57 N.Y. 560 | NY | 1874
Lead Opinion
Neither party has appealed from that portion of the judgment of the General Term of the Supreme Court which reverses the judgment entered at Special Term. It must consequently be assumed that the complaint was improperly dismissed. The only question, therefore, presented for our decision is, whether the General Term properly rendered judgment for damages in favor of the plaintiff.
It appears by the decision of the justice at Special Term, that it was based on the ground that he considered the contract "so objectionable in its terms and in the circumstances under which it was procured, that a court of equity will not lend its peculiar and extraordinary jurisdiction to enforce it." The opinion given by INGRAHAM, J., on the reversal of the judgment entered on that decision shows, that while he considered the refusal to grant specific performance right, he thought that the justice "should have retained the case for the purpose of awarding to the plaintiff the damages he was entitled to for the non-performance." Assuming that such course ought to have been pursued, a new trial should have been ordered by the General Term. The question of damages was one that should be determined by the court or tribunal for the trial of issues of fact, and not by the appellate court, which can only review the decisions of the tribunal from which the appeal is taken. The General Term, therefore, erred in rendering final judgment in favor of the plaintiff for the amount of damages resulting from the breach, by the defendant, of the contract, which had never been passed on by the court below. *562
It is true that the findings of fact by the justice show that the plaintiff had paid the defendant the sums for which judgment was rendered by the General Term, on account of the price that he was to pay for the land sold to him, and, according to the findings, "in part performance" of his agreement; but those sums do not necessarily constitute the whole compensation to which the plaintiff would be entitled as damages. Indeed, the opinion referred to states certain facts, from which it is fairly inferable that there are other items for which an allowance could be claimed. It is unnecessary to mention them particularly, and without an examination of the evidence it would be impossible to say what would be proper to be allowed.
A new trial should be ordered, and upon the facts then disclosed it will be proper to determine what relief should be granted. It is not, under the circumstances in which the case is presented on the present appeal, proper to indicate whether the decision at Special Term, declaring that the plaintiff was not entitled to a specific performance, was proper or not, but that should be left an open question.
It follows, from the preceding considerations, that the portion of the judgment appealed from should be reversed and a new trial ordered, costs to abide the event.
Concurrence Opinion
The learned judge, before whom this cause was tried at Special Term in the Supreme Court, felt it his duty to dismiss the plaintiff's complaint, without costs. The action being for the specific performance of a contract for a conveyance of land, it rested largely in judicial discretion whether the decree prayed for should be granted or refused, and I do not propose now to consider whether that discretion, in this case, was discreetly exercised or not. Judgment having been entered, the plaintiff appealed therefrom to a General Term of the same court. That tribunal discovered in the evidence, and in the decision below, that the plaintiff had paid the defendant, including interest, something over $500 on account of the purchase-money provided *563 by the contract to be paid, and it appeared just that he ought to recover that sum back if he could not have the contract specifically performed. Accordingly, the judgment of the Special Term was reversed, and, instead of granting a new trial, final judgment was ordered in favor of the plaintiff for the sum paid on account of the purchase-money, and interest; with a further provision, that if either of the parties objected to the amount as the court had computed it, it was referred to a referee to compute the amount for which, under the decision, the plaintiff should have judgment. It does not appear that the plaintiff did anything further in the case until the defendant, by leave of the court, entered final judgment under the decision of the General Term. He then appealed to the Court of Appeals from every part of the judgment of the General Term, except that part reversing the judgment of the Special Term by which his complaint was dismissed, and in this condition the case comes to us for our determination. As the defendant has not appealed from any part of the judgment below, and the plaintiff has not appealed from that part reversing the judgment at Special Term, we must assume that both parties agree that the judgment of the Special Term was properly reversed; and the only question I shall consider is, whether a new trial should have been granted; or, whether the subsequent action and order of the General Term has been in accordance with law.
It cannot be denied that, under very many circumstances, where a court of equity would not decree the specific performance, the party aggrieved may have an action at law for his damages. It is, also, well settled, that in many cases where courts of equity have obtained jurisdiction in a suit for the specific performance of a contract, and find it necessary to refuse the decree, the bill, in the discretion of the court, may be retained, for the purpose of awarding the complainant his damages; and these damages have been ascertained, sometimes, by a reference to a master of the court, or, upon issues sent to a jury. I shall not undertake to debate the question, how far the organization *564 of the present Supreme Court in the powers of its different branches is analogous to the powers of the late Court of Chancery. It may perhaps be admitted, that if in this case the trial judge, instead of dismissing the complaint absolutely, had retained it for the purpose of awarding the plaintiff his appropriate damages, a very different question of practice would have been presented. In that condition the case would have been within the control of the court of original jurisdiction, and every proper order in furtherance of justice could, and doubtless would, have been made.
It certainly will not be doubted, that where a party cannot have the specific performance of a contract, yet may still be entitled to his damages consequent upon the non-performance, such damages are not necessarily limited in amount to the sum actually paid by the plaintiff, with interest, on account of the purchase-money provided to be paid by the contract, no matter by what tribunal the amount is to be ascertained. In this case the General Term of the Supreme Court has peremptorily limited the plaintiff to the amount actually paid, with interest, without, in my judgment, giving him any form of trial known to our present system, and I think without any authority of law. The plaintiff demanded specific performance of the contract and the evidence given on the trial had reference solely to that demand, and proof of the amount paid on the contract was given in aid of that issue alone. No consideration of plaintiff's damages, in case he could not have performance, was had at the trial term, at all.
Upon the appeal from the judgment dismissing the plaintiff's complaint, the General Term of the Supreme Court had power to reverse, affirm or modify the judgment appealed from, or order a new trial. (Code, § 330.) That court did reverse the judgment appealed from and then rendered a final judgment in favor of the plaintiff, who had been defeated below, for such sum as from an examination of the evidence it was thought he should have recovered at the Special Term. This the General Term had no power to do. *565
They had power to order final judgment when the facts were agreed to by the parties or found by the court or a jury on the trial. (Purchase v. Matteson,
It is, however, earnestly insisted by the learned counsel for the defendant, that the judgment of the General Term was a substantial modification of the one appealed from, and to sustain this view we are referred to several adjudged cases. Marquat v.Marquat (
The case of Beach v. Cooke (
It is indeed found that the plaintiff had paid the defendant a given sum on the contract, for which the General Term rendered judgment in his favor, and it is urged that this is the limit and is conclusive as to the damages the plaintiff could recover by reason of the defendant's non-performance. That the amount of money paid on the contract may be recovered back is quite true, but that sum is not the damages resulting from non-performance, and, as before suggested, that question has never been tried anywhere, and if the plaintiff cannot have the contract performed, he is entitled to have his damages, if any he has sustained, assessed in a trial court, either by a judge or a jury, and the amount definitely ascertained. In this respect it is apparent the case at bar is different from that of Beach v.Cooke (supra), where the amount actually due on mortgage had been ascertained at the trial.
It is to be further observed that, as the case comes before us, the judgment of the Special Term stands reversed, and we cannot interfere with that part of the judgment of the General Term for the reason that neither party has appealed from it, and we cannot reverse or modify any judgment or *567 order other than "in the respect mentioned in the notice of appeal." (Code, § 330.) It therefore seems that there is an untried issue now at Special Term, whether the plaintiff is or not entitled to specific performance, and a judgment of the General Term in favor of the plaintiff for the money he had paid in performance of the contract, and this does not appear to be quite consistent.
There must be a new trial.
All concur.
Judgment, as far as appealed from, reversed and new trial granted.