D & H Construction Co. v. City of WoodstockD & H Construction Co. v. City of Woodstock
The City of Woodstock mistakenly made a duplicate payment to D & H Construction Company for construction work performed for the City. When D & H Construction refused to return the duplicate payment, the City filed suit for unjust enrichment, conversion, attorney fees under OCGA § 13-6-11, and punitive damages. The trial court subsequently denied summary judgment to D & H Construction and granted summary judgment to the City on its claims for unjust enrichment, conversion, and attorney fees. D & H Construction appeals, contending that the voluntary payment doctrine bars the City’s unjust enrichment and conversion claims. D & H Construction also contends that the grant of attorney fees was erroneous because, among other things, there was a bona fide controversy and it was not given an opportunity to cross-examine the City’s counsel concerning the reasonableness of the fees. For the following reasons, we affirm the trial court’s grant of summary judgment to the City on the unjust enrichment and conversion claims and its ruling that the City was entitled to attorney fees. However, because D & H Construction was not permitted to cross-examine the City’s counsel about the reasonableness of the requested fee amount, we vacate the award of fees and remand for an evidentiary hearing on that limited issue.
To prevail on a motion for summary judgment, the moving party must demonstrate that there is no genuine issue of material fact, and that the undisputed facts, viewed in a light most favorable to the party opposing the motion, warrant judgment as a matter of law. OCGA § 9-11-56 (c); Lau’s Corp. v. Haskins,261 Ga. 491 (405 SE2d 474 ) (1991). In reviewing the grant or denial of summary judgment, we apply a de novo standard of review.
(Citations and punctuation omitted.)
Greer v. Provident Bank,
So viewed, the undisputed record reflects that the City engaged D & H Construction to perform work on a construction project in Cherokee County. On March 6, 2002, after completing the construction work, the vice president of D & H Construction executed a sworn document entitled “Contractor’s Certificate and Release of Liens” (the “Contractor’s Certificate”). The Contractor’s Certificate stated that D & H Construction was only owed the final payment amount of $100,049.10 from the City for its work on the project. The Contractor’s Certificate further provided that upon receipt of that final payment, D & H Construction would release the City “from any and all claims arising under or by virtue of” the construction contract between the parties.
On March 19,2002, the City tendered the amount of $100,049.10 to D & H Construction via check number 46430. D & H Construction deposited the check into its bank account. However, on April 17,2002, the City mistakenly tendered a duplicate final payment of $ 100,049.10 to D & H Construction via check number 46793. D & H Construction deposited the duplicate payment and used it to pay off outstanding company debts. Five months later, the City realized that it had inadvertently tendered a duplicate final payment to D & H Construction and demanded return of the payment. D & H Construction refused to return the duplicate payment, resulting in the City commencing the instant litigation for unjust enrichment, conversion, attorney fees, and punitive damages.
The voluntary payment doctrine is codified in OCGA § 13-1-13, which provides in part:
Payments of claims made through ignorance of the law or where all the facts are known and there is no misplaced confidence and no artifice, deception, or fraudulent practice used by the other party are deemed voluntary and cannot be recovered unless made under an urgent and immediate necessity therefor or to release person or property from detention or to prevent an immediate seizure of person or property.
Significantly, however, in the seminal case of
Gulf Life Ins. Co. v. Folsom,
Based on Folsom, there are two primary issues that must be addressed in applying the voluntary payment doctrine in this case. The first issue is whether in making the duplicate payment, the City was negligent in ascertaining the true facts. The second issue is whether D & H Construction would be prejudiced by having to return the duplicate payment, subject to a weighing of the equities between the parties. Here, the uncontroverted evidence reflects, and the City in fact concedes, that it was negligent in ascertaining the true facts before tendering the duplicate final payment to D & H Construction. Thus, there is no genuine issue of material fact over whether the City was negligent in ascertaining the true facts, and so the focus of this case for summary judgment purposes is on the second issue.
