MEMORANDUM OPINION & ORDER
The Court has reviewed the Defendant Pinnacle Mining Company, LLC’s Motion for Summary Judgment (Document 104), filed on October 21, 2013. After careful consideration of the motion, the parties’ memoranda, attached exhibits, and the entirety of the record, the Court, for the reasons stated herein, finds that the Defendant Pinnacle Mining Company, LLC’s Motion for Summary Judgment should be granted.
The dispute herein arises from a strategic business alliance between two coal mining companies, Pinnacle Mining Company, LLC (Pinnacle), and Covol Fuels No. 4, LLC (Covol). Plaintiff Covol is incorporated in Utah with its principal place of business in Utah, and Defendant Pinnacle is incorporated in Delaware with its principal place of business in Ohio. (Compl. ¶¶ 9-10.) From 2008 until 2012, the parties operated under a contract providing for Covol to process the coal waste material from Pinnacle’s mining operation in Wyoming County, West Virginia, into saleable coal. (Compl. ¶ 13.) Covol alleges that certain actions and omissions by Pinnacle breached the parties’ contract, fraudulently and/or negligently misled Covol, and unjustly enriched Pinnacle. (See Compl.)
Pinnacle owns and operates an underground coal mine in Wyoming County, West Virginia. (Compl. ¶ 10.) Near the end of its mining process, Pinnacle utilizes a wash plant to strip and clean the mined coal of unwanted particulates, and then depоsits the resulting waste (refuse material) into an adjacent impoundment pond. (Compl. ¶ 15.) Prior to the parties’ written agreement, an affiliate company of Pinnacle, Beard-Pinnacle, LLC, operated a coal waste processing facility near the im-poundment to clean and process the refuse material into saleable coal. (Compl. ¶ 16.)
In 2008, Covol purchased Beard-Pinnacle’s assets at the Pinnacle mine, including the coal waste processing facility, for $14 million.
Section 1. Covol states its primary intention is to purchase, remove, transport, clean, and process the refuse material from Pinnacle’s mine into sa-leable coal.
Section 4. Covol agrees to purchase and process “all or part of the Refuse Material produced, previously, currently and any in the future” from Pinnacle’s mine. Covol will be responsible for transporting, storing, handling, and processing the refuse material and will do so “in such a way which does not interfere with Pinnacle’s Mining Operations.”
Section 5. Covol will pay Pinnacle $1.00 per ton of saleable coal produced from Covol’s refuse material processing operation.
Section 7. Both parties agree to comply in all respects with any and all laws, orders, mandates, and other governmental requirements. The parties take sole responsibility for their own compliance with all governmental requirements and any penalties for failing to do so.
Section 8. Covol must maintain and comply with the permits and licenses necessary for the operation of its coal waste processing plant. Pinnacle must “maintain its existing permits that are required for its performance under this Agreement.”
Section 10. Covol maintains complete control over its operations but must*729 conduct all activities in a manner that reasonably does the least possible damage to Pinnacle’s premises.
Section 12. The term of the contract is five years with a reoccurring option to renew for one year if the parties agree. Covol can unilaterally terminate the contract at any time if Covol decides the waste processing operation is no longer economically feasible.
Section 16. Either party can terminate the contract on the basis of material breach (after giving the breaching party an opportunity to cure), bankruptcy, or ceasing operations.
Section 18. Pinnacle agrees to: (1) “permit Covol to operate the Processing Facility for recovery of the Refuse Material”; (2) provide Covol with an area near the impoundment to operate its processing facility; (8) grant Covol “any right-of-way reasonably needed by Covol to transport the Refuse Material from the ponds to the processing plant”; and (4) allow Covol ingress and egress over Pinnacle’s property.
Section 20. Pinnacle disclaims any express or implied warranties and representations regarding the refuse material or the suitability of Pinnacle’s property for processing the refuse material.
Section 28. The CPRRA “embodies the entire understanding between the Parties with respect to the subject matter hereof’ and supersedes any prior understand or other writings.
(See Document 21-2.) The CPRRA also mandates that Covol is responsible for the waste from its processing facility, identifies West Virginia as the choice of law jurisdiction, and includes terms regarding assignment, written notice, paying taxes, record-keeping, indemnification, insurance, and legal ownership and liability for the land and the refuse material. (M) The CPRRA also references a Coal Sales Agreement between Covol and Pinnacle Coal Sales, LLC. (Compl. ¶ 23.)
