Gutmann v. CrouchGutmann v. Crouch
- Reporters:
- , , , , ,
- Before:
- Bradley, Follett Ch., Vann, Landon
BRADLEY, J.—The action was brought upon a bond made by the defendant to John R. Strauchen of date of September 29, 1886, containing the condition that if John Wadsworth & Son should “in all things hold to and strictly perform and keep all the conditions and obligations” of an agreement of date September 28, 1886, made between them and Strauchen, the obligation should be void; otherwise to re
The question remaining for consideration is whether or not there was breach of the condition of the bond, in that the Wadsworths were chargeable with damages for delay within the meaning of their contract in its performance. The contract between the plaintiff and Strauchen provided for performance of the work by the 1st of April, 1887, and further that the latter should allow and pay to the plaintiff “ten dollars damages for each day‘s delay after that time, if the same should arise from any act or default on the part” of such contractor. And further, that if there should occur a strike or other interference with labor, so that the contractor or his sub-contractors should not be able to continue and complete the work within that time without yielding to the demands of the strikers, the contract should be extended for such additional time as might be reasonably required by them to complete the work.
The further question has relation to delay, subsequent to that time, in the completion of the carpenter work. The Wadsworths ceased work upon the building about July 30, 1887. There were then some defects and omissions in the
Judgment affirmed, with costs.
All concur, except FOLLETT, Ch. J., VANN and LANDON, JJ., dissenting.