DAKOTA CONSTRUCTORS, INC., Petitioner and Appellant, v. HANSON COUNTY BOARD OF ADJUSTMENT, Respondent and Appellee.
#30084-a-SRJ
IN THE SUPREME COURT OF THE STATE OF SOUTH DAKOTA
OPINION FILED 07/26/23
2023 S.D. 38
THE HONORABLE CHRIS S. GILES, Judge
PAUL H. LINDE of Schaffer Law Office, Prof. LLC, Sioux Falls, South Dakota. Attorneys for petitioner and appellant.
JACK H. HIEB, ZACHARY W. PETERSON of Richardson, Wyly, Wise, Sauck & Hieb, LLP, Aberdeen, South Dakota. Attorneys for respondent and appellee.
JENSEN, Chief Justice
[¶1.] In 2021, Dakota Constructors, Inc. (Dakota Constructors) purchased a quarry located in Hanson County that had operated since 1986 under a state license to mine sand, gravel, and rock. The Hanson County Zoning Ordinance (Ordinance) took effect in April 2000. After the purchase, the Hanson County Zoning Administrator advised Dakota Constructors that because the quarry is located in a district that is currently zoned as agricultural, it would need a conditional use permit (CUP) under the Ordinance in order to extract sand, gravel, and rock from the site. Dakota Constructors submitted a CUP application but argued before the Hanson County Board of Adjustment (Board) that it did not need a CUP because the operation of the quarry was a continuing prior nonconforming use. The Board disagreed and determined that Dakota Constructors did need a CUP because the nonconforming use contemplated—the extraction of materials from the site—had ceased for more than one year. The Board granted the CUP application with specified conditions. Dakota Constructors petitioned for a writ
Background
[¶2.] Fisher Sand & Gravel Co. (Fisher) initially operated a quarry at the property.1 From and after 1986, Fisher annually renewed its mining license with the South Dakota Department of Environmental and Natural Resources (now the Department of Agriculture and Natural Resources) Mineral and Mining Program, pursuant to
[¶3.] At the direction of the County Zoning Administrator, Dakota Constructors submitted a CUP application to Hanson County on November 15, 2021. A Board hearing on the application was initially set for December 22, 2021, but was deferred to January 26, 2022. During this time, the Board received a report from an engineering firm providing recommendations for stabilizing a portion of the quarry that was impacting the integrity of a nearby County road. The report discussed needed repairs in an area where a fence had been constructed ten feet from the highwall of the quarry and twenty feet from the guardrail. A slump undermining the fence had come within fifteen feet of the guardrail, and the ground was eroded up to the fence in four other locations. The estimated cost of the repairs was $620,500.
[¶4.] At the hearing, Dakota Constructors argued to the Board that a CUP was not required because the operation of the quarry was a continuing prior nonconforming use. The Board received voluminous documents and statements concerning the operation at the quarry dating back to 1986. These submissions showed the quarry operated as a state-licensed mining operation since 1986 and that aggregate in the form of sand, gravel, and rock had been continuously removed from the quarry since that time. Dakota Constructors presented an affidavit from Clinton Degen, former Hanson County Highway Superintendent, who stated that he hauled material from the property each year except for 2004 and 2005 when Spencer Quarries was operating and hauling aggregate from the site.
[¶5.] However, the submissions also showed that since 2004 the sand, gravel, and rock removed from the quarry had come from stockpiles stored at the site that had been extracted from the ground prior to 2004. In particular, the annual mine reports required by
[¶6.] The Board held hearings on three dates to consider the CUP application. On February 23, the Board made findings determining that the previous operation of the quarry had ceased for more than one year and was thus not a prior nonconforming use that could continue without a CUP. After determining a CUP was necessary for Dakota Constructors to operate the quarry, the Board approved the CUP and established conditions for use of the quarry, including repair of the erosion near the road, before commencing blasting. The Board‘s findings included:
- [Dakota Constructors] presented a legal statement to the Board. Statement is on file with the Hanson County Zoning Office.
- The requested conditional use is permitted under Article 5, Section 507 of Hanson County Zoning Ordinance.
- The request does require a Conditional Use permit. The current owner will be expanding to occupy a greater area of land. Article 3, Section 1305, Hanson County Zoning Ordinance.3
- The previous operation has ceased for more than one year according to all records filed with the State of South Dakota. Article 3, Section 1305, Hanson County Zoning Ordinance.
[¶7.] Dakota Constructors filed a petition for writ of certiorari with the circuit court. The court held a hearing on the petition and issued a memorandum decision and a corresponding order denying the writ. The court concluded that the Board‘s interpretation of the Ordinance must be given deference under
[¶8.] Dakota Constructors appeals and raises a single issue, which we restate as follows:
Whether the circuit court erred in denying the writ of certiorari challenging the Board‘s decision to require Dakota Constructors to obtain a conditional use permit to extract gravel, sand, or minerals from its quarry.
Analysis
[¶9.] Decisions granting or denying CUPs are reviewed under the writ of certiorari standard.
Any appeal of a decision of granting or denying a conditional use permit shall be brought under a petition, duly verified, for a writ of certiorari directed to the approving authority and, notwithstanding
any provision of law to the contrary, shall be determined under a writ of certiorari standard regardless of the form of the approving authority. The court shall give deference to the decision of the approving authority in interpreting the authority‘s ordinances.
