Many questions, most of which are duplicating, overlapping, or related, are raised by the two appeals and defendant’s numerous cross-assignments of error. The determination of these questions will be facilitated and this opinion greatly shortened by discussing the questions to the extent necessary, and some require no discussion, in connection with the subject that they relate to.
*394 I
The Award of Punitive Damages for Defendant’s Bad Faith Refusal to Settle Plaintiffs Contract Claim and for the Malicious Acts of its Agent Charnock in Furtherance Thereof
The defendant’s liability to plaintiff under the policy in the amount of $157,000 has been set at rest. The primary question raised by plaintiffs appeal is whether the verdict for punitive damages was erroneously set aside. Stated a different way, are punitive damages recoverable in this state where the basic, underlying claim is for breach of contract?
a.
The general rule in North Carolina is that punitive or exemplary damages are not recoverable for a mere breach of contract, unless the contract is to marry.
King v. Insurance Company of North America,
b.
Because this is an appeal from a judgment
non obstante veredicto,
instead of a dismissal under Rule 12(b)(6), the main question presented is somewhat different from the one adjudicated in the other cases above referred to. The question raised by a judgment
non obstante veredicto
is essentially the same as that raised by a directed verdict.
Dickinson v. Pake,
The evidence indicates that though the fire occurred on 25 July 1980, and it was immediately obvious that defendant’s potential liability under the policy was substantial, it was not until 10 October 1980, two and a half months after the fire and more than three weeks after plaintiffs first proof of loss was received — the proof of loss itself having been delayed for some weeks by defendant’s failure to send the form in its first mailing — that defendant took steps to have plaintiff investigated, and that though Char-nock advised defendant shortly after 15 October that the investigation was fruitless and there was no defense to the claim, it was not until 17 December 1980, two months later and nearly five months after the fire, that defendant had an unlicensed builder, whose lack of qualifications to do the work were not checked, to examine the house, and it was a month after that before defendant offered to settle the claim based on that builder’s estimate, which was grossly inadequate. This evidence and the other evidence above stated fairly shows, we think, that after arbitrarily *397 rejecting plaintiffs well documented claim defendant took no steps at all to check plaintiffs estimated construction costs for several months and then selected an unqualified builder to do the checking, and then waited another month before making a settlement offer for the real property loss that had no reasonable basis and an offer to settle the contents loss that disregarded the actual utility and value of the destroyed items.
The evidence supports the conclusion, we think, that defendant’s effort to settle plaintiffs claim consisted of requiring him to go to the inconvenience and expense of obtaining qualified, expert estimates defendant had no intention of considering; inordinately delaying both the settlement and plaintiffs return to his usual comforts and amenities of life; and then offering about half the amount owed in anticipation that plaintiff would have neither the will nor the resources to refuse it. More aggravated, oppressive conduct, not involving physical force or personal insult, by one having a duty to relieve financial distress and inconvenience is hard to imagine. But that was not all. Defendant, through its agent Charnock, also told some of plaintiffs friends and neighbors, with no basis whatever, that it had determined that plaintiff had his house burned “for insurance purposes,” and “stirred up a lot of hate and discontent” against plaintiff among his neighbors.
When taking defendant’s motion to set aside the verdict under advisement the trial judge, who heard and saw the testifying witnesses, appraised defendant’s conduct as follows:
I would say to you in all candor that when this jury went out that I went and called my insurance agent to check that my fire insurance wasn’t with your client. There is no question in my mind based on the evidence I heard that your client did not act in good faith in settling this claim. I wouldn’t any more let those two people in Goldsboro work on my house, much less go inside my house than anything. I can understand why the jury would feel the same way. The plaintiff on the one hand offered uncontested evidence from five licensed contractors who build the majority of the homes apparently in the New Bern area as to the cost of repair and the only evidence really that you had was two people from Goldsboro, a father and son team who were going to work at six percent *398 profit and use their profit — just give up their profit — to buy all the extra materials they would need; and you know, I love American businessmen but I just never have met two quite as kind as those people. It was just a little far fetched, you know, that legitimate licensed contractors could be so far afield from these two people. I think that your client in representing that those two gentlemen from Goldsboro were competent in good faith to repair this home breached a duty that they had to their policyholder; and, then they would come along with an appraiser who testifies as to the personal property that every pair of shoes I have which is over a year old has no cash value whatsoever and when that is coupled with an investigator who comes down and tours the neighborhood and goes and talks to others and conducts himself as the jury found he did then I think the evidence clearly supports the punitive damage verdict if that verdict, if that issue, were properly to be submitted to the jury.
The jury’s finding that defendant’s conduct was tortious and warranted punishment has the sanction of law, in our opinion, and it was error to disturb it. Thus, the judgment of the trial court setting aside the punitive damages awarded is vacated and upon remand the jury verdict with respect thereto will be reinstated. By five cross-assignments of error the defendant maintains that the evidence does not support the punitive damage awards and that even if the judge erred in ruling that our law does not authorize punitive damages in cases of this kind the judgment appealed from should nevertheless be upheld. These contentions were considered and rejected in determining that the evidence of defendant’s tortious and aggravating conduct is sufficient to support the awards made, and discussing defendant’s contentions ad seriatim would serve no useful purpose.