Covol renovated the coal waste processing facility and, in the summer of 2008, began removing and processing refuse material from the impoundment.
By 2010, however, the slopes of the im-poundment had become too steep for Covol to continue removing the available refuse material, so the company began an excavation project to remedy the problem. (Compl. ¶ 25.) The parties dispute whether Pinnacle encouraged Covol to excavate the impoundment, and whether Pinnacle agreed to pay for some of the expenses. (Compl. ¶ 25; Document 30 at 5.) According to Covol, Pinnacle agreed that the project was necessary, “encourаged Covol to perform the excavation work,” and “gave Covol its assurance that it would share the cost of the work evenly.” (Compl. ¶ 25.) Pinnacle disagrees, arguing that it did not request that Covol complete the excavation project, nor did it agree to pay any of the expenses. (Document 105
Before beginning the excavation, Covol had to obtain approval from the Mine Safety and Health Administration (MSHA) on Pinnacle’s existing MSHA plan. (Document 105 at 5.) Per the revised MSHA plan, Covol intended to dredge the im-poundment in six twenty-five (25) foot lifts, and anticipated that the water level in the impoundment would be lowered accordingly after each lift.
Around the same time period that Covol completed the excavation project, Pinnacle made two significant changes to its mining operations. Pinnaсle (1) upgraded its own wash plant, and (2) changed its water management system, defeating both companies’ ability to lower or control the water level in the impoundment. (Compl. ¶¶ 27, 30.) Covol claims that the latter change made it “impossible for Covol to obtain access to the layers of coal waste that it can economically recover and process.” (Compl. ¶ 32.) These two changes, discussed in more detail below, form the basis of Covol’s claims against Pinnacle.
In late 2010, Pinnacle upgraded its wash plant. (Document 105 at 8.) Pinnacle does not dispute that improving its wash plant’s efficiency resulted in less coal content being deposited in the impoundment. (Id.) Pinnacle claims that the wash plant was outdated and inefficient. (Id.) Pinnacle further argues that the CPRRA did not prohibit Pinnacle from upgrading the wash plant, nor did it require Pinnacle to inform Covol that it intended to do so. (M) Regardless, Pinnacle claims that it told Covol of the planned upgrade in June 2010, and that Covol was aware that the upgrade would result in lower quality refuse material filling the impoundment. (Document 105 at 9.) Covol argues, however, that Pinnacle began planning to upgrade its wash plant in 1997, and failed to inform Covol of the same before the parties entered into the CPRRA. (Document 109 at 13.) According to Covol, this upgrade significantly decreased Covol’s ability to efficiently process the refuse material into saleable coal. (Compl. ¶¶ 28-29.)
The second change Pinnacle made — implementing the new water management system — was in response to a West Virginia Department of Environmental Protection (WVDEP) enforcement action against the company regarding selenium pollution.
Covol stresses that Pinnacle had an additional viable option for managing the selenium pollution issue — a water treatment program. This method for managing selenium is allegedly used by Pinnacle’s parent company at other mines, and was initially, albeit temporarily, submitted to the WVDEP as the company’s plan for selenium management at the Wyoming County, West Virginia, mine.
In essence, Covol argues that by choosing water management instead of water treatment, Pinnacle chose to eliminate both companies’ ability to lower the water level in the impoundment and “mak[e] it impossible for Covol to conduct operations.” (Compl. ¶ 4; Document 109 at 19.) Covol argues this decision effectively killed its waste processing operation. Because
In addition, Covol argues that Pinnacle did not keep Covol reasonably informed, respect Covol’s contractual or common law rights, or consider Covol’s recommendations regarding the selenium management issue. (Document 109 at 12.) Covol argues that Pinnacle only provided Covol with Barr’s draft report instead of its final report, and that Covol relied on the representations in the draft report to proceed with the excavation project. {Id. at 27.) Covol also claims that Pinnacle ignored Covol’s concerns and complaints about losing the ability to lower the water level, and that Pinnacle understood that lowering the water level was necessary for Covol to continue operations. (Compl. ¶¶ 6, 30, 33; Document 109 at 20.)
