Case Information
*1 IN THE SUPREME COURT OF TEXAS
444444444444
N O . 12-0251
444444444444 C ROSSTEX E NERGY S ERVICES , L.P., P ETITIONER ,
V .
P RO P LUS , I NC ., R ESPONDENT
4444444444444444444444444444444444444444444444444444 O N P ETITION FOR R EVIEW FROM THE C OURT OF A PPEALS FOR THE F IRST D ISTRICT OF T EXAS Argued September 10, 2013
J USTICE G REEN delivered the opinion of the Court.
This interlocutory appeal arises out of property damage that resulted from an explosion at a natural gas compression station. The station owner, Crosstex Energy Services, L.P., sued the lead construction contractor, Pro Plus, Inc. The parties then entered a Rule 11 agreement to move expert designation dates beyond the limitations period. After limitations ran, Pro Plus moved to dismiss because Crosstex had not filed a certificate of merit with its original petition as required by section 150.002 of the Texas Civil Practice and Remedies Code. See ODE § 150.002. In a single order, the trial court denied the motion and granted Crosstex an extension to file the certificate. The court of appeals reversed the trial court’s ruling and remanded the case. We must decide: (1) whether the court of appeals had jurisdiction to hear Pro Plus’s interlocutory appeal of the extension order; (2) whether section 150.002’s “good cause” extension is available only when *2 a party filed suit within ten days of the end of the limitations period; (3) whether a defendant’s conduct can waive the plaintiff’s certificate of merit requirement; and (4) if waiver is possible, whether Pro Plus’s conduct constituted waiver. Because we answer yes to the first three questions but hold that Pro Plus did not waive Crosstex’s certificate of merit requirement, we affirm the judgment of the court of appeals.
I. Jurisdiction
This Court has limited jurisdiction over interlocutory appeals.
See
EX G OV ’ T ODE
§ 22.225(b)(3). We always have jurisdiction, however, to consider whether a court of appeals
appropriately exercised jurisdiction.
E.g.
,
Austin State Hosp. v. Graham
,
II. Facts and Procedural Background
Crosstex provides natural gas gathering and transmission services. Crosstex uses compression stations to increase the pressure of gas from the field and discharge the gas through pipelines to downstream stations. Crosstex hired Pro Plus, a registered professional engineering firm, as the principal contractor to construct the Godley Compression Station. On November 15, 2008, a control valve gasket at the station failed. The resulting gas leak, once ignited, created a massive fire causing $10 million in property damage. Crosstex filed suit on April 14, 2010, asserting causes of action for general and specific negligence, negligent misrepresentation, breach *3 of implied and express warranty, and breach of contract. Pro Plus’s answer generally denied each allegation, raised affirmative defenses, and included requests for disclosure under Texas Rule of Civil Procedure 194.2. Notably, Pro Plus’s answer did not raise the issue of a certificate of merit under Texas Civil Practice and Remedies Code section 150.002.
The trial court entered a docket control order setting the dates for the parties to designate experts pursuant to Rule 194.2. Pro Plus joined Crosstex’s motion for continuance, which the court granted just before the two-year statute of limitations ran on the negligence claims. The parties signed a Rule 11 agreement extending Crosstex’s expert designation deadline to April 8, 2011, beyond the limitations period. On December 2, 2010, after limitations had run, Pro Plus moved to dismiss Crosstex’s claims for failure to attach a certificate of merit to its original petition as required by section 150.002. T § 150.002(e). Crosstex responded by arguing that Pro Plus waived its right to dismissal through its conduct, and that this conduct was sufficient “good cause” for an extension under section 150.002(c). § 150.002(c), (e). The trial court denied the motion to dismiss and granted an extension in the same order.
Pro Plus appealed the interlocutory order. The court of appeals held: (1) it had jurisdiction
to hear the interlocutory appeal; (2) the trial court abused its discretion by granting the extension
without good cause; and (3) Pro Plus did not waive its right to dismissal.
III. Court of Appeals’ Interlocutory Appeal Jurisdiction
The certificate of merit statute applies to actions for damages arising out of “the provision of professional services by a licensed or registered professional,” such as Pro Plus. See EX . C IV . P RAC . & R EM . C § 150.002(a). A plaintiff “shall” file an affidavit of a qualified third party in the same profession; the affidavit must substantiate the plaintiff’s claim on each theory of recovery. See id. § 150.002(a), (b). Failure to file this affidavit (hereafter “certificate of merit”) results in dismissal. § 150.002(e). This dismissal may be with or without prejudice. See id.
The threshold question is the court of appeals’ jurisdiction to hear this interlocutory appeal.
