007, cracks appeared in the basement slab and foundation walls of a partially constructed house on one of the first lots that Dan Ryan had purchased. An engineering firm engaged by Dan Ryan concluded that stabilization of that house, as well as of another house displaying similar cracks, required remediation. These problems and their associated costs exacerbated existing tensions between Dan Ryan and Lang, ultimately leading to a “divorce” (the parties’ term) between the two. The parties memorialized the divorce in the “First Amendment to Lot Purchase Agreement” (the Amendment). Under the Amendment, Dan Ryan agreed to purchase from Lang the remaining thirty-three lots in Crystal Ridge, and the parties’ development responsibilities were apportioned differently.
In December 2009, Dan Ryan filed this lawsuit against Lang seeking monetary damages. In its complaint, Dan Ryan asserts three causes of action. Initially and principally, Dan Ryan alleges negligence by Lang in connection with construction of the fill slope. Second, Dan Ryan alleges that Lang breached several of its contractual duties under both the LPA and the Amendment. The third cause of action alleges fraudulent misrepresentation by Lang; Dan Ryan abandoned this last claim at trial.
Following several pre-trial conferences and numerous pretrial submissions, the district court held a five-day bench trial. The court admitted many exhibits and considered testimony from more than a dozen witnesses. After extensive post-trial submissions,
On the contract claim, the district court awarded Dan Ryan $175,646.25 in damages and $77,575.-50 in pre-judgment interest for breach of the LPA and the Amendment with respect to claims for repairs on the road leading to Crystal Ridge. The court found that Dan Ryan had failed to carry its burden of proof with respect to other asserted breaches of the LPA and the Amendment, i.e., those relating to an entrance easement, a stormwater management and erosion control system, and other “miscellaneous bad work.” J.A. 2353.
We “review a judgment following a bench trial under a mixed standard of review — factual findings may be reversed only if clearly erroneous, while conclusions of law, including contract construction, are examined de novo.” Roanoke Cement Co. v. Falk Corp.,
II.
Dan Ryan offers two reasons why the district court erred in its “gist of the action” holding. We consider each in turn.
First, citing Greenlaw v. United States,
Greenlaw is the Supreme Court’s most robust articulation of the party presentation principle. There, in language on which Dan Ryan rests its claim, the Court stated that “in the first instance and on appeal, ... we rely on the parties to frame the issues for decision.” Greenlaw,
Moreover, neither in Greenlaw nor in any other case has the Court ever suggested that the party presentation principle constrains a court’s fundamental obligation to ascertain controlling law. A party’s failure to identify the applicable legal rule certainly does not diminish a court’s responsibility to apply that rule. The judiciary would struggle to maintain the rule of law were it limited to the parties’ competing assertions about what the law requires. For this reason, it is well established that “[w]hen an issue or claim is properly before the court, the court is not limited to the particular legal theories advanced by the parties, but rather retains the independent power to identify and apply the proper construction of governing law.” Kamen v. Kemper Fin. Servs., Inc.,
Here, West Virginia’s “gist of the action” doctrine is just such an “antecedent” and “dispositive” issue, since it goes to the duty element of any West Virginia tort claim. The “gist of the action” doctrine requires plaintiffs seeking relief in tort to identify a non-contractual duty breached by the alleged tortfeasor. See Gaddy Eng’g Co. v. Bowles Rice McDavid Graff & Love, LLP,
We must therefore reject Dan Ryan’s contention that the party presentation principle barred the district court, when adjudicating a West Virginia tort claim, from considering whether the elements of such a claim had been met.
B.
Dan Ryan also contends that the district court erred in holding that the “gist of the action” doctrine dooms its tort claim. This contention is meritless. Given that Dan Ryan’s tort claim rests on Lang’s asserted negligence in performing two contracts — the LPA and the Amendment— and not on any duty independent of those contracts, the “gist of the action” doctrine does indeed bar that claim.
