26 Pa. Super. 10 | Pa. Super. Ct. | 1904
Opinion bt
This was an issue joined on a scire facias sur mechanic’s lien, and the trial before the court and the jury resulted in a verdict in favor of the defendants, and judgment being entered thereon the plaintiffs appealed. We find in this record fourteen assignments of error, and an examination of them leads us to the conclusion that the only important question for consideration may be stated in substance thus: The contract on its face purporting to have been executed on October 3, 1897, and filed in the prothonotary’s office on October 19,1897, was the court justified in permitting evidence tending to show that the contract was in fact not signed and executed until October 18, 1897. Upon this question the evidence tended very strongly to show that the date of the contract was a mistake and that in truth and fact it was not executed by Mrs. Pierson till the
The eleventh assignment is as follows: “ That by the pleadings in this case and the issue ■ framed thereunder, the plaintiffs having claimed the right to a lien under and by virtue of the written contract as filed, if the jury shall find from the evidence that tire contract was executed and filed within ten days of its execution, and that it contained a stipulation against filing of liens by subcontractors and materialmen, then in such case the plaintiff is not entitled to recover and their verdict should be for the defendant. Answer, this point is affirmed, unless you should find from the evidence that Mrs. Pierson authorized the contractor to begin work before the signing and execution of the contract.”
The contract in qxrestion contained proper covenants against mechanics’ liens as to contractor, subcontractor, materialmen and other persons, and the stipulation against subcontractors, etc., was contained in the original contract. In Phelps v. Burns, 16 Pa. Superior Ct. 391, we held: “ The appellant urges that the written document filed should on its face show that the stipulation against liens was executed prior to the giving of authority to proceed with the work. The act contemplates, as we have seen, the filing either of the original contract or of a separate stipulation. Some of the legislative requirements apply to both courses of action. But' the provision which requires that the stipulation against liens shall be written and executed prior to the giving of authority to the contractor to proceed with the work, applies only to the case of the filing of a separate stipulation. Here, the contract itself was filed, and no recital of the fact that it was executed prior to the time of the giving of authority to proceed with the work was needed. Furthermore, on the face of the contract
The above ruling is in strict accordance with the Act of June 26, 1895, P. L. 369. Therefore, the learned court gave more favorable instructions to the jury in answer to defendant’s sixth point than they were entitled to, because the covenant against liens by the subcontractor and materialman was contained in the original contract, and, therefore, the burden did not rest on the defendant to show that the contract was signed and executed before the giving of authority to the contractor to begin the work. See also Blaisdell v. Dean, Owner, and Guise, Contractor, 9 Pa. Superior Ct. 639.
The principal contention in the present case is that the court erred in permitting the defendants to show that the date of the execution of the contract against liens was other than the date appearing on its face. “As a general proposition the actual date of a contract may be shown by parol.” Meaning of course the date when it was actually executed: Jones on Evidence, section 443. In Parke v. Neeley; 90 Pa. 52, it is held, “ That the date of a mortgage as it appears on the registry thereof is not to be conclusively taken to be the date or time of its execution, and parol evidence is admissible to show, that in point of fact, it was subsequently éxecuted and delivered.” This rule was based upon the fact that there was enough on the face of the papers to put the purchaser at a sheriff’s sale upon inquiry and visit him with notice, and, that there was no error in admitting parol evidence to prove the actual date of delivery. The circumstances which appeared on the face of the papers in that case, held to be sufficient to put the purchaser at sheriff’s sale upon inquiry, were very slight. In our opinion the same doctrine must be applied to the contract in the present case. It purported to have been executed on October 3d, but the evidence tended strongly to show that it was not executed until October 18th and it was filed in the prothonotary’s office on October 19th.
Now, the circumstance which ought to have put the plaintiffs on inquiry was that this contract manifestly made under the act of 1895 to protect the property against liens purported to have been signed and executed more than ten days before it
In our opinion it is not a material question whether the owner gave the contractor permission to begin the work before the contract' was executed. But conceding the law to be otherwise, then the plaintiff has no ground of complaint, because the learned court over and over again, in the charge, told the jury that the plaintiffs might recover if the owner consented to the contractor beginning the construction of the house before the contract was executed. This question was submitted to the jury very favorably for the plaintiff, and by finding in favor of the defendants they must have found that no such consent or authority was given by the owner to the contractor.
All of the material constituting the plaintiff’s claim except $2.50 worth, was furnished after the contract against liens was on file and indexed in the prothonotary’s office. If the plaintiffs had shown or offered to show that they made inquiry of the defendant in regard to the date of the contract, and the fact that it had not been filed for more than ten days after its apparent execution, and ..they had been informed that it was
The second and third assignments relate to the ruling of the court upon offers of evidence. But these rulings were not excepted to, and therefore these assignments cannot be considered.
The fourteenth assignment is in regard to the answer of the court to an inquiry made by the jury, after the charge had been completed and the jury had retired. This assignment does not appear to be based on an exception. In addition to this we are unable to see that the plaintiffs have any just ground of complaint in regard to the instruction given by the court to the jury in answer to their inquiry.’ In fact we consider the answer moré favorable to the plaintiff than the law warranted.
In our opinion the questions raised by the several assignments of error do not convict the court of any serious or reversible error, and therefore the assignments are all dismissed and the judgment is affirmed, at the costs of the appellants.