90 Cal. 68 | Cal. | 1891
This action is to foreclose a mechanic's lien, and the complaint sets forth two counts,—the first
The defendant Ross, in his answer, among other things, admitted the contract for $525, and claimed to have paid all he owed thereunder, and alleged another contract to have been made between the parties for $325, which included all of the work done and performed as to the second cause of action stated, and further alleged that the whole sum due the plaintiff by defendant, upon any ground, was the sum of $109.50, of which tender of payment had been made to and refused by the plaintiff.
The question as to what amount was due for all the work done was, by consent of both parties, upon a suggestion of the court, submitted to a jury, who, upon that special issue, found for the plaintiff in the sum of $289.15.
By inadvertence, the clerk entered up a judgment upon this verdict, when the other issues as to the existence of a mechanic’s lien, amount of attorney’s fees due, counterclaim set up by defendant, etc., remained undetermined by the court. Upon this being brought to its attention within a reasonable time, the judgment was set aside, and evidence had as to the other matters involved. Thereupon the court adopted the advisory verdict of the jury upon the specific matter therein involved, and made findings as to the other issues, upon which a decree and judgment was duly given, made, and entered, enforcing the lien, etc. From that, and an order denying a new trial, this appeal is taken.
The first point made for a reversal of the judgment and order is, that the evidence is insufficient “ to sustain the judgment.” The reason given in the appellant’s points and authorities being, that each cause of action
The particulars in which the evidence was stated, in the first specification of the insufficiency of the evidence to sustain “ the verdict, findings, and judgment,” does not contain anything which points to the question raised, and hence it was not fairly called to the attention of the trial court, and was therefore not to be considered. It nowhere appears therein that the evidence was alleged to be insufficient to show that any specific part of the work was unperformed, or that the value of any specific part thereof remained unproved. It is thus stated: “The evidence is insufficient to sustain the verdict, findings, or judgment, for the reason that there is no testimony proving what was the value of said work, or that the same was ever performed, as alleged in the amended complaint.”
This could only have reference to the whole work claimed to have been performed under both counts of the complaint; that performed by virtue of the contract; that under a quantum meruit; and that claimed for extra work under both contracts.
The only other respect in which the evidence is specified to be insufficient is thus stated: “The evidence shows that the entire amount due to the plaintiff was not more than the sum of $850, and that all of such sum had been paid.”
This certainly does not intelligibly assert that the evidence was insufficient to show upon which story of the building the extra work was proved to have been done.
The party moving for a new trial for insufficiency of evidence must specify in the statement the particulars wherein the evidence is alleged to be insufficient, in
Besides, the specifications as to the insufficiency of the evidence to sustain the decision are not directed at any particular one of the numerous findings of fact upon the various issues involved here, but at all of them; at the verdict which was adopted by the court, and a finding made thereon (the case being one in equity), and at the judgment. This renders the specifications as set out in the statement and relied on to show error insufficient, under the rule declared by the appellate court of this state. (Coveny v. Hale, 49 Cal. 555; Hayne on New Trial and Appeal, sec. 150.)
It is further contended that the court below erred in allowing the plaintiff to show that a certain written contract introduced by defendant was signed by the plaintiff, through the misrepresentation of the defendant, and that the plaintiff had never intended to sign that contract, but supposed he was signing one which had before that been drawn up in lead-pencil.
The action was brought on a contract such as the lead-pencil draught contained, and the defendant, in the answer, denied the performance of the contract as sued on. When he introduced the written contract to show the real nature of the transaction as he claimed, it was competent for the plaintiff, in support of the issue made, to show that in point of fact he had made no such contract as defendant had brought forward in evidence.
■ One cannot be made to stand on a contract he never intended to make. If the defendant had sued the plaintiff, and sought to charge him on such a contract, it would certainly be competent, in defense, to show that
The verdict rendered by the jury was upon a special issue advisory to the court, submitted by consent of all the parties, and it was not error on the part of the court to instruct the jury as it did.
The setting aside of the judgment upon the verdict in an equity ease, which judgment had been inadvertently entered by the clerk, without judicial sanction, and when other issues of fact remained yet to be determined by the court, and the trial of those issues upon the evidence introduced, the adoption of the advisory verdict and finding thereon, and the other issues, was proper, and as no error appears in the record, we advise that the judgment and order be affirmed.
Belcher, 0., and Vanclief, C., concurred.
For the reasons given in the foregoing opinion, the judgment and order are affirmed.