34 Wash. 420 | Wash. | 1904
This action was brought in the lower court by the plaintiff, a resident and taxpayer, to restrain the payment of certain school warrants, issued by the officers of school district No. 24, in Snohomish county, in payment of the contract price of a school building for said district, constructed by defendant Grant. TJpon a trial the court entered a decree, restraining payment of a part of the warrants and refusing to restrain payment of the balance, and also ordered the school district to pay $500 as an attorney’s fee to plaintiff’s attorneys. The plaintiff appeals from that part of the decree refusing to restrain the payment of all the warrants. Defendant Grant appeals from that part of the decree restraining the payment of warrants. The school district appeals from that part awarding an attorney’s fee in favor of the plaintiff.
The amended complaint contains four causes of action, one of which was abandoned by stipulation. The gist of the other three is, (1) failure of the contractor to construct the building in accordance with the plans and specifications; (2) that the contract was void because of failure of the school board to advertise for bids for the erection of the building; and (3) fraud and collusion in mating the contract. The answer of the defendant Grant, after denying the material.allegations of the complaint, alleges substantial compliance with the contract, but admits certain minor departures and omissions from the plans and speci
Upon tbe facts, as they appear in tbe record, there is substantially no dispute, except as to tbe reasonable value of tbe building which was erected. They are briefly as follows: In February, 1902, the school district was reorganized under tbe law providing for a district in cities containing over 10,000 inhabitants. At tbat time tbe school buildings in tbe district were inadequate to accommodate tbe school children, and there- was great necessity for another school building. Tbe city board of education determined to erect an eight-room school building on tbe site of tbe Jefferson school grounds, to be known as tbe “Jefferson Annex.” Architects were thereupon employed to prepare plans and specifications for such building. A building was designed, consisting of a two-story wooden structure, resting on a basement of masonry. On account of tbe site being a hillside, tbe basement walls were not of tbe same dimensions on all sides. Tbe superstructure contained a number of ornamental wooden columns at tbe entrances. Tbe specifications provided for a complete eight-room building, provided with ventilating and beating apparatus and a basement.
The board accordingly purchased another site on a level place, and directed the architects to amend the specifications so as to eliminate the ornamental columns and make the basement conform to the new site. These changes, and others necessitated by the location, were made in the plans and specifications. The size of the building Was also slightly reduced without the knowledge of the board. The architects thereupon gave the board an estimate of $6,230 as the amount which should be deducted on account of these changes. Thereafter, on March 29, 1902, the board adopted a resolution authorizing the erection of the building on the new site, “in accordance with the changes and alterations, as suggested by the board and architects, of the original plans;” and the name of the new. building-was changed from “Jefferson Annex” to “Jackson School.”
Uo further advertisement for bids-was published,-but the board deducted $6,230, as estimated by the .architect to be the difference in cost between the original and the modified plans and specifications, from .the bid of Mr. Grant, and authorized a contract with him-for the erection of the building for $26,670. This contract was-entered into on April 1, 1902. It is the usual builder’s-contract, providing for deductions and extras and for the payment
Work was begun on the building on May 1, 1902. During the progress of the work, the district decided to make a change in the heating plant, and it was accordingly made, and a more expensive heating plant was installed, and an allowance of $1,500 was made to the contractor on account thereof. Extra Work on the foundation was. ordered and also allowed, to the amount of $892.50. Numerous other minor changes were made by the contractor for his benefit, without the knowledge or authority of the board, which changes are estimated to amount to about $1,200. In September, 1902, when this action was begun, the building was substantially completed, and was shortly thereafter put to use by the district, and was occupied as a school building during the trial of the case. Warrants amounting to' $27,092.50 had been issued by the board, and delivered to the contractor, and disposed of by him before the action was begun. The holders of these warrants were not made parties to the action. Defendant- Grant held none of the warrants. The building erected is a good, substantial, modem school building, well adapted to the purposes intended, and well supplied with sanitary, lighting, and heating facilities, but lighter in structure, somewhat smaller in size, and- cheaper in many details of construction, than the building first advertised for. '
In addition to the facts above stated, the trial -court found that the defendant Grant and the architects, who were the agents of the board, collusively and fraudulently changed the plans and specifications, and substituted in
It is first argued by appellant Criswell that the contract which was entered into by defendant and the school board was ultra vires and void, because it was let without advertising for bids. Many eases are cited to the effect that, where a municipal corporation is required by its charter to let contracts in a certain specified way, it is beyond the powter of such a corporation to let contracts in any other way; that obligations entered into in violation of law are void, and no rights or liabilities are incurred thereunder. The cases cited are all based upon statutes which require the officers of the corporation to advertise for bids, and to let the contract to the lowest bidder, and there was no discretion left to the officers, except perhaps to determine the lowest bid. Among many cases cited are: Arnott v. Spokane, 6 Wash. 442, 33 Pac. 1063; Moran v. Thompson, 20 Wash. 525, 56 Pac. 29; State v. Pullman, 23 Wash. 583, 63 Pac. 265; 83 Am, St. 836. There can be no doubt that the principles announced in these cases are the settled law, not only of this state, but of all the states where similar questions have arisen. If this ease falls within the principles of those cases, the rules therein announced must govern.
