This is an appeal of a decision by the Pulaski County Circuit Court awarding the appellee damages in the amount of $16,093.39, $12,095.00 of which was awarded by the jury for services rendered in connection with “extra ditching” and $3,998.39 of which represented contract costs awarded by the judge, plus prejudgmerit interest on that portion of the judgment representing contract costs. The appellant contends the court erred in (1) failing to direct a verdict in its favor, as the appellee failed to show (a) any consideration for the alleged promise to pay extra for the ditching, (b) any waiver of the contract provisions requiring written approval of extras and determination of the quantity of work by the engineers, Garver & Garver, Inc., or (c) sufficient evidence to allow the jury to determine damages without resorting to sheer speculation; (2) failing to instruct the jury that they must find a definite agreement to pay for the alleged extra work; and (3) giving an improper jury instruction on damages. The appellee contends on cross-appeal that the court erred in failing to award it prejudgment interest on the portion of damages relating to the costs of the “extra ditching.” The portion of the judgment representing the contract costs has not been appealed. Because we find merit in the appellant’s contention that the trial court should have directed a verdict in its favor, on the basis that the appellee failed to show any consideration for the alleged agreement to pay him extra for the ditching, we need not reach the other points raised in the appeal and cross-appeal,
The appellant was the general contractor on a project to build an extension of a railroad for the Little Rock Port Authority. The appellee entered into a subcontract agreement with the appellant in January 1982 to do the excavation and dirt work on the project, which provided that the appellee would perform the work according to the plans and specifications provided by Garver & Garver, Inc. The problem in this case arose when the water would not drain out of the ditches the appellee constructed because the culverts through which they were to drain were clogged off of the jobsite. This caused the ditches to collapse, requiring the appellee to repeatedly have to redig the ditches. Larry Moyer, owner of the appellee, testified that, because of this problem, which began shortly after he started working, he told the appellant’s representative, Alan McElhaney, that he would not continue to work without extra pay for redigging the ditches. He stated that McElhaney agreed to this.
The Port Authority’s Invitation to Bid required each bidder to make an inspection of the jobsite, stating, Moyer testified that the contract required him to make this inspection, that he did do so, and that there was nothing stopping him from inspecting the culverts. He also admitted that he was required under the contract’s plans and specification to build the drainage ditches to meet the specifications and be up to grade at the time the project closed. Moyer acknowledged that that was precisely what he accomplished.
Each Bidder should visit the site of the proposed work and fully acquaint himself with the existing conditions there relating to construction and labor, and should fully inform himself as to the facilities involved, and the difficulties and restrictions attending the performance of the Contract. . . .The Contractor by the execution of the Contract shall not be relieved of any obligation under it due to his failure to receive or examine any form or legal instrument or to visit the site and acquaint himself with the conditions there existing and the Owner will be justified in rejecting any claim based on facts regarding which he should have been on notice as a result thereof.
Under Arkansas law, there must be additional consideration when the parties to a contract enter into an additional contract. Buchanan v. Thomas,
If no benefit is received by the obligee except what he was entitled to under the original contract, and the other party to the contract parts with nothing except what he was already bound for, there is no consideration for the additional contract concerning the subject matter of the original one. Thompson v. Robinson,34 Ark. 44 ; 1 Brandt on Suretyship and Guaranty, §387; 1 Page on Contracts, §312.
“Mere performance of an existing contract or a part thereof,” says Mr. Page in the section cited above, “is of itself no consideration for a new promise to the party performing. * * * If, without legal justification, one party to a contract breaks it, or threatens to break it, and to induce performance on his part the adversary party promises to pay more than was provided for by the original contract, there is in principle no consideration for such promise, as the party who threatens to break the contract does, when he finally performs it, no more than he was bound in law to do.”
Here, the contract admittedly required the appellee to dig the ditches so that he met the specifications at the time the project was approved, and it is undisputed that that is what the appellee did. Where the work performed is covered under the terms of the contract, as here, there can be no recovery for it as extra work. Baton Rouge Contracting Co. v. West Hatchie Drainage District of Tippah County,
There has been no appeal of the award of $3,998.39 for costs under the contract. While a single, inseparable verdict may not be divided, we have the power to divide two causes of action in a circuit court judgment, so long as we are not dividing a single jury verdict. Westinghouse Credit Corp. v. First National Bank of Green Forest,
Affirmed as modified.
