CRESCENT UNIVERSITY CITY VENTURE, LLC v. TRUSSWAY MANUFACTURING, INC. and TRUSSWAY MANUFACTURING, LLC
No. 407A19
IN THE SUPREME COURT OF NORTH CAROLINA
Filed 18 December 2020
MORGAN, Justice
Kiran H. Mehta and William J. Farley III for plaintiff-appellant.
Fox Rothschild LLP, by Elizabeth Brooks Scherer and Jeffrey P. MacHarg; and Martyn B. Hill and Michael A. Harris for defendant-appellees.
MORGAN, Justice.
In this case we must determine whether, under North Carolina law, a commercial property owner who contracts for the construction of a building, and thereby possesses a bargained-for means of recovery against a general contractor, may nevertheless seek to recover in tort for its economic loss from a subcontracted manufacturer of building materials with whom the property owner does not have contractual privity. The Business Court determined that North Carolina‘s economic
Factual and Procedural Background
Plaintiff Crescent University City Venture, LLC (Crescent) was the owner and developer of an initiative to build and lease several student apartment buildings near the campus of the University of North Carolina at Charlotte (the project). In 2012, Crescent entered into a contract with AP Atlantic, Inc. d/b/a Adolfson & Peterson Construction (AP Atlantic), a general contractor, whereby AP Atlantic agreed to construct a multi-building apartment complex on Crescent‘s property. As a matter of course, AP Atlantic entered into agreements with several subcontractors to facilitate the construction of the project, including a subcontract with Madison Construction Group, Inc. (Madison) for the provision and installation of wood framing for the buildings. The AP Atlantic-Madison subcontract required Madison to procure the floor and roof trusses at issue in the present controversy. The trusses in this context were structures of wood members held together by metal plates bristling with teeth, which were pressed into the pieces of wood at points where they connected at angles, creating a cross-supporting web of triangles. The trusses were delivered
Students of the University of North Carolina at Charlotte began occupying the apartments for the 2014-2015 academic year. Following a party attended by 80-100 people hosted in one of the units of Building C—one of the student apartment buildings erected during the project—on 30 January 2015, the occupants of the unit below reported that their living room ceiling had cracked and was sagging. Crescent relocated the residents of both units in Building C, after which the residents of a unit in Building E reported similar problems on 1 May 2015. Initial inspections revealed that the floor trusses between the apartments in Buildings C and E were defective. Crescent hired an engineering firm, Simpson Gumpertz & Heger, Inc. (SGH), to conduct an investigation into both the identified failures as well as a random sampling of the remaining apartments to determine if the structural defects were isolated or systemic. After examining the apartments with noticeable defects and a wider sample of other apartments, SGH informed Crescent that it believed the floor-truss defects were systemic and pervasive throughout the project. The investigation
On 5 August 2015, AP Atlantic filed suit against Crescent for outstanding payments on the project, to which Crescent responded with a breach of contract counterclaim on multiple grounds including the defective trusses. Crescent initiated a separate action against AP Atlantic‘s parent company to enforce a performance guaranty while AP Atlantic maintained multiple derivative claims against the subcontractors on the project, including Trussway. The matter was designated as a complex business case and assigned to the North Carolina Business Court for administration and resolution. The Business Court consolidated the actions on 10 October 2016. Following multiple rounds of pleadings, a lengthy discovery process, and several settlement agreements and voluntary dismissals, the resulting procedural posture led Crescent to move the Business Court to realign the parties, with Crescent as plaintiff, AP Atlantic and its parent company as defendants, and
On 12 February 2018, the parties to the consolidated action filed motions for summary judgment, while Crescent filed a complaint asserting a single negligence claim against Trussway, along with a motion to consolidate the new claim with the ongoing matters. Crescent‘s new complaint alleged that Trussway‘s negligence in manufacturing the trusses resulted in almost eight million dollars in damages from a combination of the project-wide repairs and stipends to residents for temporary accommodations, transportation, and storage. After this new action was itself designated as a complex business case on 7 March 2018, Trussway filed a motion to dismiss Crescent‘s new negligence complaint, arguing that the “prior action pending” doctrine barred such a claim. The Business Court held a hearing on the summary judgment motions, Trussway‘s motion to dismiss the new Crescent action, deemed the “Trussway Action” by the Business Court, and Crescent‘s motion to consolidate the Trussway Action with the remaining cases on 30 May 2018. In an order dated 16 July 2018, the Business Court denied Trussway‘s motion to dismiss the Trussway Action and granted Crescent‘s motion to consolidate. Following this consolidation and denial of its motion to dismiss, Trussway filed an answer to the Trussway Action denying Crescent‘s negligence allegation and lodging several defenses.
