OPINION
In 1984, Cubit Corporation sought to foreclose its claim of a mechanic’s lien against property owner Travis M. Hausler in the amount of $4,573.78 for planning and design services relating to real estate which was to be part of a planned community development in Lincoln County, New Mexico. As a result of Hausler’s subsequent bankruptcy proceedings, the case was closed subject to reopening upon proper application. Reinstatement occurred in January 1990 with the parties stipulating to submission of the case on briefs and depositions in lieu of trial.
The trial court issued a letter decision in November 1990, which subsequently was withdrawn and set aside. A bench trial was held in March 1991, with findings of fact, conclusions of law, and judgment for Cubit entered in May. All of Cubit’s requested findings of fact and conclusions of law were adopted by the court; Hausler’s trial counsel failed to file any proposed findings and conclusions. The trial court concluded that personal judgment against Hausler was barred under 11 U.S.C. § 524 (1988 & Supp. II 1990); that the court had in rem jurisdiction over the subject property which was not included in Hausler’s bankruptcy estate; that Cubit established a valid claim of lien; and that the project was abandoned by Hausler without fault of Cubit, constituting completion under Albuquerque Lumber Co. v. Montevista Co.,
Before discussing the merits, we nota that Hausler attempts to support his argument by referring to portions of the trial tapes without specifically challenging any findings or conclusions entered by the district court.
1
Our law is clear that oral statements by the court do not constitute its decision. Peace Found., Inc. v. City of Albuquerque,
We further note Hausler’s violation of Rule 12-213(A)(2) in failing to include references to the record in the summary of facts. Counsel for appellant is encouraged to comply with our appellate rules in the future. See Fenner v. Fenner,
Hausler presents two factual grounds for the contention that Cubit was not entitled to claim a lien; however, both were incorporated into the court’s findings of fact and, as stated above, are deemed conclusive on appeal. In affirming the judgment, we discuss only the legal question of whether a mechanic’s or material-man’s lien can attach to property where no improvement occurred due to the owner’s abandonment of the project through no fault of the claimant. This question presents an issue of first impression in New Mexico, although several New Mexico cases have addressed closely related issues. Our holding today extends New Mexico law to permit a lien on unimproved property under certain limited circumstances. 2
The statute under which a mechanic’s or materialman’s lien may be claimed, NMSA 1978, Section 48-2-2 (Cum.Supp.1992), states in pertinent part:
Every person performing labor upon, providing or hauling equipment, tools or machinery for, or furnishing materials to be used in the construction, alteration or repair of any mining claim, building, ... or any other structure, who performs labor in any mining claim, or is a registered surveyor or who surveys real property has a lien upon the same for the work or labor done, for the specific contract or agreed upon charge for the surveying or equipment, tools or machinery hauled or provided, or materials furnished by each respectively, whether done, provided, hauled or furnished at the instance of the owner of the building or other improvement or his [or her] agent, and every contractor, subcontractor, architect, builder or other person having charge of any mining, or of the construction, alteration or repair, either in whole or in part, of any building or other improvement shall be held to be the agent of the owner for the purposes of this section.
“The purpose of our lien statute is ‘to protect those who, by their labor, services, skill, or materials furnished, have enhanced the value of the property sought to be charged.’ ” Vulcraft v. Midtown Business Park, Ltd.,
Under present New Mexico law, an architect is entitled to a mechanic’s lien for preparing and furnishing plans, even if the architect does not supervise the construction, so long as the plans are actually used in the construction of the building. Gaastra, Gladding & Johnson v. Bishop’s Lodge Co.,
[S]ome physical work must commence on the designed structure in order for the architect’s lien to rise. The Gaastra case requires that the architect’s plans be actually used in the construction before the architect is entitled to a lien. Therefore, the lien cannot arise until some physical work has commenced upon the site (or until materials have been delivered thereto).
Id. at 491. Several New Mexico cases, however, have suggested that abandonment of a project, if through no fault of the lien claimant, does not affect the claimant’s right to a mechanic’s lien.
