85 W. Va. 516 | W. Va. | 1920
From a judgment for plaintiff pronounced by the lower court sitting in lieu of a jury in an action of assumpsit to recover money paid defendants, alleged to belong to plaintiff as trustee in bankruptcy, defendants prosecute this writ. On July 5, 1916, the Bluestone Construction Company, now bankrupt, contracted with the State Board of Control for the construction of a certain addition to Welch Hospital No. 1, at Welch, the work to be completed on or before December 1, 1916. The contract contained this provision: “If, at any time, the contractors should for any cause fail or be unable to secure sufficient supplies, mate-nial or labor to continuously and diligently prosecute the work in such a manner as to complete it within the time specified,
Shortly after the date of the contract the Bluestone Construction Company employed defendants to install the plumbing specified for the building. The former was unable to complete the building within the time specified, and defendants, becoming aware of its probable insolvency shortly after they began to perform their agreement, notified the Construction Company orally and the Board of Control by letter, January 20, 1917', of their intention not do the work they had contracted to do. In order to expedite the completion of the building, the superintendent of construction for the Board of Control, acting for and on its behalf in accordance with the provisions of paragraph six, verbally notified defendants to proceed with the plumbing and assured them that if they did the Board would pay them out of the balance due the Construction Company. Defendants, acting upon that assurance, installed the plumbing and completed the installation about February 10th, the date on which the Construction Company petitioned for and was adjudged a bankrupt. Two days later they presented to the Board of Control their bill for the services rendered, amounting to $327.00, of which the Board paid $189.25, deducting that sum from the unpaid balance due under the building contract. To recover the amount so paid, plaintiff, as trustee, instituted this action, charging such sum to be part of the assets of the bankrupt’s estate; and it seems that was the view taken by the trial court.
With this opinion we do not agree. Though deducted from the balance that would then have been due and payable to the bankrupt, had it fully performed the contract without the intervention of the Board of Control, as authorized by paragraph six, nevertheless under the circumstances the money formed no part of the assets of his estate. Similar provisions for like contingencies occasioned by default or failure of a contractor to complete his work within a reasonable time by giving the owner the right to take charge and to complete it at the builder’s expense, are not uncommon in building contracts. 9 C. J. 812, 813;
Though the promise given orally by the superintendent to pay defendants for their work was in substance one to pay the debt of another, the Board derived some benefit to itself thereby, which it otherwise would not have had, and for that Teason it is an
For these reasons we reverse the judgment of the court below, and on the agreed stipulation of facts enter judgment for defendants, and award them costs.
Reversed; judgment for defendants.