51 La. Ann. 29 | La. | 1899
The opinion of the court was delivered by
The plaintiff applied in the District Court for a-mandamus commanding the defendant to receive, transport and deliver poles, wires, cross-arms, etc., offered to bo shipped by it on the line of the latter’s railroad from Boutte station to Morgan City, Louisiana, and to deliver the same in the swamps along the line of the defendant, between the said termini. That the right of the railroad company to regulate the time, .order and manner of delivery, so as not to conflict with its other business, be protected by said judgment, and" its right to demand and receive from plaintiff the usual, just and proper freight charges for said service, be also reserved.
The application was based upon allegations, that plaintiff was-actually building a telephone line from New Orleans to Morgan City, for the service of the public. That to erect said line it required poles, wires and cross-arms. That said line was being built along the line of the defendant’s company, between Boutte station and Morgan City,
That said freight was to be shipped at New Orleans, and at Boutte .station. That defendant was properly equipped for the carriage of the same, had done so for other corporations, and did not place its refusal upon the ground that it had stations to which to carry the same. That defendant’s refusal to receive and carry said freight was .arbitrary, and operated to suspend the building of plaintiff’s line; that defendant was a public carrier, organized under the law of Louisiana, and domiciled in New Orleans; that it was bound by law and by its charter to render the services to all the public alike. That plaintiff was without a remedy except by mandamus, and said railroad .company should be ordered, after hearing, to receive, carry and discharge the said poles, wires and cross-arms offered to it by plaintiff, from swamps along the line of its -road from Boutte station to Morgan City.
The court ordered an alternative writ of mandamus to issue.
The defendant answered under benefit and reservation of a prior peremptory exception, that plaintiff’s petition disclosed no right or cause of action. Defendant further excepted, that plaintiff prayed the 'enforcement of no duty which was defined by law, and sets forth no right which was granted by law and which was free from doubt. In its answer, defendant admitted its creation by act of the. General Assembly of Louisiana, of the 8th of March, 1877.
It admitted that it owned a railroad, and a right of way between Boutte station and Morgan City, but it averred it did not operate the said railroad, and did not for its own account receive, transport, and • deliver freight along said railway. That said railway and appurtenances were operated by the Southern Pacific Company, a corporation •erected under the laws of Kentucky, the railroad and its appurtenances having been delivered to the last named corporation under a contract of lease, and respondent had not the right or power to make •any contract respecting the receiving or transferring of freight upon
Respondent denied that it had done for other corporations or for any corporation what was demanded of it by the plaintiff. Respondent denied that its refusal to receive and carry the said freight as-described in plaintiff’s petition was arbitrary, or that such refusal operated practically to suspend the building of plaintiff’s line. Respondent averred that between Bontte station and Morgan City, in the so-called inaccessible swamp, there were on defendant’s lino-fifteen sidings or side tracks and stations the longest distance between these stations and sidings being less than six and one-half miles, and the shortest being less than one and one-half miles. The distance-between Boutte station and Morgan City being1 fifty-six and one-half miles, there was one siding then to every three G3-100 miles.