In Dysart v. Youngblood,
The district court based its conclusion that Hausler’s abandonment of the project constituted completion under Albuquerque Lumber Co. v. Montevista Co., which upheld a lien attached to property where the improvement had commenced but later was abandoned by the property owner. The claimant successfully filed a lien against the property upon which only a foundation and part of a wall had been constructed before the project was abandoned through no fault of the claimant. This Court held that the worthless improvement presented no obstacle to the claimant’s recovery.
While fundamentally and in a broad sense presumptive[,] benefit to the land improved by another’s labor or material from the beginning has afforded constitutional justification for and still supports the theory of mechanics lien legislation, yet so to recognize does not mean that a showing of benefit in a particular case is indispensable to the right to the lien____ Such a construction would greatly restrict the field of usefulness of these remedial acts as against those intended to be aided thereby.
Id. at 12-13,
Application of this rationale to the case at bar is consistent with the well-established public policy behind our lien law as announced in Ford v. Springer Land Ass’n,
Neither Dysart, which established a lien for a dry well, nor Albuquerque Lumber, which upheld a lien for a worthless, abandoned improvement, precisely addresses the issue at hand. Accordingly, we turn for guidance to those jurisdictions which have squarely confronted this issue. In Lamoreaux v. Andersch,
Nolte v. Smith,
Other California cases, Walker v. Lytton Savings & Loan Ass’n,
Allowing [a claimant’s] lien to stand is also not inconsistent with the idea that visible construction on the site serves to notify potential lenders of existing liens. That is because the architect can only assert the lien against the interest of the one who contracted for his services, not against other lien claimants. The doctrine of Lamoreaux arises only when the architect is the sole mechanic’s lien holder. When there are other mechanic's liens, all liens will date back to the commencement of the work of improvement. Thus, the lender will not face “invisible liens.” In other words, an architect has a lien as against the owner’s interest once the architect completes the contract. When the work of improvement commences, the architect’s lien dates from that point, with a priority relating to that date.
It would be manifestly unjust to deny an architect a lien because the person with whom the architect contracted has prevented the work that raises the lien. Architects have little or no control over the construction of their designs; they can do nothing themselves to begin work on the ground to make their liens valid. Consequently, this court adopts the holding of Lamoreaux, and rules that as against an owner who prevents commencement of a work of improvement, no actual or visible work on the ground is necessary for an architect to attach a mechanic’s lien if the lienable work is completed.
Id. at 978-79 (citation omitted).
Likewise, we find the Lamoreaux reasoning in line with the policy behind our lien law and the liberal construction necessary to serve its remedial purpose. Because architects rely upon their entitlement to a lien against property upon which they have contributed labor, the lien statutes should not be given a construction so narrow as to defeat their intent and purpose. To do so would undermine the purpose of insuring payment to those who render services toward a project that has been abandoned through no fault of a claimant.
Other jurisdictions have reached a similar result.
3
In Seracuse Lawler & Partners, Inc. v. Copper Mountain,
For the purposes of the mechanics’ lien law, the claimant is not to be charged with another’s mistake in judgment which results in the noncompletion of the project. To hold otherwise would defeat the purpose of the statute. An owner could easily shutdown a project before substantial completion, and, arguing that a partially complete project represents no value enhancement to the property, he could thereby leave those who worked on the project without any lien remedies.
Id. at 1331. Along the same line, the Indiana Court of Appeals recognizes an estoppel exception to the general rule that for a lien to arise, materials and labor must be actually used in the construction. In O’Hara v. Architects Hartung & Ass’n,
Based upon the above discussion and the intent of our legislature in enacting our mechanic’s lien statutes, we affirm the judgment of the district court in its entirety.
IT IS SO ORDERED.
Notes
. Hausler only cited finding of fact number 14 and conclusion of law number 5 as a reference for his statement of the issue.
. In extending our lien law, we are mindful of the dicta announced in Lembke Construction Co. v. J.D. Coggins Co.,
. In reaching our holding, we are aware of certain jurisdictions that, because of the wording of their lien statutes, hold an architect’s claim of lien invalid if construction or improvement does not occur. See, e.g., Torkko/Korman/Eng’rs v. Penland Ventures,