The parties vigorously dispute whether Pinnacle expressly or impliedly agreed to continue lowering the water level in the impoundment. Covol asserts that Pinnacle “repeatedly represented it could and would lower the watеr.” (Document 109 at 6.) In addition, Covol argues that the CPRRA requires Pinnacle to lower the water level because (1) Pinnacle expressly granted Covol “any right-of-way reasonably needed by Covol to transport the Refuse Material” from the impoundment pond to its processing plant; (2) Pinnacle “approved and submitted plans to governmental agencies that expressly provided” for lowering the water level; and (3) Co-vol’s right to access the refuse material was a predicate act and necessary to achieve the general purpose of the agreement-to recover refuse material to process into saleable coal.
As a result of Pinnacle’s actions (upgrading the wash plant and implementing the water management system) and alleged omissions (failing to inform Covol of the same), Covol argues that it was forced to shut down its operations. (Compl. ¶ 34.) Covol subsequently filed a Complaint (Document 1) against Pinnacle on August 7, 2012 asserting four claims: (I) breach of contract; (II) fraudulent concealment; (III) negligent misrepresentation; and (IV) unjust enrichment. (Compl. ¶¶ 38, 42, 49, and 57.) Covol demands a jury trial and seeks judgment in its favor, compensatory and consequential damages, interest on any judgment, costs and attorneys’ fees, and all other just and proper relief. (Compl. at 12.) In its Answer (Document
After extensive discovery by both parties,
II. STANDARD OF REVIEW
The well-established standard for consideration of a motion for summary judgment is that summary judgment should be granted if the record, including the pleadings and other filings, discovery material, depositions, and affidavits, “shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed.R.Civ.P. 56(a)-(c); see also Hunt v. Cromartie,
The moving party bears the burden of showing that there is no genuine issue of material fact, and that it is entitled to judgment as a matter of law. Fed.R.Civ.P. 56(a); Celotex Corp.,
III. DISCUSSION
A. Breach of Contract
In the first cause of action, Covol claims that Pinnacle breached the CPRRA. The Court notes that neither party challenges that the CPRRA was a valid and enforceable contraсt, or that both parties were mutually bound by its terms. The parties disagree, however, concerning the nature and extent of their respective rights and obligations pursuant to its terms.
Pinnacle asserts that it did not breach any express term of the CPRRA and argues that no implied or express term created a duty to lower the water level or provide Covol access to the refuse material in the impoundment. Covol argues that it cannot access the refuse material unless Pinnacle lowers the water level, and claims that the contract expressly and impliedly grants it the right to access and remove the refuse material. Pinnacle replies that the contract defines the full extent of Co-vol’s right of access as a limited right-of-way that “clearly does not obligate Pinnacle to lower the water level at Covol’s demand.” (Document 113 at 3).
1. Express Terms of the CPRRA
Claims alleging breach of an unambiguous contract are “particularly suited for summary judgment disposal” because a court can “ascertain the meaning of the agreement as manifested by its language” and “enforce it as written.” Bank of Montreal v. Signet Bank,
If the language is unambiguous, it “must be construed according to [its] plain and natural meaning.” Fraternal Order of Police,
If the court determines that the contract is ambiguous, it should consider
The Court finds that the language of the CPRRA is clear and unambiguous. The terms are straightforward, understandable, and definitive. They are not susceptible to more than one reasonable interpretation. Further, the contract is the product of negotiations between sophisticated corporate parties, both represented by counsel. Therefore, the Court will identify and enforce the plain and natural meaning of the language of the CPRRA.
Covol’s assertion that Section(s) 1, 4, 8, and 18 of the CPRRA provide it with an express right of access to the refuse material in the impoundment is unavailing. Section 1 of the CPRRA defines Covol’s intentions in entering into the agreement.
Pinnacle hereby agrees to permit Covol to operate the Processing Facility for recovery of the Refuse Material at the Refuse Site. Pinnacle shall provide to Covol: (i) a mutually agreeable area in the immediate vicinity of each fines pond that is adequate for Covol to install and maintain its Processing Facility and equipment for recover of Refuse Material; (ii) any right-of-way reasonably needed by Covol to transport the Refuse Material from the ponds to the processing facility; and (Hi) ingress and egress over the property of Pinnacle or its lessors to support the activities described in this Agreement.
(Document 21-2 at 10.) Covol asserts that the right-of-way in Section 18(H) “necessarily extend[s] beyond the water’s edge through the depth of the water.” (Document 109 at 17.) However, allowing Covol access to the bottom of the impoundment pond does not require Pinnacle to affirmatively lower the water level. The Court will not impose an additional duty or right that is not expressed by the plain language of an unambiguous contract. See Fifth Third,
Covol also argues that Section 8 of the CPRRA requires Pinnacle to lower the water level in the impoundment pond in accordance with certain mining plans submitted to MSHA and the WVDEP.
