70 So. 666 | Ala. | 1916
The question presented is this: Whether, after the contractor had breached his contract and abandoned the work, and after notice of the materialman’s claim, the owner, proceeding under a stipulation of the contract made for just that emergency, had the right, as against the materialman’s claim, to expend in the completion of the work any balance that would thereafter have become due to the contractor had he continued the work and completed the building according to contract. This question has been settled against the plaintiff in our cases of Alabama & Georgia Lumber Co. v. Tisdale, 139 Ala. 250, 36 South. 618, and McDonald Stone Co. v. Stern & Marx, 142 Ala. 506, 38 South. 643.
There are expressions used in the court’s argument of the case first above named that would seem on casual reading to lend color to plaintiff’s contention; but in the more recent case, McDonald Stone Co. v. Stern & Marx, the court, speaking through the same justice, made it clear that the judgment in the first case had been determined by the fact that the owner, after notice of the materialman’s claim, had made payment to the original contractor. And in the first case the court had said that: “Doubtless, if the owner should proceed with the improvement, expending what the contractor would have been entitled to had he not abandoned the contract, his property could not be subjected” — citing 43 Am. St. Rep. 903.
This view was repeated in the last-named case.
No error appearing, the judgment is affirmed.
Affirmed.