“To prevail in a negligence suit, the plaintiff must prove by a preponderance of the evidence that the defendant owed a legal duty to the plaintiff.” Stratum v. Cleavenger,
Only two years ago, in Gaddy, the West Virginia Supreme Court of Appeals reiterated this requirement. There, the court unequivocally held that a plaintiff cannot recover in tort if the complaint does no more than include “the bare bones aver
Gaddy further explains, in words that resonate here, that recovery in tort will be barred if. any of the following factors is demonstrated: “(1) where liability arises solely from the contractual relationship between the parties; (2) when the alleged duties breached were grounded in the contract itself; (3) where any liability stems from the contract; and (4) when the tort claim essentially duplicates the breach of contract claim or where the success of the tort claim is .dependent on the success of the breach of contract claim.” Gaddy,
In its briefing on appeal, Dan Ryan points to one additional source of Lang’s supposed duty: “[t]he common law duty of care owed by a contractor.” Appellant’s Br. 30. But if, as Dan Ryan contends, “the gravamen of the breach was the failure to construct the fill slope in a good and workmanlike manner,” id. at 31, Lang breached not an independent legal duty but an implied warranty arising out of — in fact, created by — the LPA and the Amendment. See Thacker v. Tyree,
In sum, this is precisely the kind of ease in which plaintiffs claims are “simply breach of contract claims masquerading as” tort claims. Gaddy,
III.
Alternatively, Dan Ryan now seeks damages under contract claims never alleged or even asserted before the district court. Specifically, Dan Ryan contends that the district court should have awarded it damages for a breach of the fill slope contracts.
Nowhere in its pleadings did Dan Ryan assert such a claim. The district court pointed out that Dan Ryan did not reference the fill slope contracts in its original complaint. Indeed, neither Dan Ryan’s Amended Complaint, nor its pre-trial listing of contested issues of fact and law, nor its seventy-eight-page post-trial proposed findings of fact and conclusions of law even mentions the fill slope contracts — let alone alleges that Lang breached them. Dan Ryan concedes, as it must, that this is so. Nevertheless, Dan Ryan ■ maintains that “the absence of explicit reference to the [fill slope contracts] in the pleadings is of no consequence,” because a claim as to breach of those contracts was tried by consent, as permitted by Federal Rule of
That Rule provides that “an issue not raised by the pleadings” mil be treated as if it were raised, provided it is “tried by the parties’ express or implied consent.” Fed.R.Civ.P. 15(b)(2). Of course, Rule 15(b)(2) does not offer a failsafe for any and every faulty pleading. Rather, the Rule sets forth “an exception to the general rules of pleading ... when the facts proven at trial differ from those alleged in the complaint, and thus support a cause of action that the claimant did not plead.” Gilbane Bldg. Co. v. Fed. Reserve Bank of Richmond,
First, the record offers no support for Dan Ryan’s assertion on appeal that Lang expressly consented to trial of any claim of breach of the fill slope contracts. Dan Ryan maintains Lang did so by including, among its pre-trial contested issues of fact, the question of whether “the Lang Defendants [are] liable to [Dan Ryan] for breach of contract in relation to” the fill slope contracts. J.A. 305. But Lang’s single reference to a breach of the fill slope contract in its pre-trial memorandum does not constitute consent.
In fact, as early as the final pretrial conference, Lang pointed out the absence of any reference to the fill slope contracts in the Amended Complaint. Lang’s counsel specifically noted that “there were additional agreements” that “were not attached as exhibits to the complaint” and distinguished the obligations in those unpled contracts from the obligations in the LPA and the Amendment, on which Dan Ryan did rest its contract claims. J.A. 380-81. Similarly, in its post-trial submission, Lang noted that although the fill slope contracts were introduced as evidence at trial, they were not “even mentioned anywhere within the Complaint or Amended Complaint” and so could not provide Dan Ryan with a basis for recovery. Far from consenting to trial of unpled issues, then, Lang consistently and expressly disclaimed any consent to trial on the unpled claim of breach of the fill slope contracts.
