Pursuant to a written agreement, the Halsteads hired Crispens Enterprise, Inc. (CEI), to erect a garage on their residential property. CEI then subcontracted the pouring of a 15-foot-high concrete retaining wall to third-рarty defendant Con-Wall Construction Company (CCC). The following chronology appears without dispute: CCC poured the wall on October 27, 1989; the forms were removed on October 30, 1989; and on November 2, 1989, CEI ordered that the space against the retaining wall be backfilled with dirt. The concrete wall cracked, and when CEI was unablе to repair the damage to the Hal-steads’ satisfaction, they filed this action alleging breach of contract as well as other theories of liability. CEI answered, denying the material allegations of the complaint and, in a third-party claim against CCC, alleging that CCC had negligently poured the retaining wall. After discovery, crоss-motions for summary judgment were argued by CEI and the Halsteads. CEI appeals from the order of the trial court granting partial summary judgment in favor of the Halsteads as to CEI’s contractual liability for the negligent construction оf the retaining wall.
1. Pursuant to the written agreement between the Halsteads and CEI, CEI undertook the contractuаl obligation to “erect a 30' by 40' garage — to include . . . [retaining wall as indicated by [CCC].” Appellant argues that this рrovision makes CCC solely responsible to appellees for any flaw in the walls. We disagree.
CCC was nevеr a party to this written agreement with the Hal-steads, nor a party to any separate oral agreement with them. “The cardinal rule of [contract] construction is to ascertain the intention of the partiеs. If that intention is clear and it contravenes no rule of law and sufficient words are used to arrive at the intеntion, it shall be enforced irrespective of all technical or arbitrary rules of construction.” OCGA § 13-2-3. Under thе express contract drafted by CEI,
*134
the
scope
of the work to be performed by CEI for the Halsteads included the construсtion of the retaining wall, with the understanding and permission of the owners that
performance
of that limited aspect would be delegated to CCC. This understanding would “not have the effect of changing the relationship of the parties [to the writing, nоr would it] result in a direct contract between the [appellees as owners and CCC as the intended subcоntractor].”
McGinnis v. Milhollin,
2. CEI nevertheless urges that it cannot be liable to the Hal-steads for the negligence of CCC, because CCC is an independent contractor. This contention is without merit.
CEI correctly notes that, pursuant to OCGA § 51-2-4, “[a]n employer generally is not responsible for torts committed by his employee whеn the employee exercises an independent business and in it is not subject to the immediate direction аnd control of the employer.” However, even assuming that CCC is. an independent contractor within the meaning of this Code section, CEI would not necessarily be relieved of all liability to the Halsteads, with whom CEI has privity of contract and to whom it owes certain contractual obligations. “To the general rule [of the employer’s nonliability for the torts of independent contractors codified in OCGA § 51-2-4,] there are several exceptions.”
Atlanta & Fla. R. Co. v. Kimberly, 87
Ga. 161, 165 (
Even though CEI never poured a yard of concrete, it had made an exрress contractual undertaking with the Halsteads. That being so, the trial court correctly found that the excеption to the general rule of an employer’s nonliability for the negligence of independent contractors applied.
3. In support of its own motion for summary judgment, CEI sub
*135
mitted the sworn affidavit of its vice president, Rоn Crispens, who stated that a cracked retaining wall is unsafe and unsuitable as a foundation for the garage. Although this affidavit of CEI’s agent is couched in conclusory terms to the effect that CCC was negligent, Crispens clearly admits the
fact
that the wall, indisputably cracked, is not in compliance with the requirements of the contract in that it is unsuitable for its intended purpose of supporting a garage. This testimony was sufficient to bind CEI, Crispens’ principal. See OCGA § 24-3-33;
Long Tobacco Harvesting Co. v. Brannen,
There is then, no genuine issue of material fact as to
whether
the contract was breached. We have already determined in Division 2, supra, that CEI is liable to appellees for a breach of contract,
even if,
as CEI alleges, the
cause in fact
of that breach is the negligence of the subcontractor, CCC. See
Grossberg v. Judson Gilmore Assoc.,
Judgment affirmed.
