Cox v. Cameron Lumber Co.

39 Wash. 562 | Wash. | 1905

Rudkin, J.

On the 8th day of October, 1901, the plaintiffs and the defendant entered into a written contract, whereby the plaintiffs agreed to cut, from lands owned by the defendant, on the Little North - Eork of the Cceur d’Alene river, as per plat and description attached to the contract, not less than four million, - and not more than *565ten million, feet of logs, and to deliver the same in the Cceur d’Alene river, below the Old Mission. The logs were to be delivered not later than July 1, 1903, and as much earlier in that year as possible. The defendant agreed to pay at the rate of $4.12% per thousand for all logs so delivered, and to advance $3 per thousand on the logs whenever two hundred thousand feet, or more, were banked on or in the Little North Fork of the river. The defendant further agreed to construct a road to the plaintiffs’ camp, by the nearest-and most practicable route, for the purpose of furnishing the camp with supplies, the road to be completed not later than June 15, 1902. Under this contract the plaintiffs cut, and placed in the Little North Fork of the Cceur d’Alene river, 3,700,000 feet of logs, and received, on account thereof, the sum of $10,880.89. The plaintiffs brought this action to recover damages for a breach of the above contract.

The complaint alleged the execution of the contract, and that the contract was -fully performed by the plaintiffs, until they were compelled by the defendant to cease work under it, on or about- the 6th day of December, 1902. The complaint further alleged, as breaches on-the part of the defendant, that the defendant failed and refused to construct the road to the plaintiffs’ camp, as -agreed, and that the defendant stopped work under the contract as above stated. As a second cause of action, the complaint alleged that the plaintiffs were directed by the defendant to cut and remove timber from public lands of the United States; that they were indicted therefor, in the district court of the United States for the district of Idaho; that the-defendant failed and refused to defend them, or give them counsel or assistance; and that the plaintiffs paid, and became liable to the United States in the sum of, .$1,000 for cutting timber on four hundred acres of public land.

■The plaintiffs prayed judgment as follows: For $219.11, due on account of logs actually furnished and delivered; *566'$14,000 on account of profits on the uncompleted portions of the contract; $5,000 for failure to-construct the road as agreed, and $1,000 paid the government, as alleged in the second cause of action. The jury returned a general verdict in favor of the plaintiffs in the sum of $8,589.11. The jury also returned special findings, showing the items which made up their general verdict. The substance of these special findings was: For loss of profits, $4,000; for failure to construct road, $4,189.11; on account of second cause of action, $400. A motion for a new trial was denied, and from the judgment entered on the verdict of the jury, this appeal is taken.

The principal contention of the appellant, as to- the first cause of action, and the only one urged in the oral argument before this court, is that the contract in suit is illegal and void, and that no action can be founded thereon. This contention arises out of the following state of facts: Some time before the contract was entered into, the appellant made forest reserve scrip selections of extensive tracts of unsurveyed public lands, along the Little North Fork of the Coeur d’Alene river, in the state of Idaho-, under the act of June 4, 1897, 2 U. S. Comp. St. 1901, p. 1541, and the lands so selected are the lands referred to in the contract in suit. It is now maintained that these selections were unauthorized and void, for the reason that unsurveyed public lands were not subject to selection under said act; that the lands referred to in the contract in suit were therefore public lands of the United States; that the contract contemplated the cutting and removal of timber from such public lands, and was and is against public policy and void.

The contract was not illegal for any reason appearing on its face, as it expressly provided that the timber was to be cut from lands owned by the appellant. Nor was there any suggestion in the answer that the contract was illegal or void. On the contrary, the appellant itself interposed a counterclaim, and asked damages for the breach *567of the same contract. The defense of illegality in the contract cannot, therefore, prevail, unless a case is presented such as requires the court to interpose, of its own motion, and stop the proceedings, on grounds of public policy. "We are satisfied that no such case is presented here. The utmost that is claimed against the respondents is, that they knew the land was unsurveyed and knew that the appellant had scripped it. It does not necessarily follow from this that the appellant had no title.

The appellant contends, however, that it was the duty of the respondents to investigate the nature and character of its title, and had they done so, the law would charge them with notice that the appellant had no title, and that the title vested in the United Sates. No such duty rested upon the respondents. In the case of sales, or contracts of sale, this court has strictly enforced the doctrine of caveat emptor, but this iá not such a case. It will scarcely be maintained, as a rule of law, that a party, entering into a contract to perform certain acts on the lands of the other party to the contract, is required to investigate the nature of the title of such other party, at his peril, and, if he does not, and the performance of the contract will result in a trespass on the lands of a third person, the contract is void ab initio. In justice to both parties, we must presume that they supposed the appellant had a right to cut timber on the lands described in the contract. The defense now interposed is manifestly an afterthought, and neither the pleadings nor the evidence wárrant the court in holding, of its own motion, that the contract of the parties contemplated a violation of the laws of the United States. The contract was either’ valid or void, in its inception. Nearly all the errors assigned as to the first cause of action relate to the defense we have just considered. We have examined the other assignments, and find no error in the record as to this cause of action.

By the second cause of action, the respondents sought to *568recover money paid the United States in compromise’ and settlement of a criminal prosecution. This money was paid under the provisions of section 5, of the Act of June 3, 1878, 2 U. S. Comp. St., 1901, p. 1530, which reads:

“That any person prosecuted in said states and territory for violating section 2461 of the Revised Statutes of the United States who is not prosecuted for cutting timber for export from the United States, may be relieved from further prosecution and liability therefor upon payment, into the court wherein said action is pending, of the sum of two dollars and fifty cents per acre, for all lands on which he shall have cut or caused to be cut timber,' ór removed or to be removed the same.”

We confess we are at a loss to know how á recovery as to this cause of action can be sustained. If the respondents were guilty, there cán be no recovery, as the law permits no contribution between wrongdoers. The respondents contend that they were not guilty, but that they compromised the prosecution as a matter of precaution, and as the easiest way out of the difficulty. They contend further that the compromise was not conclusive evidence of guilt, in this case. We agree entirely that the compromise was not conclusive evidence of guilt, if indeed it was competent at all; but, for the sake of argument, let us concede that they were not guilty. When one person seeks to recover from another money which he has paid to a third person, he must show that the money was paid by request of the party from whom he seeks a recovery, or he must show that there was a legal obligation on his part to pay. Suppose a party is sued as an endorser on a negoti: able instrument for a large sum; he feels conscious that he is not liable, but, owing to the uncertainty as to the outcome, he compromises the claim for a lesser amount. He then sues the principal debtor to. recover the sum paid. Must he not show that the demand against him was well' founded law? So in this case, before the respondents can recover the amount paid the government from the appellant, they must show that there was a legal obligation on their 'part *569to make the payment, and they cannot show this without showing that they were guilty of the offense charged. So that, whether the respondents were guilty or not, they cannot recover from the appellant the amount paid the United States in compromise' of the criminal charge.

The judgment of the court below is therefore modified by eliminating therefrom the sum of $400, and as thus modified, the judgment is affirmed. The appellant will recover its costs on the appeal.

Mount, C. J., Fullerton, Root, and Crow, JL, coneur.
midpage