Moreover, in Dan Ryan’s own submissions to the district court it confirmed that it did not advance such a claim. Rather, when Dan Ryan raised contract claims at trial, it expressly identified the pertinent contracts that formed the source of the asserted breach — the LPA and the Amendment — not the fill slope contracts. Furthermore, after trial, in its proposed findings of fact and conclusions of law, Dan Ryan set forth in numbered paragraphs each of the damage awards sought for breach of the LPA and the Amendment. Dan Ryan did not devote a numbered paragraph to any damage claim under the
In sum, Dan Ryan’s own statements about the theory of its case, as well as its repeated omission of the now-asserted breach of the fill slope contracts from any argument at trial or post-trial confirm what Lang’s submissions make clear: Lang did not consent to trial of claims for breach of the fill slope contracts. See Pinkley, Inc. v. City of Frederick,
Moreover, Dan Ryan cannot establish Lang’s implied consent by demonstrating that evidence at trial clearly supported only this unpled claim. We have previously explained that admission without objection of evidence related to the unpled claim may be “an indicium of implied consent” to trial of that claim. McLeod v. Stevens,
Dan Ryan contends that consent to trial of a breach claim under the fill slope contracts may be implied from its evidence related generally to the slope failure and from the admission of the two fill slope contracts themselves. But evidence of the slope failure was admitted in support of the claim that Lang negligently constructed the slopes, not that it breached the fill slope contracts.
Moreover, Lang would undoubtedly be prejudiced if we were to accept Dan Ryan’s contention on appeal that the opposite is true. See Withrow v. Williams,
Dan Ryan had opportunities before, during, and after trial to clarify its contract claims against 'Lang.
IV.
This is a messy case, spanning four years and thousands of pages of trial submissions. During the course of such protracted litigation, parties must be vigilant not to lose sight of the necessity of pleading and proving all of the elements of each cause of action.
The district court properly dismissed Dan Ryan’s tort claim, alleging negligence in construction of the fill slope, because Dan Ryan rested that claim solely on asserted breach of two contracts — the LPA and the Amendment. We now hold that Dan Ryan never alleged, and the parties never consented to trial on, a claim of breach of the fill slope contracts. Contrary to Dan Ryan’s contention, this result does not unfairly penalize it for a purely formal error. Rather, it simply holds Dan Ryan to the requirements of the law. A claim grounded on breach of contract (here, the LAP and the Amendment) does not give rise to tort liability, and a claim never pled (here, breach of the fill slope contracts) will not be regarded as pled unless actually tried by consent. These are the only fair standards, for without them litigants and courts alike would be unable to ever adequately prepare for trial. Parties would be forced to defend against shadow claims, and trial courts would be forced to search, as for & needle in a haystack, for unpled causes of action purportedly hiding in the parties’ submissions.
It is not the. responsibility of a trial court to wade through ambiguously or incorrectly labeled allegations in pursuit of any potential basis for awarding relief. In the case at hand, the district court did a commendable job of sorting through a museum of non-sequiturs to identify the plaintiffs meritorious claims. Notwithstanding Dan Ryan’s dissatisfaction with the resulting judgment, it is clear that the district court committed no error.
The judgment of the district court is
AFFIRMED.
Notes
. Dan Ryan concedes that "[t]he district court's findings of fact are beyond reproach.” Appellant's Br. 52. Similarly, Lang does not challenge them in any way.
.The court permitted the parties to submit up to eighty pages of proposed findings of fact and conclusions of law. After the deadline for these submissions had passed, Dan Ryan moved for leave to file a supplemental post-trial memorandum. The district court denied that motion.
. Citations to the “J.A.” refer to the Joint Appendix filed by the parties to this appeal.
. The district court also dismissed as moot the derivative claims Lang had brought against third-party defendant Hornor Brothers Engineering for contribution. Dan Ryan does not appeal that ruling.
