240 Pa. 27 | Pa. | 1913
Opinion by
The action was for the recovery of treble damages under the Act of June 4, 1883, P. L. 72, for injury alleged to have been sustained in consequence of the defendant’s refusal to furnish a siding connection with a coal mine operated by plaintiffs under a lease. Application for the siding connection was made 11th September, 1902. Some time thereafter the defendant submitted to the plaintiffs a plan, dated 4th October, 1902, showing a proposed siding which, so far as appears, was acceptable to the plaintiffs. Plaintiffs were proceeding with the opening of the mine when on the 14th November they were notified by the defendant that their application for a siding connection was declined. The claim was for damages sustained between January, 1903, when plaintiffs were prepared to ship coal, and August, 1904, when the New York Central Railroad Company by right of eminent domain appropriated the land which plaintiffs had intended for their siding. A verdict resulted to the plaintiffs in the sum of $34,814.50, single damages, afterwards reduced by remittitur to. $27,851.60, and then trebled by the court. The appeal is from the judgment so obtained.
It is complained first of all that the court held as a matter of law that the right of action was in the plaintiffs. That plaintiffs were the original lessees of the mine was undisputed. Subsequent to the demand for a siding connection, the White Oak Coal Company, a corporation, was created, in which these plaintiffs were the principal shareholders; and 5th November, 1902, a verbal agreement was entered into providing that when two drifts in the mine were opened to marketable coal, plaintiffs were to transfer the lease to the corporation
The action of the court in refusing to sustain defendant’s contention with respect to this feature of the case stands clear of error.
That the refusal to allow plaintiffs a siding connection was an undue and unreasonable discrimination against them was too clearly established to admit of question. The congested condition of traffic on defendant’s road, which was offered in explanation, afforded neither excuse nor extenuation. The means of protection against such condition was in defendant’s own hands. It was under no duty to haul more coal than could safely and conveniently be transported over its line; but a bounden duty did rest upon it, in limiting the amount to be accepted by it, because of extraordinary conditions, to show no preference as between shippers,
The evidence with respect to sale of cars by defendant to individual shippers had no relevancy to the issue being tried. No more had the evidence with respect to the loading of cars from wagons. All of this evidence should have been excluded, but it is impossible to see how it in the remotest way entered into the final conclusion. Otherwise, it would be ground for reversal.
There was no error in not distinguishing between inter-state and intra-state commerce in this case. It was not incumbent upon the plaintiffs to show what proportion of total tons they would have sold within the State. The case called for no such distinction.
The case of Robbins v. Farwell, 193 Pa. 37, furnished a complete answer to appellant’s contention that it was not for court but for the jury to say whether there should be a recovery for treble damages. Here they were trebled upon a rule to show cause. No question is made as to the verdict having been for single damages strictly as directed by the court. This was exactly the situation in the case above cited, where in affirming the action of the court in trebling damages upon rule, this court said, speaking by Dean, J., “Ever since Welsh v. Anthony, 16 Pa. 254, decided in 1851, the trial courts have exercised the power of doubling or trebling the
The verdict for single damages was conclusive as to the question of undue and unreasonable discrimination. This left nothing to be considered by the jury in connection with the trebling of the damages. The statute made provision for that. This brings us to the consideration of the only matter remaining.
The facts of the case indicated very clearly the true measure of damage. During the period for which damages were claimed plaintiffs’ mine was idle, and wholly unproductive because of the denial of siding connection. In January, 1905, the White Oak Coal Company then being in possession of the mine, a siding connection was furnished and the latter company then began and continued its operation of mining and marketing the coal from the mine. The plaintiffs offered evidence to show, 1st, the productive capacity of the mine; 2d, what the market price of the coal was month by month during the period of their trial of it; and, 3d, the market price for a corresponding period of seventeen months next following when operated by the White Oak Coal Company. By this showing, the- price had gradually declined, and the claim was for the difference in market price. Had this measure been strictly observed there would have been but little ground left for the contention. The court’s instructions to the jury on this branch of the case were as follows: “Now upon the subject of how much coal could have been mined and shipped there is a wide difference of opinion between the witnesses for the plaintiff and for the defendant.......You must satisfy yourselves from the evidence upon this subject with reasonable certainty as to the quantity of coal which might have been mined and shipped, considering all the existing conditions, the difficulties of mining, the water, the rolls in the vein of coal which would delay and make
How widely the jury departed from the measure here given them, is made very apparent by the learned trial judge in his opinion overruling defendant’s motion for a new trial, on condition of a remittitur being filed by plaintiffs. He there demonstrates how the jury arrived at their estimate of plaintiffs’ loss by taking as a factor the productive capacity of the mine instead of the amount of coal they could have marketed therefrom. He says: “The uncontradicted testimony in this case shows that in this region there has always been an insufficient car supply even when the coal trade was in normal condition. This arose not from any discrimination in car distribution, but from an insufficient number of cars to meet the demands and rated capacity of the mines. There is neither allegation nor proof of discrimination against the plaintiffs in the distribution of the
The verdict was for single damages. The court directed that upon plaintiffs’ filing a remittitur of all excess over $27,851.60, the rule for a new trial should be discharged; and this was accordingly done. This action of the court is assigned as error, and it is contended that the verdict even as reduced by the remittitur is excessive. That the verdict as rendered was in excess of the plaintiffs’ just demands was fully demonstrated by the learned trial judge in his opinion refusing a new trial. It would seem the better practice in cases of this kind, when it clearly appears that the jury in reaching its verdict overlooked items or circumstances making in relief of the defendant pro tanto, and which they were directed by the court to consider, but which in themselves furnished no fixed standard for admeasurement as to value, to grant a new trial; but we have no fixed rule' requiring it. It is within the discretion of the court to adopt either of two methods of correction: It may grant a new trial outright, or it may grant it on condition that plaintiff refuses to remit so much of the verdict as the court concludes is excessive. Here the latter course was adopted, the court fixing the amount to be remitted which it estimated to be the full equivalent of those matters making in relief of defendant which had been overlooked. This was no more than saying that had the verdict been for this reduced sum the court would have approved it, and a new trial would have been
The judgment is accordingly reversed, and motion for a new trial reinstated.