OPINION
Plaintiff, Custom Roofing Co. (Custom), entered into a subcontract to provide roofing on a school construction job specifying the use of materials from defendant, Owens-Coming Fiberglas Corp. (OC). OC had two offices in Phoenix, Branch and Supply. Branch sold exclusively to approved roofing contractors. Custom was not an approved contractor. Custom, however, had bought OC materials from Supply for many years. Custom sought quotes for materials from Supply and then placed an order with Supply. Supply ordered materials to fill this order from an OC factory and arranged a shipping schedule. OC sent a preliminary notice of lien to the school and to the general contractor. Thereafter, at the direction of defendant, Robert Ailing, an employee of Branch, those orders were cancelled. Custom, because of its inability to obtain the necessary materials, lost its contract. It brought suit for breach of contract and tortious interference with contract. The jury found in its favor, awarding $35,000 compensatory and $105,000 punitive damages. Remittitur reduced the compensatory award to $14,144. OC appeals from the judgment and Custom cross-appeals from the remittitur and from the refusal to allow prejudgment interest.
OC contends first that it did not accept the Custom order so that no binding contract was formed. It further argues that if such a contract was created, it is
The requirements of the statute of frauds, A.R.S. § 44-2308, now renumbered as § 47-2201, are met by the following facts:
(1) The failure to object to the written purchase order confirming an oral understanding of the prior day. A.R.S. § 44-2308(B);
(2) The internal memoranda of OC ordering the goods to fill the Custom order, conduct clearly evincing a belief in a contractual obligation;
(3) The filing of a preliminary notice of lien by OC in approximately the amount of the purchase order; and
(4) The testimony at trial of agents of Supply that they had accepted the order. A.R.S. § 44-2308(0(2).
OC concedes that if its contract with Custom is valid, as we have determined, it is liable for tortious interference with the contract between Custom and the general contractor on the school job. It contends, however, that its employee, Ailing, because he was acting in the scope of his employment cannot be independently liable for his acts of interference. We know of no general rule insulating employee tortfeasors from liability. The cases cited to us,
Petroni v. Board of Regents,
OC next argues that the evidence is insufficient to support a punitive damage award because the conduct of Ailing was neither motivated by ill will toward Custom nor wanton, willful or in reckless disregard for the rights of others. See
Schmidt v. American Leaseco,
With respect to the remittitur issue on cross-appeal, the parties are agreed that $14,144 is proved. The difference between that and the jury award of $35,000 depends on the testimony of an officer of Custom that had OC products been used at a higher cost than those anticipated in Custom’s bid, Custom would have expected to be reimbursed by the general contractor. The general contractor’s testimony, however, was that while negotiations might occur there was no agreement as to what, if any, adjustment might be made. On these facts, that Custom would have earned more is wholly speculative,
Rancho Pescado, Inc. v. Northwestern Mutual Life Ins. Co.,
The trial court also acted properly in rejecting Custom’s claim for prejudgment interest. Such interest is appropriate only where the claim is liquidated, where the evidence furnishes “data, which, if believed, makes it possible to compute the amount with exactness, without reliance upon opinion or discretion.”
Banner Realty, Inc. v. Turek,
The judgment is affirmed.
NOTE: This cause was decided by the Judges of Division Two as authorized by A.R.S. § 12-120(E).
