203 Mass. 448 | Mass. | 1909
Webster Court is a private way the fee of which, subject to the defendant’s right of way and to the right of the city of Worcester to maintain a sewer therein, is in the plaintiff. As to the foundation which the defendant has projected into the way, the master has found as follows:
“ The respondent has projected the foundation of its building (but'no part of the superstructure) over into Webster Court.
“ Said projections consist of a concrete foundation twelve feet deep at its westerly end, five feet at its easterly, fifty-five and*450 four tenth's (55.4) feet long, and extending into the limits of the way, two and forty-six hundredths (2.46) feet at»the bottom, sixty-five hundredths (.65) feet at the top.
“ Thus occupying one hundred thirty-six and twenty-eight hundredths (136.28) square feet.
“ This foundation was begun and finished within the three weeks preceding Feb. 12, 1909.
“ This foundation is substantially on a line with or below the surface of the way. The superstructure of the building sets back from the way four or five inches.
“ The respondent company knew the line of the way and extended its foundation beyond said line with full knowledge thereof. It did not notify the complainant that it proposed so to do or ask consent therefor, but it was told by the contractor of the building that it was all right to extend foundations over the lines of streets and ways. With this information and in the desire to obtain as large a mill building as possible, it erected its mill on the line of the court, and extended the foundation therefor into the limits of Webster Court, the fee of which subject to the rights above mentioned was owned by the complainant. ”
In this manner the master finds that the respondent has “ deliberately appropriated to itself the right to project its foundation two and forty-six hundredths (2.46) feet into the limits of the court.” While no part of the superstructure projects into the court, still the master has found that if this projection be cut off the remaining foundation would not be adequate to support the superstructure. In a word, the building is in part supported by the projecting part of the foundation, and that support is essential to the maintenance of the building in its present condition. And all this has been done without any claim of right, or even a plausible pretense of such a claim. The statement made to the defendant by the contractor that “it was all right to extend foundations over the lines of streets and ways,” was manifestly applicable only to such ways as were public, and falls far short of showing or justifying the inference that the defendant was acting under a claim of right.
Moreover the defendant had notice. While it is true that the foundation had been laid before the defendant received the letter
Here, then, is a plain, intentional violation of the right of the plaintiff as owner of the fee of the way, made under no mistake of fact, or of law, or claim of right, and (as to a considerable part of the building) after an express warning that the owner would allow no encroachments.
That in such a case equity can give relief by way of mandatory injunction is too clear for discussion, and we do not understand the defendant to contend to the contrary. It contends, however, that in many cases this kind of relief is refused, and the party whose right is violated has been remitted to his remedy at law upon the ground that it would be inequitable and oppressive to compel the defendant to restore things to their former condition; and in support of this contention it has cited several cases in this State, among which are Lynch v. Union Institution for Savings, 159 Mass. 806, Jackson.v. Stevenson, 156 Mass. 496, Harrington v. McCarthy, 169 Mass. 492, and Levi v. Worcester Consolidated Street Railway, 193 Mass. 116, as well as many in other jurisdictions where this principle has been recognized and applied. They need not be considered here in detail. The principles governing the action of a court of equity have been considered in many recent cases beside those above mentioned. See among others Tucker v. Howard, 128 Mass. 361, Starkie v. Richmond, 155 Mass. 188, Methodist Episcopal Society v. Akers, 167 Mass. 560, Attorney General v. Algonquin Club, 153 Mass. 447, Codman v. Bradley, 201 Mass. 361.
We see no redeeming feature in the case before us so far as respects the manner of the trespass. Nor do we think that the fact that an injunction will impose upon the defendant an expense disproportion ate to the apparent benefit to the plaintiff is
It may be remarked also that we are dealing not with a right of an equitable nature, for an injury to which the remedy is only in equity, but with a legal right for an injury to which an action of trespass will lie. This building as it stands is a continuing trespass, and successive actions at law can be brought. And upon the facts found by the master there would be no apparent defense to such an action. It is manifest that after judgment in the second action the plaintiff here would be entitled under R. L. c. 186, § 3, as part of the judgment, to an order abating the nuisance. We see no reason under the circumstances of this case why it should be compelled to take this more dilatory method to enforce its rights.
Decree for the plaintiff for an abatement of the nuisance, including the removal of the projecting foundation.
The master found “ that the plaintiff up to the time of filing this bill and up to the time of the hearing has suffered no actual damage from said encroachments . . . that the fair market value of the one hundred thirty-six and twenty-eight hundredths square feet of unencumbered land in the vicinity of said way is $35.00. No evidence was introduced and I am unable to determine upon any evidence the fair market value of land occupied by the encroachments subject to the defendant’s right of way over it, and with reference to the city’s sewer location fifteen feet to the north, and between said land and other property of the petitioner. I find that the defendant can undo its encroachment in three ways : 1. By tearing down the end of the building and setting the foundation back. This can be done for $1,927.40. 2. By temporarily supporting the superstructure and tearing down and rebuilding the foundation. This can be done for $825.41. 3. By cutting off the projection and strengthening the foundation on its own land. This could be done for $987.14.”