Cresvale International, Inc. v. Reuters America, Inc.Cresvale International, Inc. v. Reuters America, Inc.
—Order, Supreme Court, New York County (Edward Lehner, J.), entered on' or about May 16, 1997, which denied the motion of defendants-appellants 61 Broadway Associates and Galbreath Co. and the cross mоtion of defendant-appellant Madison Building Services, Inc. for summary judgment, unanimously reversed, on the law, without costs, the motion and cross motion granted and the complaint dismissed. The Clerk is dirеcted to enter judgment in favor of said defendants-appellants dismissing the complaint as against them.
Plaintiffs leased 28th floor office space at 61 Broadway from defendant 61 Broаdway Associates (61 Broadway). Defendant The Galbreath Co. (Galbreath) was the managing agent, and defendant Madison Building Services, Inc. (Madison) was hired to perform cleaning and security services. Pursuant to the aforementioned lease, plaintiffs-tenants obtained insurance coverage from Cigna Insurance Company, insuring plaintiffs against loss and damage to proрerty at the subject building, as well as for business interruption losses.
The lease also included a waiver of subrogation clause
On April 20, 1990, an employee of defendant Madison was cleaning the 28th floor when she observed smoke in one of the offices. Instead of pulling a fire alarm located on that floor, the employee immediately took the elevator down to the lobby and informed the security guard, also a Madison employee, to call the Fire Department. According to the cleaning employee’s deposition testimony, the security guard looked at her like she was “crazy.” The emрloyee further testified that she observed the smoke at approximately 11:00 p.m. Fire Department records reveal that the first report was received at 11:12 p.m. Plaintiffs suffered substantiаl losses as a result of the fire, including business interruption losses. Cigna paid $1,200,000 on the claim, $850,000 of which was purportedly for business interruption losses.
In January 1994, Cigna commenced this action as plaintiffs’ subrogee to recover the amounts paid on the claim. The IAS Court denied in part 61 Broadway’s and Galbreath’s motion for summary judgment on the basis that the waiver of subrogation clause was limited by its terms to claims for property damages, and therefore did not operate as a waiver of plaintiffs’ claims for business interruption losses. The court also denied Madison’s motion for summary judgment, finding that triable issues of fact existed as to whether and to what extent Madison had a contractual duty to perform fire prevention services, and if it had such a duty, whether its еmployees negligently caused or aggravated plaintiffs’ damages by failing to report the fire in a timely manner.
Madison’s motion for summary judgment should have been granted. Plaintiffs allege that Madison had a duty under the Madison-61 Broadway contract to perform basic fire prevention duties, and its employees breached that duty. Madison counters that it had no such contractual or common-law duties, and, in any event, it owed no duty to plaintiffs, who were noncontracting parties.
“[A] duty of reasonable care owed by a tortfeasor to an injured party is еlemental to any recovery in negligence” (Palka
Contrary to the IAS Court’s conclusion, Madison’s purported breach of the Madison-61 Broadway contraсt affords no basis to hold Madison liable to the plaintiffs. The record establishes that the contract required Madison to perform cleaning and security services. There is no mention of any fire fighting or fire prevention duties required of Madison. Plaintiffs point to the listing of the security guard’s name in the building regulations as the evacuation supervisor, and the managing agent’s deposition testimony that it was “understood” that all building employees had fire prevention responsibilities, as evidence of Madison’s assumption of fire prevention duties. However, these “duties” arе not derived from the Madison-61 Broadway contract; rather, they exist as a common responsibility shared by all building tenants and employees to promptly report a fire. At best, plaintiffs’ evidence establishes an incidental or collateral connection between Madison’s contractual duties and plaintiffs’ fire-related injuries.
Madison’s limited contractual undertаking to supply cleaning and security services bears no resemblance to the “comprehensive and exclusive” management contract at issue in Palka v Servicemaster Mgt. Servs. Corp. (supra, at 588). In Palka (supra), the Court of Appeals found that a management company could be liable in tort to an injured plaintiff, who was not a contracting party, based on a breach of its duties under the management contract. The management contract in Palka
Given Madison’s limited contractual duties, it cannot be said that plaintiffs relied to their detriment on Madison’s performance of fire prevention duties (see, Keshavarz v Murphy,
On 61 Broadway’s and Galbreath’s appeal, we disagree with the IAS Court’s conclusion that the waiver of subrogation clause in the subject lease did not extend to claims for business interruption losses. Where a waiver of subrogation clause is limited to a specific type of loss, a subrogation action is barred only to the extent its seeks recovery for those species of losses (Kaf-Kaf Inc. v Rodless Decorations,
Here, the waiver clause applied to “any loss or damage to [tenant’s] property * * * resulting from fire or other hazards covered by such fire аnd extended insurance coverage” (emphasis added). Although plaintiff construes this phrase as limiting the waiver to claims for property damages, we conclude that the use of the words “any loss”, followed by the disjunctive “or,” requires a much broader reading (see, Coutu v Exchange Ins. Co.,
Additionally, the waiver provision expressly provided that the landlord, 61 Broadway, was not required to obtain insurance against the interruption of the tenant’s business. The clear import оf this lease provision, and the provision requiring the tenant to obtain insurance, is that the landlord would not be liable for the tenant’s business losses in the event an insurable event occurs. Thus, plаintiffs’ attempt to recover from 61 Broadway for business interruption losses “is inconsistent with the express provisions of the waiver of subrogation clause” (Kaf-Kaf, Inc. v Rodless Decorations, supra, at 660-661; see also, Periphery Loungewear v Kantron Roofing Corp., supra, at 461), and is barred thereby. Concur—Sullivan, J. P., Rosenberger, Wallach, Mazzarelli and Andrias, JJ.