. We note that third-party defendant Hornor Brothers Engineering did develop the "gist of the action” doctrine in its post-trial submissions to the district court. See J.A. 2186-88 ("[T]ort liability cannot arise from a breach of contractual duty.... [T]he principle is that if a defendant would have no duty of care to plaintiff but for the fact that the parties have a contract, no independent professional negligence claim may be maintained.” (citing Lockhart,
. This requirement — that a tort claim must rest on a non-contractual duty — is hornbook law in most jurisdictions, even if they do not employ the “gist of the action” nomenclature. See Black’s Law Dictionary (10th ed.2014)(defining "tort” as "[a] civil wrong, other than breach of contract, for which a remedy may be obtained, ... a breach of a duty that the law imposes”); Restatement (Third) of Torts: Liab. for Econ. Harm § 3 (Tentative Draft No. 1, 2012) (explaining the general rule that “there is no liability in tort for economic loss caused by negligence in the performance or negotiation of a contract between the parties”).
. We have said as much before. See Interstate Petroleum Corp. v. Morgan,
. Nor does the district court’s observation that Lang "failed to live up to its contractual obligations” under the fill slope contracts establish that breach of those contracts was tried by consent. J.A. 2375. For the court had earlier identified the LPA and the Amendment as the sole bases for all breach of contract claims alleged by Dan Ryan. See J.A. 2324-56. Further, the court explained that any "[m]ention of the Fill Slope Contract[s] was conspicuously absent from” Dan Ryan’s complaint. J.A. 2373. Thus the court was clear that the claims Dan Ryan might have alleged are distinct from the claims it actually did allege.
. Dan Ryan repeatedly failed to clarify the precise claims under which it sought relief and the specific evidence supporting each
. In the alternative, we hold that Dan Ryan has waived any breach of contract claim based on the fill slope contracts. See Helton v. AT & T Inc.,
Concurrence Opinion
concurring in part and dissenting in part:
Dan Ryan Builders, Inc. (“Dan Ryan”) contracted with Robert Lang and his construction business, Lang Brothers, Inc. (collectively “Lang”) to fix the steep grada
Rule 15(b) allows liberal amendment of the pleadings to conform to the evidence presented at trial. See Equal Emp’t Opportunity Comm’n v. Gen. Elec. Co.,
The majority insists on formalism, finding no implied consent to try the issue of whether Lang - breached the Fill Slope Contract. However, this was the entire gravamen of the five-day trial. We may find implied consent where the defendant: 1) fails to object to evidence relating to the unpleaded issue; 2) actually produces evidence bearing on the issue; or 3) offers direct arguments contesting the issue. See Fed. Prac. & Proc. § 1493; see also McLeod v. Stevens,
In this way, Lang was fully prepared to litigate, and indeed litigated in substance, whether it was “liable to [Dan Ryan] for breach of contract in relation to [the Fill Slope Contract].” J.A. 305 (contested issue from pre-trial statement proposed by Lang). During the trial, “[t]he experts all agree[d] that [Lang Brothers Inc.] did not employ the standard construction practices that, if applied in the first instance, would have ensured the slope’s stability.” J.A. 2374 n.44. It turns out that Lang built the fill slope based on rudimentary drawings that were never meant to serve as a full set of engineering plans and specifications. Lang did not ensure the slope foundation was built according to the proper ratio, and did not install the appropriate draining system, among other failings. Basically, Lang picked up dirt from one part of the development and set it on top of another. The district court had no trouble ascertaining that, according to the “credible evidence,” Lang’s “poor construction practices were the sole proximate cause of the slope failure.” J.A. 2374 n.44.
This is not a case where the evidence “incidentally tends” to establish that Lang’s shoddy construction breached a contractual duty to build a viable fill slope. Pinkley, Inc. v. City of Frederick,
Given the ample notice, implied consent, and utter lack of prejudice to Lang, I would reverse the district court and find a breach of the Fill Slope Contract.
This figure is based on Dan Ryan’s post-trial submission asserting that expenses related to the slope remediation totaled $1,772,104.91 before prejudgment interest. PL’s Proposed Findings of Fact and Conclusions of Law at 70, ECF No. 256.
