49 Mo. 523 | Mo. | 1872
delivered the opinion of the court.
The court, sitting as a jury, tried the cause, and its finding of facts must be considered as conclusive here. The only important issue raised by the pleadings is in regard to the negligent. and unskillful manner in Avhich the work avqs done. I think there can be no doubt about the right of the city, under its charter and ordinances, to make the contract and assess the cost of the improvement against the property. The theory by Avhich the court declared the laAv in reference to damages is the only matter which Ave Avill revieAv.
There Avas evidence introduced going to shoAV that the Avork Avas not executed in accordance with the contract, and there was also evidence tending to shoAV that the work Avas Avortli as much as was charged for it in the bills. Upon this evidence the court was asked by the plaintiff to declare the law to be, that if it found that the work as done by the plaintiff Avas Avorth as much as, or more than, he contracted to do the same for, then the court should
Another instruction, offered by the plaintiff and'refused by the court, declared that if the work was not done in conformity to the contract, and the plaintiff should suffer a reduction of the amount sued for, still the defendant was not entitled to be credited with the whole amount of such reduction, but that the same should be credited pro rata on the whole cost of the work as done, and that the defendant should be credited only with a proportionate amount of such reduction. This instruction proceeds on the principle that, as the assessment is made against the specific property in the proportion which it bears to the whole work, the damage for negligent performance should be distributed in the same way. But this is surely an erroneous view of the subject. If the property-holder is damaged, his damage cannot be shown by others. And one single person only may be damaged on the whole line of the improvement, and he would undoubtedly have the right to have his injury deducted from the charge made against him. There was, therefore, no error in the action of the court in this regard.
The court, at the instance of the defendant, declared the law to be that if the court, sitting as a jury, believed from the evidence that the work contracted for, upon which the special tax-bill issued, was done in a manner inferior to that called for in the contract, then it should find for the plaintiff only such proportional amount of the sum assessed and sued on in this special tax-bill as the work actually done bore to the work if done according to the terms and specifications of the contract. This instruction was unobjectionable.
When work is to be performed in a particular manner, for a price agreed upon, the contractor cannot, by violating his'contract, place himself in a better situation than if he had complied with his undertaking. To permit the contractor to violate his agreement, and then recover the full value of his labor and materials, would be upholding unfair dealing. “ In such cases,” said Scott, J., in Marsh v. Richards, 29 Mo. 99 (see p. 105), “ the measure
In this case cross appeals were taken, and we have examined the record carefully, but have failed to find any substantial error committed by the court below.
Judgment affirmed.