Crest Const. v. Shelby Cty. Bd. of Educ.Crest Const. v. Shelby Cty. Bd. of Educ.
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *427
This case involves an interpretation of the Competitive Bid Law, specifically Ala. Code 1975, §
Two other questions are also presented:
(1) Did the trial court err in refusing to permit a witness to testify concerning the interpretation given to the term "lowest responsible bidder" by the Alabama Building Commission when a prequalification procedure was used and
(2) Was the lowest bidder, in any event, entitled to compensatory damages for the expenses it had incurred in preparing to bid?
The trial court, after conducting a hearing, held that the school board could award the contract to the company it determined to be the "lowest responsible bidder," even though it had required all bidders to show that they were qualified before the bids were submitted.
Crest sued the Board, alleging in its amended complaint that the Board had breached its duty of good faith and fair dealing. Crest sought to enjoin the execution of the contract between the Board and McCrory, and also sought a declaration that the contract, if executed, would be void. Crest also requested that the court order the Board to award the contract to it. Crest also asked for compensatory damages as reimbursement of bid preparation expenses. Crest also included McCrory as a defendant. The trial court, sitting without a jury, found that both Crest and McCrory were qualified to submit bids, but held that the Board had legitimate reasons to award the contract to McCrory. The effect to that holding was that the Board, even though it had required Crest to be prequalified, nevertheless could award the contract to the "lowest responsible bidder." The trial court denied the injunction and dismissed the claims. Crest appeals. We affirm.
Crest's argument obviously has appeal, because the trial court expressly found that Crest had qualified under the Board's qualification procedure. We hold, however, that the trial court did not err, for the reasons we will set forth in this opinion.
Of course, public agencies covered by the Competitive Bid Law must award contracts to "the lowest responsible bidder." §
Most of the decisions of this Court involving the application of the term "lowest responsible bidder" have construed the provisions of §
Although it appears that this Court has not previously addressed the specific question presented here, the United States Court of Appeals for the Eleventh Circuit, applying and interpreting Alabama's Competitive Bid Law, has considered a case involving a factual situation analogous to the one presented here. In Advance Tank *429 Construction Co. v. Arab Water Works,
Crest seeks to distinguish between a commodities contract and a construction contract, arguing that the considerations governing an award of a construction contract are different from those governing an award of a commodities contract, because all bidders for construction contracts offer to build according to the same plans and specifications. We disagree. Most of the factors listed in §
Although the case did not involve a construction contract, and even though a prequalification procedure was not involved, this Court in Inge v. Board of Public Works of Mobile,
"In the letting of public contracts to the lowest responsible bidder, the duty of the officer is not merely ministerial, but partakes of a judicial character, requiring the exercise of discretion. A discretion, however, which should always be exercised to the end of subserving the public interest, and never in the interest of the bidder. In deciding upon the responsibility of bidders it is the duty of the board or officers not only to take into consideration the pecuniary ability of bidders to perform the contract, but also to ascertain which ones, in point of skill, ability and integrity would be most likely to do faithful, conscientious work, and to fulfill the terms of the contract."
This Court has consistently held that when letting contracts covered by the Competitive Bid Law, public agencies have discretion to determine who is the lowest responsible bidder.Mobile Dodge, Inc. v. Mobile County,
"The Competitive Bid Law does not require that the lowest bid be accepted," International TelecommunicationsSystems,
Based on the foregoing, we reject Crest's argument thatAdvance Tank incorrectly interpreted Alabama's Competitive Bid Law. If we accepted Crest's argument, we would hold that the judicial discretion *430
vested in an awarding authority would be exhausted when that authority, using a prequalification procedure, determined that a bidder was qualified to bid. The fact that a contractor has been prequalified does not necessarily represent a finding of responsibility. Cf. Rollings Construction, Inc. v. TulsaMetropolitan Water Authority,
The parties dispute whether the Board intended by its prequalification procedure to deplete its discretion. Dampier testified that he had no authority to approve the qualifications of bidders. Dampier developed the prequalification criteria and consulted with Fulton. The Board's attorney reviewed some of the criteria, which were promulgated over the signature of the superintendent, Dr. Norma Rogers. Nevertheless, the Board apparently had not previously used prequalification and did not vote to use it in this case. Moreover, the specifications expressly reserved the Board'sright to reject any bid. For these reasons, we conclude that the Board did not affirmatively chose to deplete its discretion through the prequalification process used in this case. Cf. Advance Tank,
The question then becomes whether the Board's decision to award the contract to McCrory was arbitrary or capricious under the principles of law this Court set forth in White,
Crest claims alternatively that the Board's award of the contract to McCrory deprived Crest of due process because, it argues, Crest did not receive adequate notice of the Board's concerns. This argument appears not to have been made to the trial court; therefore, we will not consider it on appeal.E.g., Wang v. Bolivia Lumber Co.,
Crest further argues that the Board was estopped to declare Crest nonresponsible. The elements of equitable estoppel are:
General Electric Credit Corp. v. Strickland Division ofRebel Lumber Co.,"(1) The person against whom estoppel is asserted, who usually must have knowledge of the facts, communicates something in a misleading way, either by words, conduct, or silence, with the intention that the communication will be acted on; (2) the person seeking to assert estoppel, who lacks knowledge of the facts, relies upon that communication; and (3) the person relying would be harmed materially if the actor is later permitted to assert a claim inconsistent with his earlier conduct."
Fourth, Crest claims that the Board did not follow its own rules, under which, Crest says, it met the stated criteria for an award. Particularly, Crests argues that none of the Board's reasons for rejecting Crest's bid were listed as disqualifying factors in the published invitation for bids. The problem with this argument is that it assumes that prequalification is synonymous with a finding of responsibility, which, as we have discussed above, is not necessarily so. Furthermore, the specifications provided that meeting the prescribed provisions was a prerequisite to being considered for an award. The Board did consider Crest for an award. When planning a construction project, it would be difficult at best to conceive and list every possible factor that would disqualify contractors. The decision to disqualify a low bidder must be made in good faith, however, in the public interest and not in the interest of the successful bidder. See, e.g.,White,
Many factors indicate that the trial court did not err in excluding Sharpe's proffered testimony. First, a trial court's ruling on the materiality, relevancy, and remoteness of evidence are matters within the discretion of the trial court, and a ruling in that regard will not be disturbed by this Court unless it is shown to have been an abuse of discretion.Moseley v. Lewis Brackin,
We refuse to adopt such a rationale or procedure in Alabama. The legislature has provided a remedy to prevent an agency from violating the provisions of the Competitive Bid Law. A taxpayer or a "bona fide unsuccessful bidder" may sue "to enjoin execution of any contract entered into in violation of the provisions of [Article 3, §
Crest recognizes that a disappointed bidder's remedies are limited under Alabama law, because the Competitive Bid Law benefits the public and creates no enforceable rights in the bidders. Townsend v. McCall,
Under the facts of this case, we hold that the board did not predetermine responsibility. We should not be understood as holding that a public agency can not predetermine the responsibility of a bidder. We accept the proposition that a public agency can provide for a prequalification procedure.3 Here, however, the Board expressly reserved in the specifications the right to reject any bid by a prequalified bidder.
Based on the foregoing, we affirm the judgment of the trial court.
AFFIRMED.
HORNSBY, C.J., and SHORES, ADAMS, HOUSTON, STEAGALL and INGRAM, JJ., concur.