The power of the board of education to build a school
“In all districts contemplated -bv this chapter, when, in the opinion of the board, the cost of any lot of furniture, stationery, apparatus, fuel, building or improvements, or repairs to the same, will equal or exceed the sum of $200, it shall be the duly of the board to give due notice by publication in at least one daily newspaper published within said city, and if there be no daily, then in one or more weekly papers in three regular consecutive issues, of the intention to receive bids for such lots of furniture, stationery, fuel and other supplies, or for said improvements and repairs. The board shall determine the specifications for such bids, which shall be public.” Section 2366, Bal. Code.
While this statute does not require the contract for such supplies, buildings, or repairs to be let to the lowest bidder, yet it is the evident purpose to require a notice and an opportunity for competitive bidding, so that the contract may be let to the best advantage, of the municipality. The power of the board to contract is limited, by the section quoted, only to the extent of requiring notice of intention to receive Toids upon specifications which are open to bidders. ISTo other restrictions are made. The terms and conditions of the contract are left entirely to the discretion of the board. Mayo v. County Com’rs, 141 Mass. 74, 6 N. E. 757.
It was not the purpose of this section to tie the hands of school boards, so that every detail in plans and specifications for school buildings shall be irrevocably fixed, and no contract made or building constructed except exactly as specified. The evident purpose was to benefit the school district by inviting competitive bidding upon con
It is no doubt true that one bidder may not change his bid, after knowledge of other bids, so as to make it lower than another. This would be a fraud upon other bidders, And the board of education may not call for bids upon a given plan, and, after bids have been made thereon, so change the plan as to make an entirely different building, and require bidders to accept a contract upon the plan as changed. Ror may the board enter into private negotiations With one of the bidders upon a different plan; this would avoid the statute. But where the plan remains substantially the same, and the parties act in good faith,
The next two points presented by appellant Criswell are to the effect that, the contract being ultra vires and void, the contractor Grant cannot recover upon the contract, or upon the quantum meruit, and the fact that the district occupies the building, and has accepted the benefits, creates no liability. This is no doubt correct where the contract is ultra vires. But since we have already concluded that the contract was not beyond the power of the board, it will not be necessary to notice these points.
It is next contended that the contract was void for fraud. It is not claimed, however, that the school board was guilty of any fraud, or that the members thereof were actuated by other than the best of faith, and solely with a view to the best interests of the district. But it is claimed that defendant Grant and the architects fraudulently changed the plans and specifications, so as to make a dishonest profit. We have carefully examined the whole record in the case, and particularly that bearing upon this question, and are satisfied that there is no sufficient evidence upon which to base a conclusion of fraud, on the part of either the architects or the contractor, prior to
However, this point becomes immaterial, because the court concluded, on account of such fraud, that the district was liable only for the reasonable value of the building, which was found to be $20,535.56. In this conclusion we think the court Was right, not because of the fraud, but because the contractor, after the contract was entered into, made many material changes and omissions in the work without authority of the board, and against the protests of the architect; and on this account, if Grant were suing, he could not recover upon the contract. But where the contract is not unlawful, and the district has accepted and is using the building, which is in all respects suitable for its purposes, common honesty requires that it should pay the reasonable value thereof. 6 Cyc., 111, and cases cited; Kagy v. Independent Dist., 117 Iowa 694, 89 N. W. 972; Chapman v. Douglas County 107 U. S. 348, 2 Sup. Ct. 62, 27 L. Ed. 378. Appellant
Appellant Grant maintains that there is shown to be a defect of parties, and that the cause must therefore be reversed. This contention is based upon the fact that all the varrants issued by the district, and delivered to Grant, were disposed of, and are held by purchasers who were not made parties to the action, and who are not now before the court. The statute, at § 4907, Bal. Code, provides that, where it appears upon the face of the complaint that there is a defect of parties, objection may be taken by demurrer. Section 4909 provides that, where this fact does not appear upon the face of the complaint, the objection may be taken by answer. Section 4911 provides that, if no objection be taken either by demurrer or answer, the defendant shall be deemed to have waived the same. The complaint alleged that the warrants had been issued to defendant Grant. When defendant Grant answered, he admitted this fact, but did not allege that other persons, not parties to the action, were the owners thereof, although the fact was within his knowledge.. At the trial, and over the objection of the plaintiff, Grant was permitted to state that he was not the owner of any of the warrants, but had disposed of all of them before the action was begun. Under the statute it is clear that Grant had waived this point, and it was too late for him then to raise the question. State ex rel. McCain v. Metschan, 32 Or. 372, 46 Pac. 791, 53 Pac. 1071, 41 L. R. A. 692. It is true that in Stallcup v. Tacoma, 13 Wash. 141, 42 Pac. 541, 52 Am. St. 25, this court held, in- a case where the action was brought to restrain the payment of interest on certain bonds, that absent bond
By the appeal of the school district, the authority of the court to allow an attorney’s fee of $500 in this case is questioned. There is no statute in this state allowing attorney’s fees in a case of this kind, except § 5172, Bal. Code, which provides for $10 to be taxed as costs. In the absence of a statute, an allowance except for costs as provided is beyond the power of the court. Larson v. Winder, 14 Wash. 647, 45 Pac. 315; Trumble v. Trumble, 26 Wash. 133, 66 Pac. 124; Ditmar v. Ditmar, 27 Wash. 13, 67 Pac. 353, 91 Am. St. 817; Legg v. Legg, ante p. 132, 75 Pac. 130. That part of the judgment allowing an attorney’s fee is therefore reversed. In all other respects the judgment is affirmed. The board of directors will recover costs against appellant Criswell. Appellant Grant will recover no costs.
Fullerton, C. J., and Dunbar, Hadley, and Anders, JJ., concur.