As a general rule, appellate courts may consider appeals from interlocutory orders only when such
power is conferred expressly by statute.
See Tex. A & M Univ. Sys. v. Koseoglu
,
This is a question of first impression. As Crosstex points out, however, the expert report requirements in the Medical Liability Act, T §§ 74.001–.507, provide a useful, if imperfect, analogue. The Act requires the plaintiff, within 120 days of suit, to serve expert reports identifying the basis for liability against each health care provider. Id. § 74.351 (a), (r)(6). Failure to serve the report mandates dismissal, id. § 74.351(b)(2), but if a deficient report is timely served, a trial court may grant a thirty-day extension. Id. § 74.351(c). Section 51.014(a)(9) of the Civil Practice and Remedies Code expressly authorizes interlocutory appeals from dismissals pursuant to section 74.351(b), but also expressly bars interlocutory appeals from a grant of extension of time under section 74.351(c). § 51.014(a)(9).
To summarize, both the certificate of merit statute and the Medical Liability Act allow
interlocutory appeals of dismissals for failure to meet a threshold filing requirement. Only under
the Medical Liability Act, however, has the Legislature expressly forbidden interlocutory appeals
of extensions of time to meet the filing requirement.
See id.
The certificate of merit statute does not
address the appealability of extensions of time; therefore, such interlocutory appeals, presumably,
*6
are not permissible as the statute does not expressly confer authority for the courts of appeals to
consider them.
See Koseoglu
,
In
Ogletree
, the defendant timely objected to the sufficiency of an expert report and filed a
motion to dismiss.
We clarified the scope of
Ogletree
in
Badiga v. Lopez
,
Extending that logic to the certificate of merit context, we note that Crosstex is in a position
similar to the plaintiff in
Badiga
. In each, failure to provide timely, mandatory documentation yields
dismissal.
Compare
§ 74.351(b)(2),
with id.
§ 150.002(e). While
both statutes contain a mechanism for extension,
compare id.
§ 74.351(c),
with id.
§ 150.002(c), the
grant of an extension is immaterial in both cases where it cannot bear upon the correctness of the
dismissal ruling.
See Badiga
,
The court of appeals in this case reviewed whether the trial court erred in denying Pro Plus’s
motion to dismiss for lack of a certificate of merit. Crosstex’s failure to file a certificate left it
without a statutory basis for extension.
[2]
Thus, the court of appeals could evaluate the propriety of
the trial court’s ruling on the motion to dismiss without entanglement in the appeal of the granted
extension.
Cf. Badiga
,
IV. “Good Cause” Extension for Filing a Certificate of Merit
We must now determine the contours of section 150.002(c)’s “good cause” extension to the
certificate of merit filing deadline and whether it applies to Crosstex’s failure to file. We review
statutory construction de novo.
City of Rockwall v. Hughes
,
Subsection (c) states:
The contemporaneous filing requirement of Subsection (a) shall not apply to any case in which the period of limitation will expire within 10 days of the date of filing and, because of such time constraints, the plaintiff has alleged that an affidavit of a third-party licensed . . . professional engineer . . . could not be prepared. In such cases, the plaintiff shall have 30 days after the filing of the complaint to supplement the pleadings with the affidavit. The trial court may, on motion, after hearing and for good cause, extend such time as it shall determine justice requires. ODE 150.002(c). The parties dispute the meaning of the final sentence.
Crosstex contends that the trial court may extend the time regardless of when the plaintiff files the
lawsuit. Pro Plus argues that the good cause extension is constrained by the full language of
subsection (c) and, thus, may apply
only
if the plaintiff files the lawsuit during the final ten days of
the limitations period. Indeed, the courts of appeals have reached contradictory results.
Compare
*9
Apex Geoscience, Inc. v. Arden Texarkana, LLC
, 370 S.W.3d 14, 19–21 & n.5 (Tex.
App.—Texarkana 2012, pet. granted, judgm’t vacated w.r.m.) (constraining the good cause
extension to filings within ten days of the end of limitations),
with WCM Grp., Inc. v. Brown
, 305
S.W.3d 222, 230–31 (Tex. App.—Corpus Christi 2009, pet. dism’d) (holding that the good cause
exception may operate for suits filed outside the ten-day window). We recognize that the lack of
unequivocal language renders the statute capable of multiple interpretations. Thus, we apply our
rules of construction to discern legislative intent.
See R.R. Comm’n of Tex. v. Tex. Citizens for a
Safe Future & Clean Water
,
Read in isolation, the final sentence of subsection (c) suggests the availability of a good
cause extension untethered from the remainder of the text. But that is not the way statutes are
written or read.