Analysis
Applying the economic loss rule, North Carolina courts have long refused to recognize claims for breach of contract disguised as the type of negligence claim that Crescent asserted against Trussway in the case before us. See generally N.C. State Ports Auth. v. Lloyd A. Fry Roofing Co. (Ports Authority), 294 N.C. 73, 240 S.E.2d 345 (1978),
The State Ports Authority sued the general contractor in Ports Authority for breach of contract based upon the contractor‘s alleged failure to construct the roofs “in accordance with the plans and specifications” of their agreement. The agency also included in its complaint a second claim that E.L. Scott negligently installed portions
The Supreme Court of the United States grappled with the question of “whether a commercial product injuring itself is the kind of harm against which public policy requires manufacturers to protect, independent of any contractual obligation.” Id. at 866 (emphasis added). Applying what is now coined as the economic loss rule in denying the tanker ship operators’ recovery from the turbine manufacturer, the Supreme Court of the United States held in East River that “a manufacturer in a commercial relationship has no duty under either a negligence or strict products-liability theory to prevent a product from injuring itself.” Id. at 871.
Crescent‘s argument, in construing the Court of Appeals decision in Lord v. Customized Consulting Specialty, Inc., 182 N.C. App. 635, 643 S.E.2d 28 (2007), to represent that the application of the economic loss rule hinges on the existence of a contract between the plaintiff and defendant, is at odds with our holding in Ports Authority which is specific to the commercial-development context. To the extent that
We are well aware of how the intersection between contract law and tort law in North Carolina has developed since Ports Authority, as illustrated by Crescent‘s reliance on Lord and this Court‘s discussion of negligence as a cause of action against residential homebuilders in Oates v. JAG, Inc., 314 N.C. 276, 333 S.E.2d 222 (1985). In Oates, this Court addressed the trial court‘s allowance of a defendant-homebuilder‘s motion to dismiss for failure to state a claim after the plaintiffs in the
This Court in Oates reversed the decision of the Court of Appeals, determining instead that a subsequent home purchaser in the consumer context could recover against the builder of the home in negligence, even if the purchaser maintained no contractual privity with the builder. Id. at 281, 333 S.E.2d at 226. In so holding, this Court adopted the public policy considerations of two Florida intermediate appellate court decisions which both addressed the plight of residential homebuyers who had alleged that their residences suffered from negligent construction on the part of the defendant homebuilders. Id. at 279-81, 333 S.E.2d at 225-26 (first quoting Navajo Circle, Inc. v. Development Concepts Corp., 373 So. 2d 689, 691 (Fla. Dist. Ct. App. 1979);
Our holding in Oates is a fact-specific response to a problem eloquently recognized by the Florida First District Court of Appeal in Simmons.
We must be realistic. The ordinary purchaser of a home is not qualified to determine when or where a defect exists. Yet, the purchaser makes the biggest and most important investment in his or her life and, more times than not, on a limited budget. The purchaser can ill afford to suddenly find a latent defect in his or her home that completely destroys the family‘s budget and have no remedy for recourse. This happens too often. The careless work of contractors, who in the past have been insulated from liability, must cease or they must accept financial responsibility for their negligence.
When a plaintiff asserts that the subject matter of a contract has, in its operation or mere existence, caused injury to itself or failed to perform as bargained for, the damages are merely economic, and a purchaser has no right to assert a claim for negligence against the seller or the product‘s manufacturer for those economic losses under the economic loss rule. See East River, 476 U.S. at 871 (concluding that the economic loss rule imposes no duty upon manufacturers “under either a negligence or strict products-liability theory to prevent a product from injuring itself“); see also Moore v. Coachmen Indus., Inc., 129 N.C. App. 389, 401, 499 S.E.2d 772, 780 (1998). The plaintiff must instead look toward the breach of its contractual relationship with its supplier or general contractor to recover these purely economic
Conclusion
North Carolina‘s state courts have consistently applied the economic loss rule to hold that purely economic losses are not recoverable under tort law, particularly in the context of commercial transactions. The Business Court was correct in its interpretation and application of this Court‘s decision in Ports Authority. Therefore, we affirm the Business Court‘s allowance of defendant‘s motion for summary judgment.
AFFIRMED.
MORGAN, Justice.
