527 A.2d 1008 | Pa. Super. Ct. | 1987
Dissenting Opinion
dissenting:
A careful review of the evidence in this case persuades me that D.A. Hill Company (Hill) and Felheim Roofing Company (Felheim) failed to prove causes of action for unjust enrichment against CleveTrust Realty Investors, Inc. (CleveTrust). Therefore, I must respectfully dissent from the majority’s affirmance of the judgments entered by the trial court.
CleveTrust agreed to provide construction financing for the Edinboro Mall in Erie County pursuant to a construction loan agreement with Edinboro Development Company (Ed-inboro), the owner of the land. Pursuant to the terms of that agreement, CleveTrust was to advance the sum of $2,200,000.00 for the construction of the mall, with the loan being secured by a first mortgage. Edinboro then engaged a general contractor, Drakes Mills Development Co., to perform the construction work. Hill and Felheim were subcontractors on the job.
On November 1, 1974, the owner of the mall defaulted in the terms of the loan agreement by failing to make a required payment of interest. Five days later, CleveTrust received from the owner the ninth application for payment. Exercising its right under the construction loan agreement, CleveTrust refused to disburse further funds. At the time of Edinboro’s default, CleveTrust had advanced a total of $1,903,891.13.
Upon learning of the property owner’s financial difficulties, the general contractor stopped work in December,
The owner failed to make monthly interest payments due for the month of December, 1974, and for the months of January and February, 1975. On February 19, 1975, therefore, CleveTrust instituted foreclosure proceedings on its first mortgage. After the owner had filed a petition for bankruptcy, the trial court appointed a receiver to manage Edinboro’s assets and to operate its business. CleveTrust’s foreclosure action was thereafter stayed. When this stay was subsequently removed, the sheriff, on December 12, 1975, sold the mall property to CleveTrust for taxes and costs in the amount of $120,921.05. The deed to the mall property was recorded on May 27, 1976.
Nearly five years later, the appellee-subcontractors instituted actions in equity against CleveTrust on the theory that CleveTrust had been unjustly enriched when it purchased the mall, because it had received the benefit of appellees’ work on the project without having advanced the total amount of loan funds. CleveTrust, in its answer, contended that it had not been enriched because the value of the mall at the time when it acquired title had been less than the amount of loan funds which it had advanced. Moreover, CleveTrust contended, the funds which it had advanced to the owner for the categories of work per
The cases were consolidated for trial without jury. At the conclusion thereof, the trial court held that because CleveTrust had only advanced $1,903,000.00 of its $2,200,-000.00 loan commitment, the subcontractors were entitled to full recovery of their claims on grounds that CleveTrust had been enriched unjustly. CleveTrust filed exceptions to the trial court’s decision, and these were reviewed by the court en banc. That body remanded the case to the trial court for reconsideration in light of this Court’s decision in Gee v. Eberle, 279 Pa.Super. 101, 420 A.2d 1050 (1980). According to Gee, the court en banc explained, the key issue was whether sufficient funds had been disbursed by CleveTrust to satisfy appellees’ claims. The trial court conducted a hearing on this issue, after which it entered an order awarding $27,674.60, plus six percent interest, to Hill and $10,887.20, plus interest, to Felheim. CleveTrust’s exceptions to this second adjudication by the trial court were dismissed, and judgments were entered on behalf of Hill and Felheim in the amounts which had been awarded by the trial court. CleveTrust appealed.
“The applicable standard of review in the consideration of an appeal from a final order in equity is well-settled. The findings of fact of a chancellor have the effect of a jury verdict and if based on legally competent and sufficient evidence, will not be disturbed on appeal. Snellbaker v. Herrmann, 315 Pa.Super. 520, 462 A.2d 713 (1983); August Petroleum Co. 77B v. Casciola, 303 Pa.Super. 374, 449 A.2d 735 (1982); Wright v. Buckeye Coal Co., 290 Pa.Super. 231, 434 A.2d 728 (1981). However, it is the duty and function of [a reviewing] [c]ourt to scrutinize the inferences and legal conclusions drawn from those facts. Silo Realty Corp. v. Redevelopment Authority of City of Philadelphia, 289 Pa.Super. 67, 432 A.2d 1053 (1981); McDole v. Duquesne Brewing Co. of Pittsburgh, 281 Pa.Super. 78,
Apart from special statutory rights and a possible recovery for unjust enrichment, the decided cases hold unequivocally that a subcontractor who has furnished labor and/or materials for construction on the land of another has no right to recover therefor against the landowner, or against a construction lender, in the absence of a contractual relationship between them. See: Annot., Building and Construction Contracts: Right of Subcontractor Who Has Dealt With Primary Contractor to Recover Against Property Owner in Quasi Contract, 62 A.L.R.3d 288 (1975). In the instant case, the subcontractors did not enjoy a contractual relationship with the lender, and the subcontractors had also waived the right to assert a claim under the Mechanics’ Lien Law. Therefore, they attempted to establish a cause of action on the grounds of unjust enrichment.