Pursuant to West Virginia law, “a general reference in one writing to another document is not sufficient to incorporate that other document into a final agreement.” State ex rel. U-Haul Co. of West Virginia v. Zakaib,
In sum, the Court “will not use the vehicle of interpretation to relieve one party of a bad bargain.” Pechenik v. Baltimore & O.R. Co.,
2. Common Law or Implied Right to Access
Pinnacle next argues that Covol’s rights are “solely governed” by the express language of the CPRRA, which does not require Pinnacle to “control the water level for Covol’s benefit or grant[] Covol any right to demand that Pinnacle raise or lower the water level.” (Document 105 at 13-14.) Covol counters that the terms of the CPRRA “collectively evidence” a right to access the refuse material because doing so was a “necessary predicate” to achieving the “fundamental purpose” of the CPRRA. (Document 109 at 16-17.) Covol supports this argument with deposition testimony from Mr. William Boor, “Pinnacle’s Rule 30(b)(6) witness on the terms of the CPRRA.”
As noted supra, the Court will not create or impose an additional duty or right that is not expressed by the plain language of the parties’ unambiguous and fully integrated contract.
Even assuming arguendo that the CPRRA as a whole establishes an implied duty that Pinnacle provide Covol with a right to access the refuse material, the Court is not persuaded that Pinnacle materially breached such an obligation. When Pinnacle upgraded the wash plant and changed the water management system, these actions undoubtedly made it more difficult for Covol to access the refuse material and thereby profit from operating the processing plant. However, Covol was never denied access to the refuse material. Covol simply had to deal with more water in the impoundment where the refuse material was located. Tellingly, Section 20 of the CPRRA explicitly disclaims any warranty regarding the quantity or quality of the refuse material and the suitability of its property for the operation of Covol’s processing plant.
3. Implied Covenant of Good Faith and Fair Dealing
Pinnacle argues that the implied covenant of good faith and fair dealing “does not give Covol any rights inconsistent with those rights expressly provided for” in the CPRRA. (Document 105 at 19.) Because Pinnacle did not violate any of Covol’s rights under the CPRRA, Pinnacle argues it is not in breach of the implied covenant as a matter of law. (Id. at 20.) Covol responds that an implied covenant of good faith and fair dealing is automatically incorporated in the CPRRA, and asserts that changing the water management system so that the water could not be lowered and Covol could not receive the benefit of the contract constitutes a breach. “If Co-vol wanted to impose an unfettered duty on Pinnacle to raise and lower the water level in the Impoundment at Covol’s whim and for Covol’s sole benefit,” Pinnacle argues, “Covol should have ensured that the CPRRA contained a provision imposing that duty.” (Document 113 at 10.)
It is true that West Virginia law incorporates an implied covenant of good faith and fair dealing into every contract. Fifth Third,
Here, the implied covenant of good faith requires Pinnacle to act within “reasonable commercial standards of fair dealing” when performing its duties under the CPRRA. See Fifth Third,
B. Fraudulent Concealment and Negligent Misrepresentation
Pinnacle advances three reasons why Covol’s fraudulent concealment and negligent misrepresentation claims must fail as a matter of law. First, Pinnacle argues that Covol cannot recover under a West Virginia common law tort claim because its claims arise from the same subject matter covered by the CPRRA. (Document 105 at 21-22.) Second, Pinnacle contends that there was never a relationship between the parties that would prompt an affirmative duty to disclose. (Id. at 22-23.) Third, Pinnacle asserts that Covol’s alleged reliance on Pinnacle’s silence was unreasonable and unjustifiable based on the timing of Pinnacle’s changes and Covol’s investments. (Id. at 21-26.) Pinnacle argues that Covol purchased and upgraded the waste processing facility before Pinnacle decided to upgrade the wash plant and change the water management system.
In reply, Pinnacle again stresses that Covol’s claims arise from the CPRRA and therefore are not recoverable under tort law; that Covol and Pinnacle were not in a special relationship that would prompt a duty to disclose; that Pinnacle did not have plans to upgrade the wash plant or change the water management system before Covol purchased the waste processing facility and that Covol was informed of the wash plant upgrades and selenium pollution issue before approving the excavation project. (Document 113 at 11-16.)