Resjiondent averred, that there were operated upon its line on each and every twenty-four hours, fourteen regular schedule trains, (four of which carried the United States mail), passing to and fro between Morgan City and Boutte station. That between these named stations' there was a large number of irregular trains necessary for the proper conduct of the business, and for the trans-continental traffic which-
That, in the face of these conditions, it was unusual and extraordinary for plaintiff to demand that the material for its proposed line should be delivered between regular stations, and that there were no-usual or proper charges for such services fixed by law, by custom, or by contract. That it was under no legal duty or obligation to receive and deliver in swamps, along the line of its railway between the stations aforesaid, except at regular stations, any of the material of the plaintiff, and, that if it should undertake to do so, or agree to do it,, such undertaking would be a matter of contract, the terms and conditions of such contract must be fixed with reference to the situation,, all the circumstances of which in this, or any like judicial proceeding,, could not be brought to the knowledge of the ¡court, and it was, therefore, beyond the power of the court to coerce respondent into the making of the contract with the plaintiff, and to compel respondent by mandamus to perform a service, the conditions of which could not be known to the court, or be expressed in its writ. Respondent averred, that if had never delivered along the line of its railway between stations, any poles, wires, or cross-arms for the construction of telephone or telegraph lines, nor had the same been delivered by its lessee, except for its own use and needs, and in the performance of its-contract obligations with the Western Union Telegraph Company, by
Defendant annexed to its answer, the contract between itself and the Western Union Telegraph Company. The District Court rendered judgment, perpetuating the alternative writ of mandamus, and ordering a writ of mandamus to issue, commanding the Morgan’s Louisiana and Texas Railroad Company to receive from the plaintiff, •and to transport and deliver the poles, wires, cross-arms and materials offered to be shipped by the plaintiff for the purpose of building its telephone line along the line of said railway, from Boutte station to Morgan City, in the State of Louisiana, and to deliver the same in the ■swamps along’ the line of the said railway company between the said termini at points to be designated by the shipper
The court, in its decree, recognized the power mid right of the defendant company to regulate the time, order and means of delivery, •so as not to conflict or interfere with its regular business and passenger traffic, and to receive from the plaintiff the usual just and proper freight for the said service. It reserved the rights of the parties on this subject, declaring the same protected by the decree.
Defendant appealed.
The contract referred to in the pleadings between the Southern
It began with the recital, that the Southern Pacific Company leased and operated certain railroads and property of other railroads, which were described, among them the defendant company — that the Western Union Telegraph Company had certain contracts with these companies, and it was desirable, and to the interest of all parties 'to. supercede by a new agreement, all- contracts then in existence, whereupon, it was substantially agreed, that the Telegraph Company should purchase all lines of poles then owned by the Southern Pacific Company, or by any of its branches, with all the instruments, etc.
The outstanding accounts between the parties were adjusted, and provision was made that thereafter, the telegraph company should furnish all the necessary material to construct and reconstruct the line of wires between New Orleans and El Paso on its part, and that of the roads it leased or operated. The railroad company agreed to transport, free of charge, over the railroad covered by the agreement upon application of the superintendent or other officer of-the telegraph-company, all persons in the employ of that company when traveling on business of the same, and also, to transport and deliver free of charge-along the line of said railroads, all poles and other material and supplies for the construction, operation, maintenance, repairs and renewal and reconstruction of the lines and wires covered by the agreement, and of such additional wires and lines of poles and wires as-might be constructed under the provisions of the agreement, and all material and supplies for the establishment, maintenance and operation of the offices of both parties to the agreement, at places along and adjacent to said railroad, it being understood, that all poles and other material and supplies for use of any said railroads should be transported free over any and all of the railroads covered by the agreement. The railroad company agreed to furnish all the labor to set the-poles in the ground, and to erect the first wire and the insulators thereof, and thereafter, to maintain and keep'in order and repair the-telegraph company’s poles and wires, as well as those which might thereafter be erected. The parties agreed that a wire should be set' apart for the use of the railroad company, and the remainder of the wires without limit, should be used by the telegraph company for its general business. The contract provided for the free transmission of messages, relating- to the railroad and steamship business, to any
The telegraph company agreed to furnish the operators and the railroad the offices needed.