See TGS–NOPEC Geophysical Co. v. Combs
,
The untenable result of Crosstex’s interpretation further solidifies this conclusion. Crosstex urges a broad exception, yet a narrow exception to the filing requirement aligns more closely with the scheme created by subsection (c). A plaintiff must allege that its near-limitations filing prevented the preparation of a certificate of merit. See § 150.002(c). If Crosstex’s broad good cause interpretation prevailed, a plaintiff could bring forth good cause claims independently of when it filed the suit and without the necessity of alleging the basis for delay. Crosstex’s approach would thus produce two exceptions: (1) a narrow exception limited to a tight ten-day window and requiring specific allegations, yielding a thirty-day extension; and (2) a broad exception with no limitations other than a court’s determination of good cause, allowing extensions “as justice requires.” In practical application, a near-limitations filing would always meet the good cause standard. Therefore, the good cause exception would swallow the narrow near- limitations exception and, quite likely, the contemporaneous filing rule. We cannot adopt an interpretation that would render a statutory provision meaningless. See Columbia Med. Ctr. , 271 S.W.3d at 256.
We hold that the “good cause” exception in subsection (c) does not stand alone, but rather is contingent upon a plaintiff: (1) filing within ten days of the expiration of the limitations period; and (2) alleging that such time constraints prevented the preparation of an affidavit. A plaintiff *11 satisfying these requirements “shall” receive an extension of thirty days; upon motion, a trial court may, for good cause, extend this thirty-day period as justice requires. A plaintiff who files suit outside the ten-day window, as Crosstex did, cannot claim protection of the good cause exception.
V. Waiver
Crosstex next argues that Pro Plus waived its right to move for dismissal. This presents two questions: (1) can a defendant waive the right to obtain dismissal under section 150.002(e); and (2) if so, did Pro Plus waive this right? We address each question in turn.
A. Waiver of Right to Obtain Dismissal
We have defined waiver as “an intentional relinquishment of a known right or intentional
conduct inconsistent with claiming that right.”
Sun Exploration & Prod. Co. v. Benton
, 728 S.W.2d
35, 37 (Tex. 1987). Parties may not waive jurisdictional statutory duties.
See Dubai Petrol. Co. v.
Kazi
, 12 S.W.3d 71, 76–77 (Tex. 2000). But mandatory statutory duties are not necessarily
jurisdictional.
Helena Chem. Co. v. Wilkins
,
Section 150.002(a) states that a plaintiff “shall” file the certificate of merit with its
complaint. T EX . C IV . P RAC . & R EM . C ODE § 150.002(a). In determining whether the Legislature
intended the certificate of merit to be mandatory, “we consider the plain meaning of the words used,
as well as the entire act, its nature and object, and the consequences that would follow from each
construction.”
Helena Chem.,
Statutory interpretation principles guide our evaluation of whether section 150.002’s
certificate of merit requirement is jurisdictional.
See White
,
We address the first two factors together. The text of the statute itself does not indicate that
failure to file a certificate of merit is jurisdictional. Granted, subsection (e) mandates dismissal as
a remedy for non-compliance. T § 150.002(e). But our aversion to
*13
classifying statutory requirements as jurisdictional prevents such classification absent a clear
indication from the Legislature of jurisdictional intent.
See White
,
Because the Legislature did not declare the statute’s purpose, the third factor provides little assistance. Yet the fourth factor—consideration of the implications of alternative interpretations—strongly suggests the requirement is non-jurisdictional. If we held the certificate of merit requirement jurisdictional, a plaintiff successfully pursuing a claim to final judgment, yet omitting a certificate of merit, would find the judgment always vulnerable to collateral attack. The defendant could have the judgment set aside at any time, either returning the parties to square one or completely barring the plaintiff’s claim if limitations had run. The statute acts as a procedural bar for claims without a certificate of merit. It does not follow that because the Legislature created this procedural bar, it also wanted to create a basis for attacking the judgment in perpetuity. We must conclude that the Legislature did not intend section 150.002(e) as a jurisdictional requirement.
Returning to the medical liability arena, we find further support for this conclusion. In
Jernigan v. Langley
,
Furthermore, every court of appeals that has squarely addressed an argument for waiver of
section 150.002(e) dismissal has reached a result consistent with classifying the requirement as non-
jurisdictional.
[4]
One court of appeals explicitly recognized waiver,
see Murphy,
374 S.W.3d at
*15
635–36, and three other courts of appeals have addressed the waiver argument without the
jurisdictional analysis, as we did in
Jernigan
.
See Ustanik
,
For the reasons stated, we hold that section 150.002 imposes a mandatory, but non- jurisdictional, filing requirement. Thus, we hold that a defendant may waive its right to seek dismissal under the statute.
