D. C. Ecker Construction, Inc. (“Ecker Construction”) appeals from the trial court’s order dismissing its lien foreclosure claim. In its sole enumeration of error on appeal, Ecker Construction contends that the trial court erred by concluding that its mechanic’s lien claim must be dismissed because it was untimely as a matter of law. For the reasons set forth below, we agree and reverse.
We review a trial court’s grant of a motion to dismiss de novo.
Ga. Lien Svcs. v. Barrett,
The record in this case shows that Ecker Construction filed a complaint against Ponce Investment, LLC (“Ponce”) seeking payment for improvements made to real property owned by Ponce. In its complaint, Ecker Construction sought to foreclose on a mechanic’s lien pursuant to OCGA § 44-14-360 et seq. Ecker Construction’s lien in this case stated that it was being filed “within three months since the furnishing of said services, labor and/or materials. ...” It also stated that the claim was due on June 16, 2006, which was three months and five days before the lien was filed.
There are two critical dates for the enforcement of mechanics’ liens. One is that the claim of lien must be filed within three months after, as it relates to this case, [the completion of the work or] “the material ... is furnished.” OCGA § 44-14-361.1 (a) (2). The other is that an action for recovery of the amount of the claim must be commenced within 12 months from “the time the [claim] shall become due.” OCGA § 44-14-361.1 (a) (3).
(Citations omitted.)
L & W Supply Corp. v. Whaley Constr. Co.,
The date the [work was completed or] material was “furnished” or “delivered” is crucial to the timeliness of the lien. The date the claim is due means the same thing for mechanics’ lien purposes, even if the parties agree on a different due date. The latter is of no consequence in determining the validity of the lien.
(Citations omitted.) Id. at 682. The actual date the work is completed or the material is furnished or delivered controls. See id.
Based on the above, our courts have held that a lien is timely filed if it states the last date the work was completed or the material was delivered,
L & W Supply Corp.,
supra,
In the case now before us, the trial court granted Ponce’s motion to dismiss Ecker Construction’s lien claim based upon its conclusion that the specific due date asserted in the lien rendered it untimely. Ecker Construction argues on appeal that the trial court erred because the lien also asserted that it was filed within three months since the furnishing of its services, labor and/or materials to Ponce. According to Ecker, the trial court should not have construed the lien against it at the motion to dismiss stage of litigation; instead, it should have construed the lien in its favor. See
Field,
supra,
The crucial date in determining the validity of a lien is the date the material or labor is last provided,
not
the date the claim is due. See
L & W Supply Corp.,
supra,
Because the plain language of Ecker’s lien provides “a set of facts that could be proven in support of its claim,” the trial court erred by granting Ponce’s motion to dismiss.
Field,
supra. Our opinion in
Tri-City,
supra, does not control the outcome of this case, because Tri-City did not address the propriety of a granted motion to dismiss, but instead a grant of summary judgment. See
Judgment reversed.