The Sixth article of the contract was as follows:
Sixth — “The Southern Pacific Company, so far as it legally may, hereby grants and agrees to assure to the telegraph company the exclusive right of way on, along, and under the line, lands and bridges ■of the railroads, covered by this agreement, and any extensions and branches thereof, for the construction, maintenance, operation, and use of lines of poles and wires, and underground or other lines for commercial or public uses or business, with the right to put up or con•.sfruct, or cause to be put up, or constructed, at the telegraph company’s own proper cost or exx>ense, from time to time, such additional wires and such additional lines of poles, and wires, and underground, or other lines, as the telegraph company may require; the lines to be located on the railroad right of way, such distance from the tracks, and in such manner on bridges, as the Southern Pacific Company may •designate; and the Southern Pacific Company agrees to clear and keep clear said right of way of all trees, undergrowth, and other obstructions to the construction and maintenance of the line and wires, provided for herein, and the Southern Pacific Company will not, if it may lawfully refuse to do .so, transport men or material for the construction, maintenance or ox^eration of a line of poles and wire, or wires, •or underground or other lines in competition with the lines of the telegraxjh company, party hereto, exeexat at, and for the Southern Pacific Company’s local rates, nor will it furnish for any competing lines, any facilities or assistance, that it may lawfully withhold, nor if it may lawfully decline to do so, stop its trains, nor distribute any material therefor at other than regular stations.
“Provided, Always, That in protecting and defending the exclusive ■grants conveyed by this contract, the telegraph conpany may use any proceeding in the name of the Southern Pacific Company or of any ■other corrpanies, for which it is acting hereunder, but shall indemnify and save it and them harmless from any and all damages, .costs, charges and legal expenses incurred therein or thereby.”
Prior to the bringing of the present suit, a correspondence took
Under date of June 6th, Crandell telegraphed to Mr. Hutchinson, then in New York, to inform him of his conclusion in reference to the distribution of telephone poles. He said that his company did no telegraph business, that the Illinois Central, after first refusing on .account of contract with Western Union, finally recognized that the proposed distribution did not conflict therewith. He asked him to arrange matters while in New York. Mr. Hutchinson telegraphed hack, he would await the return of his attorney who was absent, before reaching a decision. On the 20th of June, he telegraphed Mr. Crandell, “he could not arrange as requested, too many complications likely to arise.’’
On the 23rd of June, Mr. Crandell wrote to Mr. Hutchinson, the -following letter:
“Dear Sir — As you are aware from my conversation with you, this • company 'is building- a telephone line along the route of Morgan’s Louisiana and Texas Railroad, but not on its right of way, between New Orleans and Texas, and cannot build that portion of the line between Boutte station and Morgan City, unless the railroad company will render this company the same service it renders the telegraph company.
“We understand you refuse to do this because your contract with the Western Union Telegraph Company prohibits it, and are confirmed in that belief by your telegram of the 20th instant, as follows: ‘Cannot arrange as you request. Too many complications likely to arise.’
“Fully impressed, with the desire to live on good terms, and fully ■ appreciating that public corporations should not quarrel, and seek the courts if it can he avoided, we have submitted to the refusal, and in- • curved the extra expense of wagon distribution, wherever we could •distribute by wagon. We are now, however, confronted with the situ- ■ ation that we -cannot distribute in the swamps between Boutte station and Morgan City, unless your railroad company will extend the customary facilities; we must, therefore, either abandon the line, or insist upon the performance of this duty.
“It is with deep regret therefore, that we announce to you that we must insist upon an early distribution of poles, and if your company
To this letter, the following reply was received from Mr. Hutchinson:
“Dear Sir — I have your letter of the 23rd inst., and in reply thereto, I have to say that we shall be very glad to distribute your poles upon the line of the Morgan Road, and if we are at liberty to do so without violating the obligations imposed upon us by contracts made with the Western Union Telegraph Company, bearing date, the 3rd day of January, 1887, under which we agreed, among other things, that we would not furnish for any competing line any facilities or assistance,. that we might lawfully withhold, nor if we might lawfully so to do stop our trains, nor distribute material therefor at other than regular stations.