The elements of fraudulent misrepresentation mirror the well-established elements of fraud: (1) the fraudulent act was committed or induced by the defendant himself; (2) the act was “material and false,” the plaintiff relied on it, and the plaintiffs reliance was “justified under the circumstances;” and (3) the plaintiff suffered damage from his reliance. Trafalgar House Const., Inc. v. ZMM, Inc.,
Fraudulent concealment, on the other hand, requires: (1) the concealment of facts by the one with knowledge of those facts; (2) a duty to disclose; and (3) “an intention to mislead or defraud.” Trafalgar,
Under the West Virginia gist-of-the-action doctrine, “whether a tort claim can coexist with a contract claim is determined by examining whether the parties’ obligations are defined by the terms of the contract.”
The Court finds that Pinnacle is entitled to summary judgment on Co-vol’s claim for fraudulent concealment and negligent misrepresentation. In essence, Covol is claiming that Pinnacle is liable for failing to disclose its plans to upgrade its wash plant. This argument is based on a claim for fraudulent inducement, which requires that (1) Pinnacle induced Covol to enter into the CPRRA (2) by false representations (3) Pinnacle knew, or had a duty to know, were untrue. Folio v. Clarksburg,
C. Unjust Enrichment
Finally, Pinnacle argues that Covol’s unjust enrichment claim must fail as a matter of law because Covol cannot establish genuine evidence that Pinnacle benefited from the excavation project. (Document 105 at 26.) Pinnacle also claims to have expressly rejected any proposed agreement to share the expenses, which it argues defeats any suggestion that Covol is equitably entitled to receive payment for the excavation.
In West Virginia, the claim of unjust enrichment has three elements: (1) a benefit bestowed upon the defendant; (2) knowledge of such benefit by the defendant; and (3) “the acceptance or retention by the defendant of the benefit under such circumstances as to make it inequitable for the defendant to retain the benefit "without payment of its value.” CUMIS Ins. Soc’y, Inc. v. Raines,
Covol undertook the excavation project so that it could “access more mina-ble [refuse] material” in performance of its rights and duties under the contract. (Document 109 at 13.) As such, the excavation project — as well as any alleged benefit conferred to Pinnacle — falls within the scope and subject matter of the parties’ written contract.
Instead, Covol agreed to “accept the risks associated with the ... suitability of Pinnacle’s premises” for removing and processing refuse material. (Document 21-2 at 12.) Thus, the subject matter of this claim involves the performance of an express contract, and as such, cannot be the basis of an unjust enrichment claim. Accordingly, the Court finds that Pinnacle is entitled to summary judgment on the unjust enrichment claim.
CONCLUSION
Wherefore, after thorough review and careful consideration, the Court hereby ORDERS that the Defendant Pinnacle Mining Company, LLC’s Motion for Summary Judgment (Document 104) be GRANTED. The Court further ORDERS that any outstanding motions be
The Court DIRECTS the Clerk to send a copy of this Order to counsel of record and to any unrepresented party.
Notes
. This was accomplished through an Asset Purchase Agreement dated February 2008 between Covol and Beard-Pinnacle, LLC.
. Covol spent $4 million to renovate the coal waste processing facility. (Document 109 at 3.)
. Pinnacle does not dispute that "during certain periods of time the water level in the impoundment was periodically adjusted by pumping water out of the impoundment.” (Document 30 at 4.)
. Covol argues that it "bestowed a significant monetary benefit on Pinnacle by redesigning and recontouring the banks of the impoundment, including the removal of approximately one million cubic yards of unstable material from the banks of the impoundment.” (Compl. ¶ 55.) Pinnacle denies these allegations. (See Document 30 at 5.)
. Covol asserts that Pinnacle submitted the water lowering plan to MSHA (Document 109 at 6-8), while Pinnacle argues that Covol submitted it. (Document 105 at 6.)
. The excavation project began in 2010 and was completed in 2011. (Compl. ¶¶ 25-26.)
. The Court notes that there are multiple disputes between the parties over Pinnacle’s management of the selenium pollution issue. Selenium is a contaminant found in coal seams and a problem for coal companies in this region. (Document 105 at 14.)
. Pinnacle does not dispute these facts.
