OPINION
The owner of an office and warehouse, K & 0 Limited Partnership, sued the general contractor, CTTI Priesmeyer, Inc., and others for cracks that developed in the concrete slab foundation of its building. 1 Prior to trial, K & 0 settled with all defendants except CTTI and Duke Garwood Architects, Inc. The jury found CTTI liable for breach of contract, and Garwood hable for its negligence. During trial, K & 0 entered into a high-low settlement agreement with Garwood. The trial court entered judgment on the verdict against CTTI and denied any settlement credits.
CTTI raises five issues urging that, as a matter of law, the parties’ subsequent contract regarding repair of the cracks in the slab was a novation of the original contract warranting the building, or in the alternative, that the jury’s failure to find novation was against the great weight and preponderance of the evidence. CTTI also relied on the “one satisfaction rule” to claim that it was entitled to settlement credits. We hold that the novation issue was properly submitted to the jury and that the great weight of the evidence does not preponderate against the jury’s verdict. Furthermore, we rely on the supreme court’s ruling in
Crown Life Ins. Co. v. Casteel,
BACKGROUND
In 1997, K & 0 entered into a contract with CTTI for the construction of an office and warehouse building. K & 0 also entered into a contract with Duke Garwood Architects, Inc. to serve as the architect on the project. As such, Garwood’s plans and specifications were incorporated as part of the overall contract documents. The source of the controversy in this case is the building’s slab foundation that CTTI poured in the summer of 1997. Construc *679 tion was substantially completed in October 1997, and K & 0 moved into the facility at the end of that month.
Cracks in the slab appeared as early as late August 1997, and continued to increase in both size and number as the building was occupied and used. K & 0 consulted with CTTI, Duke Garwood, and John Buford, the project’s engineer, regarding the cracks; they were told that the cracks were typical for a slab of that size. Buford recommended that K & 0 contact a concrete repair expert. The repair expert confirmed that the cracks were the typical result of concrete shrinkage and recommended that K & 0 wait about four to five months for the slab to cure completely. The expert recommended that after the slab had cured, epoxy be applied to repair the cracks. K & 0 obtained an estimate of $182,000 as the cost to complete such repairs.
Pursuant to the expert’s report and recommendations, K & O and CTTI entered into a new agreement in April 1998, in which CTTI agreed to make the recommended epoxy repairs in return for K & O’s final completion payment. Whether this new repair agreement was a novation of the original agreement is at issue on appeal. The agreement detailed the necessary repairs to the slab floor, and provided, in pertinent part:
“The work of this Agreement is subject to all terms of the General Conditions of the Contract for Construction (a part of the Construction Contract between the parties) (the “General Conditions”) with the exception of the payments provision of such General Conditions.” and
“Notwithstanding the terms of the parties’ Construction Contract dealing with resolution of disputes, it is the parties’ agreement that this Agreement shall govern the resolution of their dispute
regarding correction of cement floor slab problems in lieu of arbitration. All other terms of such Construction Contract shall apply to the extent practical.”
CTTI repaired a test area in December 1998, but never repaired the entire slab. As the slab continued to deteriorate, K & O became convinced that the recommended repairs would not stop the deterioration. K & O again consulted a concrete repair expert regarding the condition of the slab. This time the engineers and experts agreed that the slab had been improperly designed and constructed. The testimony at trial indicated that multiple factors contributed to the problems with the slab. Some of the problems were design related, such as the improper spacing of control joints and insufficient designated concrete strength. Other factors were related to the construction of the slab, such as misplacement of rebar and the use of materials other than those designated in the plans and specifications.
K & O filed suit in October 1999 against CTTI, Garwood, Commercial Indemnity Insurance Company (the surety on the repair contract), and MLA Labs, Inc. (the geotechnical firm that had performed testing on the site). K & O later joined Bums Construction, Inc., the subcontractor who provided the fill material for the slab base. CTTI joined John Buford, the project engineer, as a third-party defendant. Prior to trial, K & O settled with the surety, the geotechnical firm, and the fill subcontractor, and such settlements were read into the record at trial. Trial proceeded against CTTI, Garwood and Buford in April 2008. K & O alleged that CTTI breached both the original construction contract and the subsequent repair contract. K & O reached a high-low settlement agreement with Garwood before the case was submitted to the jury.