By two further cross-assignments of error defendant also maintains that the punitive damages issues were erroneously formed and that this is still another alternative ground for upholding the setting aside of the verdict. But the record plainly shows not only that defendant made no objection to the form of these issues, but expressly stated to the court before they were submitted that it had no objection to their particular form. Since the defendant tried the case to a conclusion without ever raising these questions and giving the trial court an opportunity to rule
*399
on them, we will not consider them now.
Kim v. Professional Business Brokers, Ltd.,
II
Evidence that Charnock was Defendant’s Agent
By several other cross-assignments of error defendant contends that the jury verdict that Charnock was defendant’s agent during his three-day investigation of plaintiff in Craven County is not sufficiently supported by admissible evidence. It is particularly contended that plaintiff and some of his witnesses were erroneously permitted to testify as to certain out-of-court statements by Charnock to the effect that he was working for Integon while investigating the plaintiff in Craven County. As defendant correctly maintains, the general rule is that neither the fact nor the extent of an agency relationship can be proved by the out-of-court statements of an alleged agent.
Branch v. Dempsey,
Ill
The Directed Verdict Against Compensatory Damages on Plaintiff’s Second Claim
Returning to plaintiffs appeal, was it error for the trial court to direct a verdict against plaintiffs
second claim
for compensatory damages because of expenses that he incurred and emotional distress that he suffered as a result of defendant’s bad faith refusal to settle his claim? Plaintiff argues that the dismissal of this claim violated the mandate of this Court following the first appeal. We disagree. There is a difference between sufficiently alleging a claim and sufficiently proving it. The tort of intentional infliction of emotional distress was recognized in the case of
Stan-
*401
back v. Stanback, supra. See also, Morrow v. King’s Department Stores,
The other part of this claim seeks recovery for fees plaintiff paid out for construction and repair estimates, photographs, expert witnesses, and other things in processing the claim and this lawsuit. But, under our law, such losses are not recoverable as damages unless authorized by statute,
City of Charlotte v. McNeely,
IV
Evidence of Other Alleged Derelictions by Defendant
During the course of the trial plaintiff unsuccessfully sought to introduce testimony by two former insureds of the defendant *402 that they were treated almost identically the way the evidence indicates plaintiff was treated. And plaintiff was not permitted to offer evidence as to the fact that more than a year after the lawsuit was filed, defendant purchased the note and deed of trust on his property from the original mortgagee and that a few days before the trial defense counsel wrote a letter to plaintiff and his counsel, stating that defendant held the note and deed of trust, and since plaintiff was behind in his payments defendant was exercising its option to accelerate the remaining payments due, and to demand that the full balance due, including interest and late charges, be paid at once. Plaintiffs contention that the excluded evidence should have been received into evidence because it tends to show defendant’s bad faith, overreaching, and wilfulness will not be ruled on, since a new trial is not being granted.
V
Prejudgment Interest on Amount Recovered Under the Policy
Under the terms of its policy defendant was required to pay plaintiff the amount due thereunder for damage done to the house and personal property within sixty days after proof of loss was filed. Since plaintiffs first proof of loss was sent to defendant on 18 September 1980, the trial court in entering judgment ordered that interest attach to the $142,000 recovered for the house and contents damage from 18 November 1980 until paid. Defendant contends that this order was erroneous because those damages were unliquidated and undetermined until the verdict was rendered. This contention is without merit and we overrule it. A policy of insurance is a contract. The amount defendant owed plaintiff was due under its policy and the statutory basis for the award of prejudgment interest in this case could not be plainer. G.S. 24-5, in pertinent part, provides as follows:
All sums of money due by contract of any kind, excepting money due on penal bonds, shall bear interest, and when a jury shall render verdict therefor they shall distinguish the principal from the sum allowed as interest; . . .
Nothing in this provision supports the proposition that a party obligated by contract to pay money to another can use the other party’s money at no cost merely because the exact amount due has not already been established. Indications to the contrary in
*403
some earlier cases have long since been abandoned. In
Perry v. Norton,
In this the trial judge simply followed the law as established by the decisions of this Court. . . . The statute says that all sums of money due by contract of this kind, excepting money due on penal bonds, shall bear interest. . . . From this it would seem to follow in this State that whenever a recovery is had for a breach of contract and “the amount is ascertained from the terms of the contract itself or for (sic) evidence relevant to the inquiry,” that interest should be added.
Nor does G.S. 24-5 require that an issue be submitted to the jury before interest can be allowed in contract cases. The requirement is merely that the jury “distinguish the principal from the sum allowed as interest,” which obviously pertains only to those rare situations where
evidence as to both principal and interest
is submitted to the jury for their consideration. This distinction was recognized in the early case of
DeLoach v. Work,
As to plaintiffs appeal (a) the judgment setting aside the verdict on Issues 5 and 6 is vacated and on remand the judgment for punitive damages originally entered thereon will be reinstated; (b) the verdict directed against plaintiffs second claim is affirmed.
As to defendant’s appeal and cross-assignments, the judgment appealed from is affirmed and all the cross-assignments of error are denied.
Affirmed in part; vacated and remanded in part.