. Covol asserts that "[i]n April 2008, Pinnacle submitted a permit modification application to WVDEP to reduce selenium discharge through bioremediation treatment оf the water.” In October 2008, Pinnacle changed the treatment plan in its permit modification to the water management system, which Pinnacle implemented after the WVDEP approved it in February 2009. (Document 109 at 10-11.) Pinnacle does not dispute these facts.
. Pinnacle does not dispute this fact. However, Pinnacle argues that “neither of those reports 'rejected' water management techniques as a solution or concluded that treatment alone was a viable option; instead, both reports concluded that water management was necessary.” (Document 113 at 16.) The Court reads otherwise. A side-by-side comparison of the draft report to the final report reveals multiple material changes. For example, in the draft report, Barr states:
Overall, of the nine treatment technologies reviewed, the passive microbial reactor appears to be the best suited for application at the site. It has been proven to be able to reduce selenium concentrations to meet regulatory requirements and the design is easily adaptable to the site. The low capital and operational costs and minimal supervision make this option an attractive solution.
(Document 109-1 at 292.) In Barr’s final report, however, this language was chаnged to:
None of the nine treatment technologies reviewed has proven to be a technically or practically feasible means of complying with low level selenium discharge limits on a mining scale. Any treatment alternative will require additional testing and evaluation.
(Document 104-22 at 63.) Further, the Court found the following language in the draft report, but not the final:
Finally, pump flow from the impoundment is a significant contributor to the water system discharge and should be minimized when possible. The fines recovery process [processing of refuse material] and required impoundment water elevation changes further exacerbate the selenium contribution.
(Document 109-1 at 288.)
. Covol claims that when it purchased the waste processing facility in 2008, Pinnacle was operating under an "MSHA-approved mining plan that required the lowering of the water level in the impoundment.” Additionally, "Covol reviewed the [plan] and discussed it with Pinnacle prior to the execution of the CPRRA; both parties understood the importance of lowering the water level in the im-poundment so that Covol would have access to the coal fines.” (Document 109 at 7.)
. Pinnacle attached the following as exhibits to its Answer: (A) a thirty-one page “Asset Purchase Agreement” dated February, 2008, and signed on separate pages by Covol Fuels No. 4, LLC, and Beard-Pinnacle, LLC; (B) an eighteen page "Coal Purchase and Refuse Recovery Agreement” dated February 15, 2008, and signed by Covol Fuels No. 4, LLC, and Pinnacle Mining Company, LLC; and (C) a fourteen page "Coal Sales Agreement” dated February, 2008, and signed on separate pages by Covol Fuels No. 4, LLC, and Pinnacle Coal Sales, LLC. The same three exhibits that were attached to Pinnacle’s original Answer were attached to its Amended Answer.
. The Court notes that discovery was ongoing as of November 5, 2013, evidenced by footnote 26 of Covol’s response in opposition, which states, in relevant part, that "the parties are in the process of arranging a deposition.” (Document 105 at 10, n. 26.)
. Pinnacle attached the following as exhibits to its Memorandum in Support of Its Motion for Summary Judgment: (A) portions of the transcript of the deposition of J. Scott Ballard on September 11, 2013, and several of the exhibits; (B) portions of the transcript of the deposition of Kirk A. Benson on September 30, 2013, and several of the exhibits; (C) additional portions of the transcript of the deposition of Kirk A. Benson on September 30, 2013; (D) portions of the transcript of the deposition of William C. Boor on September 27, 2013, and a copy of the Coal Sales Agreement between Covol Fuels No. 4, LLC, and Pinnacle Coal Sales, LLC; (E) portions of the transcript of the deposition of Matthew R. Cartier on July 23, 2013, and several of the exhibits; (F) portions of the deposition of Russell E. Combs on September 5, 2013; (G) portions of the deposition of John W. Flegel on September 4, 2013, and one of the exhibits; (H) portions of the deposition of William H. Gehrmann, III on October 1, 2013, and several of the exhibits; (I) portions of the deposition of Edward H. Greenwald, Jr. on July 24, 2013, and several of the exhibits; (J) portions of the deposition of Barry O’Bryan on August 7, 2013; (K) portions of the deposition of Roy Palmer on August 8, 2013, and several of the exhibits; (L) portions of the Rule 30(b)(6) deposition of Covol Fuels No. 4, LLC and Gina Rau on October 1, 2013, and several of the exhibits; (M) portions of the deposition of Michael Stevens Rich on October 2, 2013, and one of the exhibits; (N) portions of the deposition of Donald S. Risher on September 12, 2013, and one of the exhibits; (O) portions of the deposition of John R. Shaal on July 11, 2013, and one of the exhibits; (P) portions of the deposition of Donald Douglas Townsend on September 27, 2013, and one of the exhibits; (Q) portions of the deposition of D. Douglas Townsend on July 12, 2013, and several of the exhibits; (R) portions of the deposition of Darrell J. Turner on September 25, 2013, and several of the exhibits; (S) one portion of the deposition of Duke D. Vetor on September 24, 2013; and (T) Declaration of D. Douglas Townsend dated October 16, 2013, and the exhibits.