*680 Nine questions were submitted to the jury, of which four are the subject of this appeal: Question 1 — Did CTTI fail to comply with the construction contract; Question 2 — Was CTTI’s failure to comply excused by a new agreement; Question 3— What damages flow from a positive answer to question 1 and a negative answer to question 2; and Question 6 — What reasonable attorneys’ fees arise from a finding of breach of contract. Although K & 0 alleged in its pleadings that CTTI had breached the repair agreement, a question as to that breach was not submitted to the jury, and K & 0 did not object to such omission.
The jury found that CTTI had breached the construction contract, that CTTI’s breach was not excused by the repair agreement, and that Buford and Garwood were negligent. On the basis of its findings the jury awarded K & 0 $561,750 for CTTI’s breach of contract and $400,000 for attorneys’ fees. The jury also awarded K & O $187,250 for Garwood and Buford’s negligence, and further determined that 70% of the negligence that caused the damages was attributable to Garwood and 30% attributable to Buford. However, under the high-low agreement, K & O settled with Garwood for $190,000 for negligence damages. The trial court entered judgment on the verdict awarding K & O a total of $1,071,714.48 from CTTI.- This amount included prejudgment and post-judgment interest, as well as attorneys’ fees and court costs; the trial court refused to grant CTTI any settlement credits. This appeal followed.
DISCUSSION
Standard of Review
CTTI raises five issues on appeal. Four of CTTI’s issues are raised as matters of law. CTTI’s second issue is a factual sufficiency point.
When reviewing a party’s assertion that its claim or defense was established as a matter of law, and where a jury has made an adverse finding of fact on that issue, we apply a special analysis.
See Holley v. Watts,
When reviewing a factual sufficiency challenge, we must assess all of the evidence and may not substitute our judgment for that of the trier of fact. When the challenge is to a finding on which the prevailing party had the burden of proof, we may reverse the judgment only if the challenged finding shocks the conscience or clearly shows bias, or if the favorable evidence is so weak as to make the judgment clearly wrong and manifestly unjust.
Pool v. Ford Motor Co.,
Novation
In its first two issues, CTTI contends that the repair agreement was a novation of the original contract as a matter of law, and in the alternative, that the jury’s failure to find a novation was against the great weight and preponderance of the evidence. The party urging novation as a
*681
defense bears the burden of proof.
Honeycutt v. Billingsley,
Where there are no inconsistent provisions, “a second contract will operate as a novation of a first contract only when the parties to both contracts intend and agree that the obligations of the second shall be substituted for, and operate as a discharge of, the obligations of the first.”
Chastain v. Cooper & Reed,
CTTI contends that the language of the repair contract is unambiguous and conclusively establishes that CTTI and K & O intended the repair contract to replace the construction contract with respect to the defective slab. While we agree that the repair contract is unambiguous, we find that the repair contract and the original contract do not have inconsistent provisions. Rather, the provisions regarding the specific steps to be taken to complete the repairs supplement the terms of the original construction contract. Other provisions expressly incorporate the terms of the original contract. The only significant modification to the original contract was the provision stating that any disputes over the repair of the slab would not be subject to the binding arbitration provision of the original contract.
A novation occurs if a contract evidences an intention to relinquish and extinguish pre-existing claims and rights of action. Here, the repair contract does not extinguish all claims of the previous contract, as CTTI argues, but instead incorporates and reaffirms the rights under that contract to the extent feasible. An agreement to make final payment upon completion of the repairs and not to require arbitration for any dispute over that repair is not inconsistent with the general terms of the original contract. The most important of these terms, that CTTI warrants delivery of a defect-free budding, is in fact referenced at least twice in the repair agreement, with the clear intention of maintaining its applicability to the extent possible. Paragraph 3(b) of the repair contract states, “It is the understanding of the parties that such work should approximate (as close as possible) the standard originally intended by contract.” Paragraph 5 states that “[a]ll other terms of such Construction Contract shall apply to the extent practical.” These statements address the possibility that even after the repair work, the building might not meet the defect-free standard warranted in the original contract. The statements serve to allow variation from the warranty to the extent necessary but no further. They *682 clearly evidence the intention that the original contract remain in force to the extent possible.