The theory of unjust enrichment is founded on the principle that when a person receives a benefit from another, and it would be unconscionable for the recipient to retain that benefit, equity can be done only by requiring the recipient to make restitution. See: Myers-Macomber Engineers v. M.L.W. Construction Corp., 271 Pa.Super. 484, 490, 414 A.2d 357, 360 (1979). In order to recover under the theory of unjust enrichment, “there must be both (1) an enrichment, and (2) an injustice resulting if recovery for the enrichment is denied.” Meehan v. Cheltenham Township, 410 Pa. 446, 449, 189 A.2d 593, 595 (1963). The burden of proving the existence of these elements is upon the party seeking restitution. See: 66 Am.Jur.2d Restitution and Implied Contracts § 88.
For purposes of analyzing a claim for unjust enrichment, an “enrichment” is deemed to be the value of the benefit
The subcontractors in the instant case failed to prove the extent to which the shopping mall had been enhanced, if at all, by their work. They offered only their unpaid invoices. These invoices, however, reflected the costs of labor and material expended and also profit allowed by their agreements with the general contractor. Under these circumstances, it cannot accurately be said that the invoices represented benefit received by CleveTrust as a result of work performed and materials supplied by the subcontractors.
Moreover, “[i]f the lender has in fact made advances to pay for the work of a subcontractor, it has satisfied its obligation — so far as it is concerned, it has paid for the work — and the subcontractor may not claim part of the proceeds of the profit [if the premises are resold] on an unjust enrichment theory. If, however, the lender has not
Felheim was unable to show that CleveTrust had failed to advance moneys sufficient to cover its invoices prior to the owner’s default. Felheim had performed work under categories ten and eleven. It had invoiced CleveTrust a total of $77,900.00. CleveTrust had advanced $97,984.80 for work done on these categories. Of this amount, $58,760.00 had been paid to Felheim by the general contractor. Although the trial court found that other subcontractors had also done work under these categories, there is no evidence with respect to the work which they had done or the amount which they had invoiced for such additional work. Thus, the record does not support Felheim’s contention that Cleve-Trust’s advances were insufficient to pay its invoice in full. Because the amount advanced by CleveTrust ($97,984.80) exceeded the amount invoiced by Felheim ($77,900.00), Fel-heim’s evidence failed to establish that CleveTrust had been unjustly enriched by virtue of the work which Felheim had performed.
Even if the subcontractors had been able to establish that CleveTrust was benefitted by the work which they had performed, they would not be entitled to recover from the lender unless the lender were enriched unjustly. This, too, the subcontractors failed to prove. Under the circumstances of this case, it would not have been unjust to deny the subcontractors’ claims. “The legislature in Pennsylvania has by statute provided the mechanics’ lien as a means by
It was undisputed that CleveTrust had advanced the sum of $1,903,891.13 for mall construction. At the time of the sheriff’s sale, CleveTrust notes, its claim for unpaid principal, interest and penalties was in the amount of $2,227,-400.00. The trial court did not make a finding with respect to the value of the mall at the time of the sheriff’s sale but found that the mall at the time of default, a year prior to the sheriff’s sale, had an approximate value of $2,000,000.00. At this time, the estimated cost of completing the mall was $100,000.00. Thus, the evidence did not show that the lender had acquired an asset whose value exceeded the advances and costs which the lender had paid for it. Under these circumstances, the equities of the lender were equal or superior to those of the subcontractors.
I would reverse the judgments entered in favor of the subcontractors.
. Judgment was also entered for George H. Althof, Inc. Although CleveTrust filed a notice of appeal from this judgment to No. 1532 Pittsburgh, 1985, that appeal has been discontinued. The propriety of the judgment entered for George H. Althof, Inc., therefore, is not before this Court.
Lead Opinion
Affirmed.