.Covol attached the following as exhibits to its Opposition to Defendant Pinnacle Mining Company, LLC’s Motion for Summary Judgment: (A) portions of the deposition of William C. Boor on September 27, 2013; (B) portions of the deposition of Matthew R. Cartier on July 23, 2013; (C) portions of the deposition of Russell E. Combs on September 5, 2013; (D) portions of the deposition of Barry Douglas Dangerfield on September 17, 2013; (E) portions of the deposition of John W. Flegel on September 4, 2013; (F) portions of the deposition of Barry O’Bryan on August 7, 2013; (G) portions of the deposition of Roy Palmer on August 8, 2013; (H) portions of the Rule 30(b)(6) deposition of Covol Fuels No. 4, LLC and Gina Rau on October 1, 2013; (I) one portion of the deposition of Donald S. Risher on September 12, 2013; (J) portions of the deposition of John R. Shall on July 11, 2013; (K) portions of the deposition of D. Douglas Townsend on July 12, 2013; (L) portions of the Rule 30(b)(6) deposition of
. Pinnacle attached the following exhibits to its Reply in Support of Its Motion for Summary Judgment: (A) one portion of the deposition of J. Scott Ballard on September 11, 2013, and onе of the exhibits; (B) one portion
. Section 1 of the CPRRA states in relevant part:
Covol represents that it desires to remove and purchase all or part of the coal waste material ... resulting from Pinnacle’s previous, current or future Mining Operations ... located at the Pinnacle refuse site in Wyoming County, West Virginia, and ... Covol represents that it desires to transport the Refuse Material to the Processing Facility to be cleaned and to be sold as a clean coal product....
(Document 21-2 at 1) (emphasis added).
. Section 4 of the CPRRA states in relevant part:
Covol agrees to purchase and process, while this Agreement is in effect, all or part of the Refuse Material produced, previously, currently and any in the future, from Pinnacle's Mining Operations in Wyoming County, West Virginia.” "Covol, at its own expense, will transport the Refuse Materials to Covol’s Processing Facility.
(Document 21-2 at 3) (emphasis added).
. Section 8 of the CPRRA states, in relevant part, that "Pinnacle shall maintain its existing permits that are required for its performance under this Agreement.” (Document 21-2 at 5.)
. In its complaint, Covol claims an "enforceable common law right of access to mine the coal estatе granted by Pinnacle” and that "Covol's common law rights secure access to the coal in the impoundment....” (Compl. ¶ 22.) Pinnacle counters that “the evidence demonstrates that the CPRRA is a bare license to mine that carries with it no implied rights of access as a matter of law.” (Document 105 at 13.) Covol appears to have abandoned this common law right of access argument, as the claim is absent from Covol’s response. (See Document 109.) For reasons similar to those articulated by Pinnacle in its motion for summary judgment, the Court does not find a legal basis for Covol’s alleged common law right to access.
. Mr. Boor stated the following in his deposition:
Q. Sure. It wouldn’t make any sense for Covol to enter into an agreement where it wasn’t allowed to have access to the material in the impoundment pond, would it?
A. Yeah, that would be no deal. I mean, the purpose of the deal was for their business plan to clean coal.
Q. And to clean the coal you had to have access to the coal, correct?
A. Yes.
(Document 109-1 at 6-7; Exhibit A, 69:18-70:5.)
.Section 28 of the CPRRA states, in relevant part, that the contract "embodies the entire understanding between the Parties with respect to the subject matter hereof and supersedes all prior negotiations, representations, understandings or other writings.” (Document 21-2 at 15-16.)
