89 N.J.L. 288 | N.J. | 1916
The opinion of the court was delivered by
The plaintiff having contracted with the owner for the erection of the Hotel Traymore, at Atlantic City, sublet the necessary excavation for foundations and cellar to the defendants, the terms and conditions being committed to a writing signed by both parties bearing date August -4th, 1914, in which defendants agreed to do all the required excavation of every kind, hack-filling, shoring, sheet piling and pumping of water, in accordance with the specifications contained in the principal contract between the plaintiff and the owner, the work to be done under the direction of the architects whose construction of the meaning of plans and specifications should bo final. It was also agreed that no alterations should “be made in the work except upon written order of the contractor ; the amount to he paid by the contractor, or allowed by the subcontractor by virtue of such alterations, to be stated in said order,” and if the price could not be agreed upon by the parties, the work should go on and the amount he determined by arbitration. The compensation was to be forty cents per cubic yard, the material to he excavated was, principally, ocean beach sand; water was reached when the excavation was brought to, approximately the level of the ocean, and the extent of ttie excavation shown by the plans.
The principal defence set up by the appellants is that they were directed to excavate to a greater depth than the plans called for, and owing to the peculiar character of the work, which required the exclusion of water, the increased depth enhanced the proportionate cost so that forty cents per cubic yard was not a fair compensation for the increased depth, and that such work was not within the contemplation of the parties, nor provided for by the contract without a written order from the contractor, and therefore they were justified in abandoning its performance, and also that the right of recovery is limited to the penalty of the bond. Whether it was proper practice to credit the amount of the indemnity, secured by the bond, against the total excess cost, rather than enter judgment for full amount of such cost leaving the judgment on the bond as indemnity, we are not required to determine as the form of the judgment is not questioned in that respect.
The appellants’ objections will be considered in the order stated in their brief, the first of which is, the refusal of the
The defendants excavated several thousand yards of sand before they abandoned the contract, and the trial court found (hat the actual excess excavation performed over that called for' by the plans, was twenty-eight cubic yards. There is evidence to justify this finding and as we are not dealing with the weight of the evidence, we must assume that the net result of additional work done was but twenty-eight cubic yards, an amount we think too insignificant to call an alteration requiring a written order. In addition to this if defendants were entitled to such an order for alterations, and none was given, that did not justify their refusal to do the work contracted for, that they were hound to do even if they had the right to refuse additional work without a written order. What they did was to abandon the work altogether, and refuse performance of the residue of the work required by their contract. The form of the requests indicate that they were based upon an excerpt from the opinion in Sheyer v. Pinkerton, 59 Atl. Rep. 462, cited in Landstra v. Bunn, 81 N. J. L. 680, not applicable to this case. In those eases the suit was for work claimed to have been done in excess of the contract which required a written order, and contained a condition that no
We held in Landstra v. Bunn that the mere performance of extra service without such written authority did not give rise to an implied waiver of the provisions of the contract. But no such question arises in the present ease. If the additional work was an alteration and work not provided for in the contract, the subcontractors could, if they were right, have refused to do the work without an order, but the request to perform without it, would not abrogate the contract, nor relieve the contractor from the performance of what was not an alteration. There was no reason why appellants could not go to the depth called for by the plans and refuse to go further without the order.
The next point is, that there was no evidence to justify the binding that such additional work was not burdensome. There was testimony that it was not, and we cannot consider its weight on this appeal.
The last point argued is, that the defendants having furnished a bond for $3,000 their entire liability is limited to that amount, and a number of eases are cited holding that in a suit on a bond tire penalty is the extent to which the judgment may go. Camden v. Ward, 67 N. J. L. 558, and cases there referred "to. The rule in that and kindred cases does not conflict with this judgment, for the judgment on the bond is limited to the penalty, and under our present Practice act a plaintiff may join separate causes of action against several defendants if the causes of action have a common question of law or fact, and arise out of the same transr action. Pamph. L. 1912, p. 377, § 6.
In the present case the plaintiff had two causes of action arising out of tire, same transaction, one for damages for a breach of a contract, and another on the bond given in guaranty of its performance. The breach of the contract by the defendants was a question common to both cases—they arose out of the same transaction. There can be no doubt of the right of the plaintiff to proceed against defendants for a breach of their contract, and also to enforce its indemnity
hfo error appearing in this record, the judgment should be affirmed, with costs.
For affirmance—Tite Chancellor, Chief Justice, Garrison, Swayze, Treno hard, Parker, Bergen, Mixture, Ivallsch, Black, White, Heppenheimer, Taylor, Gardner, JJ. 14.
For reversal—ISTone.