Id.
[¶10.] “The review upon writ of certiorari cannot be extended further than to determine whether the inferior court, tribunal, board, or officer, has regularly pursued the authority of such court, tribunal, board, or officer.”
[¶11.] We have not directly addressed the deference mandated by
[¶12.] The deference mandated by
[¶13.] Dakota Constructors contends that no deference should be afforded to the Board because its reading of the Ordinance implicates South Dakota law incorporated into the Ordinance. Dakota Constructors argues that the circuit court, contrary to
[¶14.] Article 5, section 507, of the Ordinance identifies conditional uses that may be permitted within an agricultural district. One such use is the “[e]xtraction of sand, gravel, or minerals provided such uses meet requirements for conducting surface mining activities of
[¶15.] The Board argues that its interpretation of the term “extraction,” which is not otherwise defined in the Ordinance or in state law, is entitled to deference under
1. Interpretation of the Ordinance
[¶16.] The Ordinance is consistent with state law in limiting “any subsequent use” of property that has “discontinued for a period of more than one year[.]”
Any lawful use, lot, or occupancy of land or premises existing at the time of the adoption of the zoning ordinance may be continued, even though the use, lot, or occupation does not conform to the provisions of the ordinance. However, if the nonconforming use, lot, or occupancy is discontinued for a period of more than one year, any subsequent use, lot, or occupancy of the land or premises shall conform with the zoning ordinance.
[¶17.] Article 13, section 1305 of the Ordinance specifies the conditions under which preexisting nonconforming uses may continue in Hanson County:
Where at the time of passage of this revised ordinance lawful use of land exists, which would not be permitted by the regulations imposed by this ordinance, and where such use involves no individual structure with a replacement cost exceeding one thousand (1,000) dollars, the use may be continued so long as it remains otherwise lawful, provided: . . .
3. If any nonconforming use of land ceases, for any reason, for a period of more than one (1) year, any subsequent use of such land shall conform to the regulations specified by this ordinance for the district in which such land is located[.]
The Ordinance defines the terms “nonconforming use” and “use” as follows:
Nonconforming Use - A land use or building or structure or portion thereof lawfully existing at the effective date of this ordinance, or at the time of any amendment thereto, which does not conform to the regulations of the zone in which it is located.
Use - Use shall mean the purpose for which a lot or a building or structure, or any portion thereof, is designed, arranged, intended, occupies or maintained, and “used” shall have a corresponding meaning.
[¶18.] There is no dispute that the property is in a district that is currently zoned agricultural. Article 5, section 501 of the Ordinance explains that “[t]he intent of Agricultural District (AG) is to protect agricultural lands and lands consisting of natural growth from incompatible land uses in order to preserve land best suited to agricultural uses and land in which the natural environment should be continued and to limit residential, commercial, and industrial development to those areas where they are best suited for reasons of practicality and service delivery.” The extraction of sand, gravel, or minerals is not a permitted principal use within an agricultural district under the Ordinance. Thus, if extraction at the site had ceased for more than one year, it was not a continuing prior nonconforming use. However, article 5, section 507 of the Ordinance authorizes the Board to grant a CUP for this use of the property.
[¶19.] In determining that the extraction of sand, gravel, and rock was not a continuing
[¶20.] Extraction is not defined elsewhere in the Ordinance or under state law. Dakota Constructors’ assertion that the Board was interpreting state law rather than its own Ordinance is incorrect. The Ordinance allows CUPs for the “[e]xtraction of sand, gravel, or minerals provided such uses meet requirements for conducting surface mining activities of
[¶21.] Dakota Constructors also cites cases from other jurisdictions that support a broader construction of the nonconforming use than applied by the Board.6 These cases are not persuasive to our consideration under our limited certiorari review. While the cases suggest that the Board could have read the term extraction more broadly, we see nothing in the Board‘s reading of its Ordinance that was wrong or erroneous. Dakota Constructors has failed to show that the Board‘s reading of extraction was contrary to the Ordinance, contrary to state statute, or otherwise wrong or erroneous.
2. Factual findings
[¶22.] After considering the information presented by Dakota Constructors, the Board found that “[t]he previous operation has ceased for more than one year according to all records filed with the State of South Dakota.” Although Dakota Constructors presented evidence that aggregate continued to be hauled from existing stockpiles in the quarry, there is no evidence contradicting the reports filed by Fisher that zero tons of gravel were removed
[¶23.] There is no claim that the Board acted fraudulently or arbitrarily, or that its findings were in willful disregard of the indisputable proof. See Powers, 2022 S.D. 77, ¶ 27, 983 N.W.2d at 604. Rather, the Board considered the information submitted in support of the CUP application and in support of the argument that a CUP was unnecessary. In fact, it continued its consideration across multiple Board meetings to ensure it had all the information it needed to reach its decision.
[¶24.] Therefore, the circuit court properly denied Dakota Constructors’ petition for writ of certiorari.
[¶25.] Affirmed.
[¶26.] KERN, SALTER, DEVANEY, and MYREN, Justices, concur.