We agree with K & 0 that the two contracts on the whole addressed different issues: the original contract covered the entire construction process and warranted the final product, while the repair contract covered only the repair of cracks in the slab foundation. The new contract merely represented the parties’ agreement as to how to resolve the dispute over repair of the cracked slab in lieu of arbitration. Because there is no express language of no-vation and no inconsistent provision in the repair agreement, we find that CTTI can not surmount the first hurdle, that there is no evidence to support the jury’s conclusion that the repair contract was not a novation of the original contract.
See Holley,
In the alternative, CTTI argues that the jury’s failure to find novation is against the great weight and preponderance of the evidence. This is a challenge to the factual sufficiency of the evidence. In the absence of inconsistent provisions, we look to the intent of the parties to determine novation.
Allstate Ins. Co.,
The evidence and testimony presented at trial provided ample support for the jury’s decision that the repair contract was not a novation and did not excuse CTTI’s performance under the original contract. Mr. O’Hearn, a 50% owner of K
&
O, testified that K
&
O intended the repair contract to allow the parties to resolve the existing dispute over the slab without having to arbitrate, and that there was no intention to relieve CTTI of the warranty provided in the original contract. Specifically, he stated that in light of the fact that the slab, at the time of the repair agreement, was less than one year old; K & O was not in a position to release CTTI from any warranty work. This testimony, combined with the terms of both contracts, cannot be held to be so weak as to preclude an adverse finding on the issue of novation. There was contrary testimony presented by both parties that the agreement was intended to govern the entire dispute over the repair of the slab. However, there was also disagreement as to what was covered by the “dispute regarding correction of the cement floor slab problems.” There was some question as to whether it covered all potential disputes over the slab or just the dispute in existence at the time of the agreement. Where there are inconsistencies in the testimony presented at trial, it is the jury as fact-finder that is the sole judge of the credibility of witnesses and the weight to be afforded the testimony.
Leyva v. Pacheco,
CTTI also argues that the basic tenets of contract interpretation must be applied in this case. Particularly, CTTI argues that because the repair contract is not
*683
ambiguous, parole evidence regarding the parties’ intent should be inadmissible, and that if there is any ambiguity, it should be resolved against K & 0 as the drafter of the agreement.
See AT & T Corp. v. Rylander,
By virtue of the nature of the agreement’s language, the actions of the parties, and the testimony at trial, reasonable minds could differ over whether the requisite intent was shown.
Ames, 776
S.W.2d at 158;
Cropper,
In its third and fifth issues, CTTI contends that it is entitled to settlement credits under the “one satisfaction rule.” It argues that because the conduct of both CTTI and the settling defendants combined to cause a single, indivisible injury of a defective slab, it is entitled to credits against its judgment for all undisputed settlements.
2
K
& O
counters that under the holding in
Hunt v. Ellisor & Tanner,
CTTI is not entitled to settlement credits.
See
The one satisfaction rule is the longstanding proposition that a plaintiff should not be compensated twice for the same injury.
See Stewart Title Guar. Co. v. Sterling,
*684
More recently, the supreme court discussed settlement credits in
Crown Life Ins. Co. v. Casteel,
Under the one satisfaction rule, the non-settling defendant may only claim a credit based on the damages for which all tortfeasors are jointly liable. ... the nonsettling defendant is entitled to offset any liability for joint and several damages by the amount of common damages paid by the settling defendant, but not for any amount of separate or punitive damages paid by the settling defendant.
Id.
The court’s use of the words “tortfea-sor” and “liability” leads us to conclude that the one satisfaction rule applies only to tort claims, not to breach of contract claims. The supreme court’s further insistence that a nonsettling defendant receive settlement credits only for settlements based on damages for which there is joint and several liability confirms this understanding. It is also telling that while Texas has four different contribution schemes, each is only applicable to particular types of tort claims and not to contract claims.