“I need not say that we should like to do this business for you and' earn the compensation to be earned by doing it; that we are acting against our own immediate pecuniary interests in declining to do it, but, we have made a contract with the Western Union Telegraph Company and we wish fairly and honorably to fulfill the obligations which - wo have assumed therewith. We do not wish to extend those obligations one whit beyond their fair and reasonable meaning, but, on the other hand, we do not wish to avoid any obligations which we have fairly assumed. If the court should hold, that, nothwithstanding this contract with the Western Union Telegraph Company, we are -bound to distribute your poles upon receiving reasonable compensation therefor, we shall certainly be glad to earn the compensation to which-we should be entitled for rendering the service, but we ought perhaps to correct an error in your letter in which you say that you cannot distribute your materials in the swamps between Boutte station and' Morgan City, unless the railroad company will extend some facilities to you in connection therewith. This must be a mistake on your part, as the Postal Telegraph Company has recently constructed a line between these points without our extending to them any facilities in connection therewith, and I know of no reason why you cannot do what the Postal Telegraph Company has done in that respect. At the-
On the 15th of July, 1898, replying to a letter of Mr. Crandell, which is not in the transcript, he wrote to him as follows:
“New York, 21st July, 1898.
“Dear Sir — I have received your favor of fifteenth, suggesting that you hope before the matter of distribution of poles is submitted to the courts, I might reconsider my decision on the subject. I am perfectly willing to reconsider the matter, but I don’t see how I can change the views in reference to it, whiclTwere expressed in my letter to you of the 27th ult. We should be very glad to do the business of distributing the poles at reasonable prices therefor, if we were at liberty to do so without violation of our contract with the Western Union Telegraph Company, which I referred to.”
Opinion.
The question which meets us at the threshhold is, whether the plaintiff is authorized to institute this action.
When a corporation undertakes to operate a railroad' franchise, it assumes all- the duties and obligations which spring by law from the characte1’ of its business, and from the customs incidental to it. It tendei-s a continuing offer to the general public, that it will perform these duties for the benefit of each and every one of them, when demanded at their hands.
When any member of the public makes a demand upon it under the general offer, there immediately results a civil obligation on the part of the company, in favor of the parties making the demand enforceable, through the usual legal remedies by which contracts are enforced; were it not so, there would be a right without a remedy, for it could not be pretended that the State officers could be called upon to bring actions in the name of the State, for the enforcement of the performance of duty by the company to all the private individuals with -whom they have business relations.
It is said that these various parties have an action for damages
There is nothing- in this claim.
The party owing’ the duty cannot drive the other party to an action for damages, and by payment of money, resist the performance of duty. What the plaintiff in this suit asks for and is entitled to, is the transportation of his freight, and not the payment of money to him. The latter would furnish no adequate remedy.
It is said that the mandamus cannot be granted, because the court would be called upon to make itself a contract between the parties, and this it is not authorized to do.
The court is not called upon to make a contract between the parties, but to order the performance by the company of the duties as a carrier, which it refuses absolutely to recognize as incumbent upon it, under any terms or conditions.
The company is left free to charge for its services upon a quantum meruit.
While we have taken up these questions and disposed of them, it is. very evident from the correspondence between the presidents of the two companies; from the pleadings in the answer, and from the stipulations in the contract annexed to the answer, that the service which the plaintiff demands at the hands of the defendant, is one which the latter is able, willing and anxious to perform, and that the only reason which stands in the way of its performance, is the contract which it' has made with the Western Union Telegraph Company.
We think it quite evident, that the defense set up in this case,, though made hi the name of the Morgan’s Louisiana and Texas Railroad Company, is one in reality made in that name by the Western Union Telegraph Company, under the stipulations in the contract made between it and Morgan’s Railroad Company, and the real question is, whether the court will permit a railroad company to tie itself up in the discharge of its duties as a public carrier, by a contract such as that shown by the record.
We think such a contract against public policy, in restraint of trade, and that it should not be permitted to stand in the way of the company’s affording to the general public all the facilities it can consistently render, and is willing and able to render.
We think such a contract should he brushed aside.
For the reasons assigned, it is hereby ordered, adjudged and decreed, that the judgment appealed from be and the same is hereby .affirmed.