We conclude, as did the trial court, that D & H Construction would not be prejudiced in returning the negligent duplicate payment to the City as a matter of law. D & H Construction’s only contention that it would be prejudiced is based solely upon the affidavit submitted by its president, Henry Graham. In his affidavit, Graham averred that D & H Construction spent the duplicate payment to “payoff outstanding debts” and changed its position to its detriment by not seeking “additional funding for operations.” Based on these statements in the Graham affidavit, D & H Construction contends that it has conclusively established prejudice or, at a minimum, has created a genuine issue of fact over the issue.
We are unpersuaded. As an initial matter, the Graham affidavit is vague and indefinite at best, and we have held that summary judgment is appropriate when the nonmovant relies upon an affidavit containing “nothing but vague assertions of fact.”
Buddy’s Appliance Center v. Amana Refrigeration,
Furthermore, Graham’s statement that D & H Construction did not seek “additional funding for operations” as a result of the duplicate payment is conclusory and is not substantiated by any financial documents or other evidence contained in the record. For this additional reason, the affidavit is insufficient to create a genuine issue of fact over the prejudice issue. See
Hobbs v. Western Surety Co.,
Given this record, D & H Construction cannot prove that it would suffer any prejudice in returning the duplicate payment. Nevertheless, D & H Construction argues that it is entitled to retain the duplicate payment under a balancing of the other equities involved in the case. We disagree based on our decision in
Wyatt,
Here, the vice president of D & H Construction signed the sworn Contractor’s Certificate stating that D & H Construction was only owed the final payment amount of $ 100,049.10 and releasing the City from any and all claims once that payment was made. Thus, as in Wyatt, the payee (D & H Construction) executed a written release that conclusively established the correct payment amount. Furthermore, this case is like Wyatt because, as noted above, there is no evidence that D & H Construction would suffer any prejudice in returning the overpayment. Accordingly, the present case is factually similar to, and is controlled by, our decision in Wyatt holding that the payor was entitled to the return of the negligent payment as a matter of law.
“Folsom
does not mandate that every [case involving the voluntary payment doctrine] must be presented to a jury, and this is not one of them.”
Time Ins. Co. v. Fulton-DeKalb Hosp. Auth.,
2. D & H Construction maintains that the trial court erred in awarding attorney fees to the City pursuant to OCGA § 13-6-11. Among other things, D & H Construction asserts there was a bona fide controversy and it was not given an opportunity to cross-examine the City’s counsel concerning the reasonableness of the fees.
Attorney fees may be awarded to a plaintiff under OCGA § 13-6-11 “where the defendant has acted in bad faith, has been stubbornly litigious, or has caused the plaintiff unnecessary trouble and expense.” “Arefusal to pay in bad faith means a frivolous and unfounded denial of liability.” (Citation and punctuation omitted.)
Jeff Goolsby Homes Corp. v. Smith,
However, we agree with D & H Construction’s argument that it should have been given an opportunity to cross-examine the City’s counsel concerning the reasonableness of the amount of fees awarded. Although D & H Construction requested an evidentiary hearing on the fees issue so that it could cross-examine the City’s counsel about the amount of fees requested, the trial court did not hold a hearing on the issue. Instead, the trial court simply awarded $22,894.50 in attorney fees to the City, which was the amount of fees requested in the affidavit submitted by the City’s counsel.
A party opposing a claim for attorney fees has a basic right to confront and challenge testimony as to the value and need for legal services. Defense counsel should have been given an opportunity to cross-examine [the City]’s attorney on the amount and reasonableness of the fees and costs requested. Because [D & H Construction] was denied this opportunity, we vacate that portion of the judgment awarding [the City $22,894.50] in attorney fees and remand the case to the trial court to hold an evidentiary hearing on the amount of the fees.
(Punctuation and footnotes omitted.)
Kwickie/Flash Foods v. Lakeside Petroleum,
Judgment affirmed in part and vacated in part, and case remanded with instruction.