. Section 20 of the CPRRA states in relevant part:
Pinnacle makes no representation as to the character or quality or amount of the Refuse Material Covol removes or receives. Pinnacle HEREBY DISCLAIMS ANY WARRANTIES, EXPRESS OR IMPLIED, IN CONNECTION WITH THE REFUSE MATERIAL. ... Pinnacle has not made any representation or warranty to Covol regarding the suitability or safety of Pinnacle’s property for the processing of the Material as contemplated by this Agreement.... Co-vol represents that it is an independent contractor and is willing to accept the rislcs associated with the safety or suitability of Pinnacle's premises for the Material processing contemplated by this Agreement.
(Document 21-2 at 11-12) (first emphasis in original) (second emphasis added).
. Counts Two and Three of Covol’s complaint are based on the same alleged facts, so the Court considers them here contemporaneously. Both parties do the same in their respective motion for summary judgment and response.
. It is undisputed that the parties entered into the CPRRA in February of 2008. (Document 21-2 at 1.) Pinnacle provides evidence that the wash plant upgrade project was presented to Pinnacle’s board of directors in November of 2009. (Document 113-20 at 7.) It is undisputed that Pinnacle did not upgrade its wash plant until 2010. (Document 105 at 8.) In addition, Pinnacle argues that it "did not face any government action regarding selenium, which necessitated its change to its water management system” until March, 2010, when the DEP denied the company’s request for an extension of its compliance date. (Document 105 at 24; see also Document 104-7 at 9; Exhibit G, 139-40) (deposition testimony from John Flegel and accompanying exhibits confirming the DEP’s denial of Pinnacle’s request for an extension in March of 2010).
.Covol’s management approved the excavation project in October of 2010. (See Document 104-8 at 39; Exhibit H, 176:14-18.) Darrell Turner, a manager at Covol, stated in deposition that Covol was aware of Pinnacle’s plan to upgrade its wash plant by July 2010. (Document 104-23 at 33; Exhibit R part 1, 293:14-18) (Q: "So is it fair to state that as of
. Covol relies on the MSHA plans that provided for lowering the water level in the im-poundment to support this assertion. (Document 109 at 6-8.)
. The gist-of-the-action doсtrine bars recovery with a tort claim when any of the following is found:
(1) where liability arises solely from the contractual relationship between the parties; (2) when the alleged duties breached were grounded in the contract itself; (3) where any liability stems from the contract; and (4) when the tort claim essentially duplicates the breach of contract claim or where the success of the tort claim is dependent on the success of the breach of contract claim.
Gaddy,
. Covol proposed to Pinnacle in November of 2011 that the parties amend the CPRRA to address splitting the cost of the excavation project after Covol had begun the project. In his deposition, Covol manager Darrell Turner stated:
Q. So is it fair to state that it was on November 1, 2011 that you submitted the proposed changes to the contract to address the spoil removal issue?
A. The context was that we had an extended period of time where we could not get any response from Duke Vetor so this, our sending the proposed changes again were in response to my email below on November 1st, 2011.
Q. And I believe you already testified, at least as far as you know, this was never signed by the parties, correct?
A. Correct.
Q. And at this point in time the spoil removal project was well underway and I think you testified there, monies had already been expended by Covol for the project, right?
A. Yes.
(Document 104-23 at 39-40; Exhibit R part 1, 319:16-320:11.)
. The Fourth Circuit concluded:
When the dust is settled, this case presents nothing more than two sophisticated parties engaged in a supplier-distributor relationship governed by written contracts. Through contract, the parties have established the scope of their benefits and the limits of their liabilities, thereby injecting predictability and regularity into their relationship .... If [the plaintiff] had desired a higher price for its services or reimbursement for its actual costs, it should have bargained for such terms and embodied them in contract.
Bright,
. In fact, Covol sought to amend the CPRRA and add a clause requiring Pinnacle pay for a portion of the excavation project. (Document 105 at 27-28) (citing deposition testimony from Darrell Turner, a manager at Covol, stating that Covol’s proposed amendment was never executed (Document 104-23 at 38-40; Exhibit R part 1, 318-20)).
.Covol admits that it communicated to Pinnacle its intentions to perform the excavation in October of 2008. (Document 109 at 13.) Pinnacle claims that only once the excavation project was nearing completion, “Covol attempted to negotiate an agreement with Pinnacle to pay for half of the project and prepared a proposed amendment” to the parties’ contract, which Pinnacle rejected. (Document 105 at 10.) Covol does not dispute these facts. (Document 109 at 14.)
