187 Mo. App. 691 | Mo. Ct. App. | 1915
This is a suit for damages alleged to have accrued to plaintiff on account of delay in the shipment of stock. Plaintiff recovered and defendant prosecutes the appeal.
The petition seems to jumble the matter of contract and tort, though it clearly states a cause of action sounding in contract. It is averred that plaintiff, desiring to ship two carloads of cattle from De Lassus, Missouri, to the National Stock Yards at East St. Louis, Illinois, entered into a contract for hire with defendant on the nineteenth day of August, 1911, for two cars to be furnished at De Lassus to convey the cattle or the morning of August 22, with a view of transporting them over defendant’s railroad to the market for sale on August 23. ' Plaintiff, relying upon the contract thus entered into, delivered his cattle at De Lassus to be loaded in the cars on August 22, but defendant breached its undertaking, in that it failed and refused to furnish the cars as agreed. Because of this, plaintiff was delayed in transporting the cattle and detained them at a pasture near De Lassus until August 23, when the cars were furnished and the shipment made, but too late for delivery on the market of that day as intended. It is said the shipment reached E;ast St. Louis about ten o’clock a. m. on August 24, and in the meantime the market had declined considerably, so as to entail a loss upon plaintiff. Continuing, the petition avers that the cattle were loaded on defendant’s cars on August 23 about eleven o’clock a. m. at De Lassus, and should, in the usual course, have reached the National Stock Yards at East St.
Though there are separate paragraphs, the petition contains but one count, and it proceeds as for a recovery both because of the breach of the contract in defendant’s failure to furnish the cars on August 22, as agreed, and the delay consequent thereto, and for damages entailed through loss suffered on account of the alleged negligence in the transportation of the cattle after they were loaded and shipped. Such a pleading is to be condemned, for one may not jumble thus a cause of action in contract with one in tort. [See Wernick v. St. Louis & S. F. R. Co., 131 Mo. App. 37, 109 S. W. 1027.] However this may be, if it appear the petition states a cause of action either in contract or in tort, and the evidence tends to support it, the other averments may be rejected as surplusage, and the case should proceed accordingly. Because the paragraph of the petition pertaining to the delay while the cattle were en route to East St. Louis employs apt words in laying a tort, as in charging such delay was occasioned through defendant’s negligence, it is argued the entire petition should be treated as stating an action in tort and the judgment reversed, for there is no evidence tending to prove the negligence charged; but we are not so persuaded.
It appears in the evidence that the shipment of cattle started from De Lassus about noon on August 23 and reached the National Stock Yards at East St. Louis about ten a. m. on the following morning, A.ugnst 24. The only delay mentioned en route was the lay over of three hours at De Soto (a division point), and it does not appear why this occurred. The case is devoid of evidence tending to prove a negligent delay
But after putting aside all of the averments touching the matter of negligent delay in the operation of the train during the transit, there appears to be stated in the petition a cause of action sounding in contract, which finds ample support in the evidence. It is averred in the petition, as above stated, that plaintiff entered into a contract for hire with defendant on the 19th day of August, whereby defendant undertook and agreed to furnish two cars at De Lassus for the reception and shipment of his fifty-nine head of cattle on the morning of August 22, so as to enable him to deliver them at the National Stock Yards, East St. Louis on the morning of August 23. It is averred, too, that plaintiff, relying upon the contract so entered into, tendered his cattle to be loaded in the cars for shipment on the morning of August 22, and defendant faded and refused to furnish the cars to receive them. Because of this, plaintiff was prevented from shipping that day, and in the meantime the market for such cattle materially declined, so as to entail a considerable loss upon him, for which damages are prayed. So much of the petition above adverted to lays both an agreement on the part of defendant and a consideration therefor and avers a breach of the contract. It is clear the case thus stated and the recovery prayed is one sounding in contract and for its breach. [See Wernick v. St. Louis & S. F. R. Co., 131 Mo. App. 37, 109 S. W. 1027; Meade v. Missouri Pac. R. Co., 183 Mo. App. 353, 166 S. W. 1116.]
The evidence for plaintiff amply supports these averments of the petition, in that it tends to prove the
But in submitting the case to the jury, the court paid no heed to the distinction between' contract and tort, in that, by the first instruction, it authorized a recovery for the breach of the contract set forth and relied upon in the petition, and the second instruction submitted the alleged negligence of defendant in’ the operation of the train, which, it is said, occasioned further delay in transit and authorized a recovery on that ground as well. Obviously the two theories of recovery may not be invoked in the same case. [Wernick v. Railroad, supra.] Moreover, there appears to be no substantial evidence tending to support the averment of negligent delay as above pointed out, and it was error to submit that issue to the jury even though the case proceeded alone on that ground.
The judgment should be reversed and the cause remanded to be proceeded with as a a suit ex contractu. Plaintiff may amend his petition, however, if so advised. It is so ordered.