See First Title Co. of Waco,
Joint and several liability arises in tort claims based on the conduct of the tortfeasors and the nature of the injury. “If the independent tortious conduct of two or more persons is a legal cause of an indivisible injury, each person is jointly and severally hable for the recoverable damages caused by the tortious conduct.” RESTATEMENT (THIRD) OF TORTS: APPORTIONMENT OF LIABILITY § A18 (2000) (emphasis added); see also RESTATEMENT (THIRD) OF TORTS: APPORTIONMENT OF LIABILITY § 10, cmt. b (2000) (explaining that joint torts are defined as those committed by multiple defendants acting in concert to cause indivisible injury). Texas has adopted a threshold version of this general rule in its proportionate responsibility statute, whereby in order to recover at all, a plaintiff must not be more than 50% responsible for the injury suffered. See Tex. Civ. Prac. & Rem.Code Ann. § 33.001 (West 1997). Additionally, the statute requires that the trier of fact determine the percentage of responsibility of each claimant, defendant, settling person, and responsible third party. See id. § 33.003 (West Supp.2004-05). The same chapter addresses rights to contribution for the various parties, including rights to offsets to reflect settlements with other parties. See id. § 33.012 (West Supp. 2004-05). These statutes apply when the cause of action is based in tort. See id. § 33.002(a) (West Supp.2004-05).
By contrast, joint and several liability arises in contract based upon the relationship between the parties and the existence of what amounts to joint promises. See RESTATEMENT (SECOND) OF CONTRACTS § 13 IN NT (1981) (more common usage of joint and several liability refers to rights and duties created by promises of same performance). In the case where multiple factors combined to produce the plaintiffs injury, there are different approaches in the tort and contract fields. In tort, when the torts of others were contributing factors, they may be held to be “joint tortfeasors,” each liable for the whole loss or harm. 11-55 CORBIN ON CONTRACTS § 999 (2004). “In the contract field, however, if the acts of others (whether wrongful or not) are contributing factors, those others are not thereby joined with the defendant as having committed the breach of contract.” Id.
We acknowledge that there are cases in which the courts have applied the one satisfaction rule and granted settlement credits or required an election of remedies where there are co-existing tort and con
*685
tract claims.
See Burke v. Union Pac. Res. Co.,
CTTI contracted with K & O directly. That contract specifically included a promise to deliver a defect-free budding. While other defendants also had contracts with K & O, none of those contracts made the promise which is the subject of this cause of action — that K & O receive a defect-free building. Therefore, even if the pre-trial settlements with other parties were to settle separate contract claims, those contracts did not promise the same performance as CTTI. Thus, there can be no joint and several liability between the various contracting parties. See RESTATEMENT (SECOND) OF CONTRACTS § 13 IN NT (1981). Garwood may have made a promise to provide architectural and supervisory services, but it did not make a promise to deliver a defect-free building. It therefore did not promise the same performance to K & O as CTTI, precluding joint and several liability. Moreover, the jury found Garwood did not breach its contract but was liable only for its own negligence. The settlement therefore covered damages caused by Garwood’s negligence, which by definition involves no promise whatsoever.
The supreme court’s decision in
Croton Life
is controlling in this case and requires that settlement credits be applied only if the parties were jointly and severally liable for the damages.
See Crown Life Ins. Co.,
*686 Having oveiTuled CTTI’s claim for settlement credits, we need not address the complaint raised in its fourth issue regarding attorneys’ fees.
CONCLUSION
Having found that the question of novation was properly submitted to the jury, that the jury’s verdict was not against the great weight and preponderance of the evidence, and that CTTI was not entitled to any settlement credits, we affirm the judgment of the district court.
Notes
. CTTI Priesmeyer, Inc. was known as Central Texas Tiltwall, Inc. at the time of the contract.
. In its fifth issue, CTTI contends in the alternative that it is entitled to a credit for only those settlements made pretrial.
. CTTI argues that once it put the settlements into the record, it satisfied its burden to prove its right to a settlement credit.
See First Title Co. of Waco v. Garrett,
