Craddock v. Dwight

85 Mich. 587 | Mich. | 1891

Grant, J.

This suit was brought to enforce a lien under Act No. 229, Lalvs of 1887.

Plaintiff entered into a written contract with defendants running from January 1, 1887, to January 1, 1888, by which he agreed to manufacture shingles for the defendants from their lumber at $1 per M. for 14 inch, $1.10 per M. for 16 and 18 inch, $0.40 per M. for culls, $0.35 per M. additional for fancy butts, and $0.20 per M. for diamond, octagon, and other similar shapes. At the expiration of the year there was a verbal renewal of the contract. He filed his statement of lien March 6, 1889, stating that the last day's work and labor was done February 26, 1889, and that the amount due was $3,419.33. April 4 he sued out a writ of attachment, which commanded the sheriff to seize all the XXX and XX shingles then in the yard of W. M. Dwight & Co., or so much thereof as should be necessary to satisfy," etc. The sheriff seized 8,000 bundles of shingles, more or less. Defendants gave bond-under the statute, and the shingles were released. Plaintiff ceased work for defendants February 26. He had delivered to them all the shingles manfactured prior to February 21. He had in his possession those manufactured between February 21 and February 26 at the time he filed his statement of lien. Defendants paid plaintiff the amount due for manufacturing them. Plaintiff had also been paid for all that was due him to October 8, 1888. About 3,000,000 were *590seized by the sheriff. Of these 3,000,000 had been manufactured after October 8, 1888, and the other 1,000,000 prior to that date. At first defendants paid cash for the work done, but from and after January 30, 1887, they requested plaintiff to accept their notes or acceptances. Plaintiff acceded to this, and afterwards plaintiff presented his semi-monthly statements of the amount due, and received notes or acceptances, giving receipt in the following language: ' Received -- months’ acceptance for $--, on account.” - Between October and February 31 he received seven acceptances, four of which he discounted, but none of which were paid by defendants.

The jury found a verdict in favor of plaintiff for $3,467.94; that the same was—

“Due for labor and services performed upon a portion of the products described in the declaration, to wit, one million and a half XXX shingles, one-half million XX shingles, and also certain other shingles delivered said defendants, but not seized under the attachment issued in this cause; subject, however, to the opinion of the court as to whether there can be a greater lien than the sum of $1.00 per M. on the above-mentioned shingles.”

In reply to a special question, the jury found that they were able to state the quantity of XXX shingles and XX shingles in Dwight & Co.’s yard on March 6, 1889, on which plaintiff performed labor and services between October 8, 1888, and February 31, 1889.

1. It is first insisted that this act is unconstitutional. This precise question was raised and decided in Shaw v. Bradley, 59 Mich. 199, and Reilly v. Stephenson, 62 Id. 589. Its constitutionality was settled by those decisions, which have been recognized by many subsequent decisions *591of this Court, involving the various provisions of the act.1

2. It is next insisted that .the "court should have instructed the jury that the notes or acceptances were received by plaintiff as payment, and discharged the lien. This became a question of fact for the determination of the jury, and was not a question of law for the court. The court properly and. explicitly instructed the jury that, if they found that these notes or acceptances were received in payment, the lien was discharged, and their verdict should be for the defendants.- The jury found that they were not taken as payment, and their finding is conclusive.

3. Defendants insist that plaintiff has no lien upon any of the shingles manufactured before October 8, 1888, and that, therefore, under the finding of the jury, his lien must be limited to $2,000 for the work and labor performed upon the 2,000,000 shingles found by the jury to have been manufactured after October 8, and to have been taken under the writ. If the work and labor performed prior to October 8 had been done under a separate contract, or if, by express act and agreement of the parties, the shingles theretofore manufactured had been set apart, and kept separate and distinct from those subsequently manufactured, showing an intention to declare the contract completed as to them, their position would clearly be correct. But the contract was treated as a continuing one. As fast as shingles were afterwards manufactured they were mingled with those previously manufactured, and when the defendants sold and shipped *592shingles they filled cars with those that were most convenient. Oftentimes the last manufactured were the first shipped. Under these circumstances, it would certainly not be giving this statute a reasonable construction to hold that the lien applied only to those that were manufactured after payments had been made. Such a construction would in many cases defeat the very object of the statute.

4. The statute requires that—

“The statement of lien shall be filed within thirty days after the completion or last day of such labor or services.”

Defendants insist that this 30 days commenced to run from the time each statement of the amount due was rendered, and that, therefore, plaintiff has no lien except on the last statement rendered, which showed the amount due for the two weeks previous to be $431.56. Their counsel say:

“It was as if every two weeks he [the plaintiff] had made a new contract with Dwight & Co. to cut their shingles for the next two weeks, and, receiving settlement for the work done under one contract, he would begin on another.”

Ve do not think that this is a proper construction of the rendering of statements showing the amount of work done and the amount due. These were not separate contracts, but the method adopted by the parties in doing their business under one and the same contract.

Judgment affirmed, with costs.

The other-Justices concurred.

See Noyes v. Hillier, 65 Mich. 636; Pack, Woods & Co. v. Circuit Judge, 70 Id. 135; Goodrow v. Buckley, Id. 513; Demars v. Conrad, 73 Id. 151; Bourgette v. Williams, Id. 208; Streeter v. McMillan, 74 Id. 123; Appleman v. Myre, Id. 359; Kieldsen v. Wilson, 77 Id. 45 (partially overruled by Phillips v. Freyer, 80 Id. 254); Grand Rapids Chair Co. v. Runnels, Id. 104; Huntoon v. O'Brien, 79 Id. 227; Phillips v. Freyer, 80 Id. 254.

midpage