B. Pro Plus’s Conduct
Waiver is primarily a function of intent.
Jernigan
,
1. Invocation of the Judicial Process
We have held that, in some circumstances, substantial invocation of the litigation process
may amount to waiver.
See Perry Homes v. Cull
,
The Texas Rules of Civil Procedure encourage liberal discovery practices.
See Jorndan v.
Court of Appeals for Fourth Supreme Judicial Dist.
, 701 S.W.2d 644, 647 (Tex. 1985). The
discovery process streamlines the insatiable quest for information as the parties try to wrap their
minds around the case.
See State v. Lowry
,
Filing an answer is similarly inconsequential in the analysis.
See, e.g.
,
Palladian Bldg. Co.
v. Nortex Found. Designs, Inc.
,
Pro Plus joined a motion for continuance, engaged in discovery under a docket control order,
and entered into a Rule 11 agreement. Crosstex construes this flurry of activity near the end of the
limitations period as deliberate misrepresentation. Yet no direct evidence of such manipulation
exists. As Pro Plus noted at oral argument, the Rule 11 agreement allowed Pro Plus ample time to
prepare its expert reports in the event its motion to dismiss was denied (which is precisely what
happened). Though Crosstex has offered some support for its waiver claim, Pro Plus’s conduct
falls far short of “clearly demonstrat[ing]” an intent to waive the right to dismiss under subsection
150.002(e).
See Jernigan
,
2. Failure to Object
Crosstex next argues that Texas Rule of Civil Procedure 90 required Pro Plus to file a special
exception to the absence of a certificate of merit. Rule 90 deems any defect, omission, or fault in
a pleading waived unless specifically pointed out by exception. T R. P. 90. However,
failure to file a certificate of merit with the original petition cannot be cured by amendment.
Landreth v. Las Brisas Council of Co-Owners, Inc.
,
VI. Extension by Agreement
Finally, we address Crosstex’s argument that the Rule 11 agreement and the docket control order operated to extend the deadline for filing a certificate of merit. Pro Plus’s answer included requests for disclosure under Rule 194.2, which includes expert information. The docket control order specified certain dates for designating those experts. Crosstex contends that the docket control order on Rule 194.2 experts was broad enough to encompass the section 150.002 certificate of merit. Thus, the argument goes, when the parties’ Rule 11 agreement moved the date for Rule 194.2 disclosures to April 2011, this delayed the section 150.002 certificate of merit requirement.
In
Spectrum Healthcare Resources, Inc. v. McDaniel,
VII. Conclusion
We hold that the court of appeals did not err in asserting jurisdiction over this interlocutory appeal. As to the merits of the appeal, we hold that: (1) Crosstex did not file suit within ten days of the running of limitations and thus cannot claim protection from the good cause extension in section 150.002(c); (2) a defendant may, through its conduct, waive the right to seek dismissal under section 150.002(e); and (3) Pro Plus’s conduct did not constitute waiver. We affirm the judgment of the court of appeals.
_______________________________________ Paul W. Green
Justice
OPINION DELIVERED: March 28, 2014
Notes
[1] The language of the order is as follows: On the below entered date came on to be heard Defendant Pro Plus’[s] Motion to Dismiss and Plaintiff Crosstex Energy Services, L.P.’s Motion to Extend Time, and the Court, after reviewing the Motions, taking judicial notice of the other pleadings on file, and considering the argument of counsel, is of the opinion Defendant’s Motion to Dismiss should be denied. For good cause shown, and in the interest of justice, the Court therefore: ORDERS, ADJUDGES and DECREES that Plaintiff Crosstex Energy Services, L.P. file an expert report in compliance with the Certificate of Merit requirements contained in CPRC § 15[0].002 on or before the agreed deadline between the parties for Plaintiff to designate experts, currently April 8, 2011, which agreement was signed by the parties and thereafter filed with the court on November 29, 2010 pursuant to Rule 11 of the Texas Rules of Civil Procedure.
[2] As discussed in part IV of this opinion, the good cause extension is not available to a plaintiff who does not file a certificate of merit. Infra at .
[3] We contrast our non-jurisdictional finding here with actions under the Whistleblower Act. Under the Act, section 554.0035 of the Texas Government Code waives sovereign immunity for violations of that chapter. T EX G OV ’ T C § 554.0035. Section 554.002 provides the standard for a violation. Id. § 554.002. In State v. Lueck , 290 S.W.3d 876 (Tex. 2009), we held that the facts necessary to allege a violation under section 554.002 were jurisdictional because they were indispensable to the jurisdictional question of the waiver of sovereign immunity in section 554.0035. at 881–82. No parallel concern exists here.
[4]
Murphy v. Gutierrez
,
