84 A. 322 | Conn. | 1912
The plaintiffs, copartners, doing business as contracting masons, in Norwich, entered into a contract with the defendant, a woolen manufacturer, by which they agreed to furnish all the mason work, supervise the carpenter work, and furnish all labor for scaffolding and cartage required to erect, build, and finish for the defendant a woolen mill in Baltic, in accordance with certain drawings and specifications which were made a part of the contract. And the defendant agreed to pay the plaintiff therefor $10,000, and to furnish all material, including brick, lime, cement, lumber, sand, granite, windows, window frames, doors and door frames, iron plates and posts, and all parts required for the completion of the building, and to furnish and pay for all necessary carpenters for the carpenter work.
Upon its face, the contract was not one to erect and complete a building, any more than was the contract in O'Brien v. Peck,
The plaintiffs did all the work and furnished all the materials required on their part, under the said contract, except that they neglected and refused to perform the labor and furnish the material required and necessary to construct the gravel roof referred to in the specifications.
The defendant was obliged to expend, and did expend, $804.01 in furnishing the labor and material necessary to construct said gravel roof. The defendant paid the plaintiffs the amount due under their contract, less the sum of $804.01, being the amount expended by them in constructing said gravel roof. *631
The plaintiffs sue to recover the balance due under their contract, viz. $804.01. The defendant pleads payment, and sets up, by way of set-off and counterclaim, the amount expended as aforesaid for said gravel roof, and claims that so much thereof as may be necessary be set off against any sum found to be due the plaintiffs. The contract did not refer to the roofing. The specifications provided that the entire roof should be covered with a gravel roof, 5-ply quality, and finished with specified material and in a specified way. And then followed this provision: "All this roof material to be furnished by the contractor."
The difference between the parties arises over their differing interpretation of the contract. The defendant claims that the plaintiffs were, under the contract, bound to perform all the work and furnish all the material required to construct the roof, while the plaintiffs claim that their part of the contract did not require them to perform any of the labor or furnish any of the material for this gravel roof.
By reference, and in terms, the specifications are made a part of the contract, so far forth as made applicable to its terms. Geary v. New Haven,
In Moreing v. Weber,
In Beattie v. McMullen,
In Hayes v. Wagner,
Baltimore O. R. Co. v. Stewart,
In White v. McLaren,
Let us construe this contract in the light of this principle. There is nothing in the contract concerning the construction of the gravel roof, or of anything to be done in connection with the gravel roof, except the obligation of the plaintiffs to do all the cartage; necessarily this included that required for the roofing. The plaintiffs' obligations under the contract are specific. They were confined to the mason work, the supervision of the carpenter work, and to the cartage. Theirs was strictly a working contract. The construction of a gravel roof, as the finding states, is a separate trade or business and not a part of the ordinary business of a brick and stone mason, or of a carpenter.
The labor required in constructing a gravel roof can by no possible construction be brought under these several heads comprising the plaintiffs' obligations.
On the other hand, the defendant bound himself to furnish all material. As no exception was made in the contract, these included the roofing materials.
It follows as a matter of law that since this provision of the specifications does not relate to any subject which the plaintiffs were required to perform, or furnish, it cannot be held to be a part of the contract.
Again, the roofing-clause of the specifications not being *634 found in the contract, and being inconsistent with the terms of the contract, is to be disregarded, upon the familiar principle that in case of conflict in terms the contract prevails over the specifications.
The reasons for this rule are well stated in Meyer v.Berlandi,
The obvious purpose of the specifications was to point out to the several contractors the details of their particular agreement to furnish material and labor, or material or labor; the kinds and quality of the material to be used, and the method and manner of performing the several kinds of work in building the mill.
There was, as we have pointed out, no possible obligation on these plaintiffs in reference to the roofing, except as to the cartage of the roofing materials. The item for cartage was at best one of comparative insignificance, for which a new trial should not be granted;Watson v. New Milford,
Several circumstances point to the correctness of our interpretation of this paragraph of the finding: (1) The defendant makes no contrary claim; (2) the court in its *635 exhaustive memorandum does not refer to such a claim; (3) the finding is otherwise entirely silent as to such claim; and (4) by necessary inference the finding denies it, — by its statement that it gave the plaintiffs notice to perform the work and furnish the materials required to construct said roof, and that upon failure to comply with said notice it procured and furnished the labor and material necessary to construct said gravel roof.
The finding further shows that the defendant expended in constructing said roof $804.01. The defendant had no right to withhold this sum, being the balance due on the contract, from the plaintiffs.
There is error, the judgment is set aside, and the cause remanded with direction to render judgment for the plaintiffs to recover $804.01, with interest from April 20th, 1908.
In this opinion the other judges concurred, except RALPH WHEELER, J., who dissented.