51 Fed. Cl. 654 | Fed. Cl. | 2002
ORDER
Before the court is Plaintiffs Motion for Reconsideration of the Court’s Order Filed July 12, 2001 (Mot.Reconsid.). Plaintiff argues that the court’s Opinion and Order of July 12, 2001 (Opinion), see 49 Fed.Cl. 776 (2001), was contrary to authority. The court addresses plaintiffs contentions, corrects two erroneous statements in its Opinion to which plaintiff has drawn the court’s attention, and otherwise denies plaintiffs motion.
Plaintiff argues that Envtl. Prot. Info. Ctr. v. Simpson Timber Co., 255 F.3d 1073 (9th Cir.2001),
The court also distinguished Simpson Timber on the ground that this case does not involve the “exercise of control through a permit.” Croman, 49 Fed.Cl. at 784 n. 8. But plaintiff correctly points out, see Mot. Reconsid. at 5, that the same considerations apply to an agency’s decision to grant a permit as to other agency decisions regarding the protection of endangered or threatened species. See 16 U.S.C. § 1536(a)(1) (2001) (requiring consultation to ensure that “any action authorized, funded, or carried out” by an agency does not jeopardize the continued existence of endangered or threatened species); 50 C.F.R. § 402.02 (2002) (defining “action” as including “actions intended to conserve listed species or their habitat” and “the granting of ... permits”). The court’s statements in its Opinion that Simpson Timber was distinguishable because it involved the issuance of a permit and the reinitiation of consultation were therefore incorrect and are hereby corrected. Nevertheless, for the following reasons, the court does not believe that Simpson Timber, even if it were controlling authority for this court, warrants a different result than the court reached in its Opinion.
Plaintiff argues that Simpson Timber illustrates that an agency may only reinitiate consultation regarding the impact of a contract on a threatened or endangered species when the agency has retained specific discretionary authority to protect that species. Mot. Reconsid. at 6-10. Plaintiff contends, see Mot. Reconsid. at 5, that Simpson Timber also illustrates that the court improperly relied on Natural Res. Def. Council v. Houston, 146 F.3d 1118 (9th Cir.1998) in holding, in its Opinion and Order of October 1, 1999, that the suspension of the contract was authorized. See Croman Corp. v. United States, 44 Fed.Cl. 796, 806-07 (1999). The court does not believe that Simpson Timber stands for those propositions.
Simpson Timber involved an incidental take permit issued to a timber company pursuant to 16 U.S.C. § 1539(a)(1). Simpson Timber, 255 F.3d at 1076-77. The permit required that the defendant timber company submit harvesting plans designed to “[m]odify silvicultural systems as appropriate to ensure compatibility with the habitat requirements of other species found within Simpson’s ownership that are considered sensitive by state and federal regulatory agencies.” Id. at 1077. The plaintiff, a nonprofit organization, sued for an injunction against timber harvesting after two species were added to the threatened species list, arguing that Fish and Wildlife was required to reinitiate consultation to address the impact of the permit on those species. Id. at 1074, 1079. The plaintiff argued that this provision required Fish and Wildlife to reinitiate consultation if the agency found that the permit could affect species subsequently listed as threatened. Id. at 1080-81. The court disagreed, interpreting the language of the permit as providing protection only for those species that were listed as threatened at the time the permit was issued, not for those species that were subsequently listed. Id. at 1081. In Simpson Timber, therefore, the permit contained a specific grant of discretionary authority. The Ninth Circuit concluded that the specific grant of discretionary authority was intended to protect species other than those that were the subject of the suit.
Here, however, the discretionary authority reserved by defendant in the contract neither contemplates the protection of specific endangered species nor, expressly or by implication, excludes other species from its scope. Rather, as the court discussed in its Opinion and Order of October 1, 1999, the contract reserves to the Forest Service discretionary authority in the adjustment of
Within 60 days of extension of contract, Purchaser shall furnish Forest Service a written general plan of operation which shall be in addition to the annual operating schedule required under B6.31. The plan shall set forth planned periods for and methods of road construction, timber harvesting, and completion of slash disposal, erosion control measures and other contractual requirements to complete sale. Forest Service written approval of the plan of operation is prerequisite to commencement of Purchaser’s Operations. Purchaser may revise this plan of operations when necessitated by weather, markets or other unpredictable circumstances, subject to the written approval of Forest Service. In the event of delays beyond the control of Purchaser which qualify for Contract Term Adjustment, the plan of operations shall be mutually adjusted as necessary to accommodate the adjusted contract period.
Appendix to Plaintiffs Reply in Support of its Motion for Reconsideration (Pl.’s Reply App.) at 664. This provision makes clear that the Forest Service must approve any changes to plaintiffs plan of operations caused by outside forces beyond the control of plaintiff and the Forest Service. The listing of the marbled murrelet as a threatened species (with the accompanying direction that the Forest Service “review and assess the potential impacts of [timber sales in Washington, Oregon and California] on the murrelet,” see Endangered and Threatened Wildlife and Plants, 57 Fed.Reg. 45,328, 45,337 (Oct. 1,1992)) (codified at 50 C.F.R. Part 17), was an event beyond the control of plaintiff or the Forest Service that disrupted plaintiffs contract performance and necessitated a change in plaintiffs plan of operations. As the court found in its October 1,1999 Opinion and Order, see Croman, 44 Fed.Cl. at 807, the listing was an “act of Government” that entitled plaintiff to a Contract Term Adjustment. Because the Forest Service had discretionary authority in adjusting the contract’s schedule in the event of an act of Government, see Pl.’s Reply App. at 664 (“In the event of delays beyond the control of Purchaser which qualify for Contract Term Adjustment, the plan of operations shall be mutually adjusted as necessary to accommodate the adjusted contract period”) (emphasis added), it retained discretionary authority over contract operations for purposes of the Endangered Species Act (ESA), 16 U.S.C. §§ 1531-1544 (1994).
To be sure, it does not appear that the Forest Service consulted plaintiff before suspending operations on the contract, and in that sense the adjustment to plaintiffs plan of operations caused by the initial suspension was not “mutual.”
Plaintiff argues that the purpose of a plan of operations is merely to ensure timely completion of the contract. Plaintiffs Reply in Support of its Motion for Reconsideration (Pl. Reconsid. Reply) at 2-7. Even assuming arguendo that plaintiff is correct, that fact does not signify that the Forest Service may not consider the impact of the plan on endangered or threatened species (or the requirement of complying with the ESA) when it exercises its discretion in adjusting the plan of operations. If the Forest Service found it necessary to adjust the contract schedule because of a storm, it would presumably require that operations resume only after the storm has passed. Likewise, the disruptive effect of the listing of the marbled murrelet as a threatened species, and the accompanying requirement of consultation with Fish and Wildlife, required the Forest Service to delay contract operations until after concerns about the contract’s effect on the marbled murrelet were addressed. The initial purpose of the plan of operations does not govern the reasons that may be cited for adjusting that plan.
Plaintiff also argues that the parties’ failure to add another clause to the contract specifically providing for the Forest Service’s authority to protect endangered species indicates that the Forest Service had no such authority under this contract. Pl. Reconsid. Reply at 8-9. The authority to suspend contract operations in the event of an “act of Government” under the contract is not set out with specific examples. That another clause could have specified the Forest Service’s authority to suspend contract operations in the exact circumstance of this or some other particular and limited case, however, does not mean that the Forest Service lacked such authority under the existing terms of the contract. Absent an ambiguity in a contract, the court looks only to the plain meaning of the text of the contract, not to extrinsic evidence. City of Tacoma v. United States, 31 F.3d 1130, 1134 (Fed.Cir.1994). The provisions discussed above do not deal separately with the protection of endangered species in a way that makes their implications for such protection unmistakable, but neither are they ambiguous. The court therefore finds that resort to extrinsic evidence to determine the contract’s meaning is unwarranted in this case.
Plaintiff also argues that Simpson Timber forecloses agency action on a contract pursuant to § 1536(a) of the ESA unless the contract specifically reserves to the agency the right to protect endangered species. The court believes that plaintiff has misread the holding in Simpson Timber. The plaintiff there argued that “existing contracts and permits that are in no way related to the ESA or do not provide mechanisms to protect threatened and endangered species may require alteration if necessary to comply with the ESA.” 255 F.3d at 1082 (citations omitted). The plaintiff in Simpson Timber cited Natural Res. Def. Council v. Houston, 146 F.3d 1118 (9th Cir.1998), in support of that argument. The Ninth Circuit found that Houston did not support the Simpson Timber plaintiffs argument, because the agency in Houston did in fact have discretionary control over the contract at issue. 255 F.3d at 1082. The Ninth Circuit in Simpson Tim
For the foregoing reasons, plaintiffs Motion for Reconsideration is GRANTED with respect to the court’s statements that Simpson Timber is distinguishable because this ease does not involve the reinitiation of consultation or the exercise of control through a permit, and DENIED in all other respects.
IT IS SO ORDERED.
. Since the filing of plaintiff’s motion, this decision has been reported as Envtl. Prot. Info. Ctr. v. Simpson Timber Co., 255 F.3d 1073 (9th Cir.2001). Accordingly, the court’s citations will be to the Federal Reporter.
. To the extent that the Forest Service's suspension of the contract without prior consultation of plaintiff may be considered a breach of the contract's requirement of a "mutual" adjustment in the event of a delay caused by "acts of Govemment," that breach of contract claim was not raised before the contracting officer, see Defendant’s Appendix at 554-59, and is therefore not before the court.
. Plaintiff also argues that paragraph C6.311 "only gives the Forest Service the right to deny approval if the purchaser’s plans were inconsistent with the existing terms of the contract.” Mot. Reconsid. at 9 n.7. The court finds no support for that reading in the text of the provision.